Generated by pacms.orera.in on date: 2024-07-22

Promoter Details
Promoter Name :
TAPAS KUMAR
Project Name :
GALAXY ENCLAVE
Project Location :
(Residential Project, S+4 Residential Apartment, No. of Units- 12)

Form- I

A. Promoter's Details

:  M/S. MAA SANTOSHI ENGINEERS PVT. LTD :  Private Company
:  U45201OR2010PTC012594 :View
NA :  Plot No. 59/2919, Udaygiri Vihar, Patrapara, Bhubaneswar-751019, Dist. Khordha, Odisha
:  Plot No.- 59/2919, Udaygiri Vihar, Patrapara, Bhubaneswar, Dist- Khordha, Odisha- 751019. :  msengineers2009@yahoo.com
:  9438204580
:  AAHCM2722M :View
:  8 YEARS OF EXPERIENCE IN REAL ESTATE :  NA
NA

B. Details of Board of Directors / Partners / MC Members

:  TAPAS KUMAR :  
:  Managing Director :  BCHPK8221K
:PAN Card :  tapas3691@gmail.com
:  B.TECH :  9438204580
:  14 YEARS OF EXPERIENCE
:  Yes :  NA
:  PRATAP SEN SWAIN :  
:  Director :  AQPPS3126C
:PAN Card :  msengineers2009@yahoo.com
:  GRADUATION :  7681099308
:  13 YEARS OF EXPERIENCE
:  Yes :  NA
:  SUSANTA KUMAR MISHRA :  
:  Director :  BBQPM4359G
:PAN Card :  msengineers2009@yahoo.com
:  GRADUATION :  9238509809
:  13 YEARS OF EXPERIENCE
:  Yes :  NA

Annexure-1

Details of last projects already implemented (Ongoing or Complete)

1. :  Shanti residency :  Residential
:  patrapada :  Ongoing
:  RP/19/2021/00542 NA
:  Joint Venture
:  S+4 NA NA :  S+4
:  No

:   :  
:   :  
:  
: No :  NA
: No :  NA
2. :  GALAXY ENCLAVE :  Residential
:  BHAGBANPUR :  Ongoing
:  RP/19/2021/00541 NA
:  Joint Venture
:  Residential Project, S+4 NA NA :  Residential Project, S+4
:  No

:   :  
:   :  
:  
: No :  NA
: No :  NA

Annexure-2

Details of the project to be registered

:   New :  GALAXY ENCLAVE
:  Residential :  (Residential Project, S+4 Residential Apartment, No. of Units- 12)
:  Khordha :  Bhubaneswar
:  751019 :  Development Authority
:  BHUBANESWAR DEVELOPMENT AUTHORITY
:  S+4 STORIED RESIDENTIAL APARTMENT :  NA

Land Details of the Project


:  105 :  668/315
:  BHAGBANPUR :  283.38
:  Yes
No :  View
:  View :  View
:  Other Person
:  TARINI PRASAD MISHRA :  LAND OWNER EXECUTED DEVELOPMENT AGREEMENT WITH PROMOTER AND ALSO THE PROMOTER IS REGISTERED POWER HOLDER OVER THE LAND.
: No
: Yes
:  11131406828 :  18-11-2014
:  SUB REGISTRAR, KHANDAGIRI :  Attached

:  104 :  668/361
:  BHAGBANPUR :  283.38
:  Yes
No :  View
:  View :  View
:  Other Person
:  BHABANI PRASAD MISHRA :  LAND OWNER EXECUTED DEVELOPMENT AGREEMENT WITH PROMOTER AND ALSO THE PROMOTER IS REGISTERED POWER HOLDER OVER THE LAND.
: No
: Yes
:  11131406829 :  18-11-2014
:  SUB REGISTRAR, KHANDAGIRI :  Attached

Development Agreement

: Yes
Serial No. Particulars of the Person Land/Plot Details Share of the Person Document Attached
1 TARINI PRASAD MISHRA PLOT NO.105 KHATA NO.668/315 40 %   Agreement Copy
2 BHABANI PRASAD MISHRA PLOT NO.104 KHATA NO.668/361 40 %   Agreement Copy

Building Plan

  View   View
  Download site plan 21-11-2025

Conditions of building plan approval

Sl. No. Description of Conditions Schedule date of compliance Present Status
1 PARKING SPACE MEASURING 297.31 SQM (STILT FLOOR) AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE. 21-11-2025 IN PROGRESS
2 THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 12.20 MTR IN WIDTH. 21-11-2025 IN PROGRESS
3 PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS. 21-11-2025 IN PROGRESS
4 OBTAIN WHEREEVER APPLICABLE FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK. 21-11-2025 IN PROGRESS
5 OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART. 21-11-2025 IN PROGRESS
6 ENSURE COMPLIANCE OF PROVISION OF VARIOUS ACTS, RULES, REGULATIONS AND CODES WHICH CONTROL OR PROVIDE FOR VARIOUS NORMS GOVERNING DEVELOPMENT INCLUDING BUT NOT LIMITED TO PLANNING NORMS FIRE SAFTEY ENVIRONMENTAL NORMS AS APPLICABLE IN EACH CASE. 21-11-2025 IN PROGRESS
7 WHEREEVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY. 21-11-2025 IN PROGRESS
8 STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE-47 OF ODA (PLANNING & BUILDING STANDARDS) RULES 2020. 21-11-2025 IN PROGRESS
9 THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED /CLOSED IN ANY MANNER. 21-11-2025 IN PROGRESS
10 AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER RULE 37 OF ODA (P&BS) RULES 2020. 21-11-2025 IN PROGRESS
11 AT LEAST 50% OF THE OPEN SPACE SHALL BE PREVIOUS AND PLANTATION @ ONE TREE PER 80 SQM OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES,2020. 21-11-2025 IN PROGRESS
12 RAIN WATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER. 21-11-2025 IN PROGRESS
13 GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA. 21-11-2025 IN PROGRESS
14 ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FOR ABSORPTION OF RAIN WATER AND SEEPAGE IN TO THE GROUND. 21-11-2025 IN PROGRESS
15 HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR SPACE PER FLAT SHALL BE PROIVDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN 12 SQUARE METERS. 21-11-2025 IN PROGRESS
16 THE BUILDING SHALL NOT BE PUT TO ANY USE OTHER THAN THE PURPOSE FOR WHICH THE PERMISSION IS ACCORDED. 21-11-2025 IN PROGRESS
17 ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS) RULES 2020. 21-11-2025 IN PROGRESS
18 THE APPLICANT SHALL PROVIDE MICRO-COMPOSTING SITE/PLANT WITHIN THE PROJECT PREMISES TO MAKE OWN ARRANGEMENT OF SOLID WASTE MANAGEMENT. 21-11-2025 IN PROGRESS
19 THE OWNER/APPLICANT/TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/ CLEARANCE OF PUBLIC HEALTH ENGINEERING DIVISION (PHED) VIDE LETTER NO.13108 ON DT.25.06.2015, NOC FROM BMC VIDE LETTER NO.9111 DATED.28.05.2016,NOC CGWA VIDE LETTER NO.CGWA/NOC/INF/ORIG/2020/7414 DATED 17.02.2020, NOC FROM CESU VIDE LETTER NO.7002(4) DATED 27.05.2020. 21-11-2025 IN PROGRESS
20 ALL THE FIRE FIGHTING INSTALLATION ETC ARE TO BE ENSURED AND MAINTAINED BY THE APPLICANT AS PER NBC-2016. 21-11-2025 IN PROGRESS
21 NO STORM WATER/WATER SHALL BE DISCHARGED TO THE PUBLIC ROAD/PUBLIC PREMISES AND OTHER ADJOINING PLOTS. 21-11-2025 NOT STARTED
22 ADHERE TO THE PROVISIONS OF ODA (PLANNING & BUILDING STANDARDS) RULES 2020 STRICTLY AND CONDITIONS THERETO. 21-11-2025 NOT STARTED
23 THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER. 21-11-2025 IN PROGRESS
24 THE APPLICANT ON ITS OWN COST SHALL DEVELOP THE EXISTING APPROACH ROAD WITH BLACK TO PUP TO THE PROJECT SITE BOOUNDARY. 21-11-2025 NOT STARTED
25 THE APPLICANT DURING THE COURSE OF CONSTRUCTION AND TILL ISSUE OF OCCUPANCY CERTIFICATE SHALL KEEP PASTED IN A CONSPICUOUS PLACE A COPY OF THE BUILDING PERMIT AND COPY OF APPROVED DRAWING AND SHALL PLACE A DISPLAY BOARD ON SITE WITH DETAILS AND DECLARATION AS GIVEN AT ANNEXURE-I. 21-11-2025 NOT STARTED

Layout Plan

: Yes :  View

Location Map with geo-coordinates of bend points

Point No. Latitude Longitude
1 20°14'14.2"N 85°45'33.4"E
2 20°14'14.1"N 85°45'33.9"E
3 20°14'14.0"N 85°45'34.4"E
4 20°14'13.4"N 85°45'34.3"E
5 20°14'13.5"N 85°45'33.8"E
6 20°14'13.5"N 85°45'33.3"E
View

Milestone of Project Construction

Description* Scheduled date of completion Current Status Site Images
Site Development 13-02-2019 COMPLETED
Roof Casting NA NA NA
Ground Floor/Stilt Floor 30-06-2019 COMPLETED
1 Floor 30-09-2019 COMPLETED
2 Floor 31-12-2019 COMPLETED
3 Floor 31-03-2020 COMPLETED
4 Floor 31-07-2020 COMPLETED
Brick Work & Plastering NA NA NA
Ground Floor/Stilt Floor 31-07-2020 COMPLETED
1 Floor 30-09-2020 COMPLETED
2 Floor 30-11-2020 COMPLETED
3 Floor 31-01-2021 COMPLETED
4 Floor 31-03-2021 COMPLETED
Electrical Works 31-01-2022 IN PROGRESS NA
Concealed Cabling including Plugs & switches 31-01-2022 IN PROGRESS NA
Installation & Charging of Transformer 31-01-2022 IN PROGRESS NA
Connection to Flats/Apartments 31-01-2022 IN PROGRESS NA
PH works 30-06-2022 IN PROGRESS NA
Laying of concealed Pipes 30-06-2022 IN PROGRESS NA
PH Fittings 30-06-2022 IN PROGRESS NA
Overhead Water Tanks 30-06-2022 IN PROGRESS NA
Water Supply Connection to all units 30-06-2022 IN PROGRESS NA
STP construction and completion 30-06-2022 IN PROGRESS NA
Distempering & Colouring of all units and exteriors 30-09-2022 IN PROGRESS NA
Fixation of doors and windows 31-01-2023 NOT STARTED NA
Scheduled Date of handing over possession 31-05-2023 NOT STARTED NA
Development of common areas, parks, gardens etc 30-04-2023 NOT STARTED NA
Site Development 13-02-2019 COMPLETED NA
NA NA NA NA
Ground Floor/Stilt Floor 30-06-2019 COMPLETED NA
1 Floor 30-09-2019 COMPLETED NA
2 Floor 31-12-2019 COMPLETED NA
3 Floor 31-03-2020 COMPLETED NA
4 Floor 31-07-2020 COMPLETED NA
NA NA NA NA
Ground Floor/Stilt Floor 31-07-2020 COMPLETED NA
1 Floor 30-09-2020 COMPLETED NA
2 Floor 30-11-2020 COMPLETED NA
3 Floor 31-01-2021 COMPLETED NA
4 Floor 31-03-2021 COMPLETED NA
Electrical Works 31-01-2022 IN PROGRESS NA
Concealed Cabling including Plugs & switches 31-01-2022 IN PROGRESS NA
Installation & Charging of Transformer 31-01-2022 IN PROGRESS NA
Connection to Flats/Apartments 31-01-2022 IN PROGRESS NA
PH works 30-06-2022 IN PROGRESS NA
Laying of concealed Pipes 30-06-2022 IN PROGRESS NA
PH Fittings 30-06-2022 IN PROGRESS NA
Overhead Water Tanks 30-06-2022 IN PROGRESS NA
Water Supply Connection to all units 30-06-2022 IN PROGRESS NA
STP construction and completion 30-06-2022 IN PROGRESS NA
Distempering & Colouring of all units and exteriors 30-09-2022 IN PROGRESS NA
Fixation of doors and windows 31-01-2023 NOT STARTED NA
Scheduled Date of handing over possession 31-05-2023 NOT STARTED NA
Development of common areas, parks, gardens etc 30-04-2023 NOT STARTED NA
Site Development 13-02-2019 COMPLETED NA
NA NA NA NA
Ground Floor/Stilt Floor 30-06-2019 COMPLETED NA
1 Floor 30-09-2019 COMPLETED NA
2 Floor 31-12-2019 COMPLETED NA
3 Floor 31-03-2020 COMPLETED NA
4 Floor 31-07-2020 COMPLETED NA
NA NA NA NA
Ground Floor/Stilt Floor 31-07-2020 COMPLETED NA
1 Floor 30-09-2020 COMPLETED NA
2 Floor 30-11-2020 COMPLETED NA
3 Floor 31-01-2021 COMPLETED NA
4 Floor 31-03-2021 COMPLETED NA
Electrical Works 31-01-2022 IN PROGRESS NA
Concealed Cabling including Plugs & switches 31-01-2022 COMPLETED NA
Installation & Charging of Transformer 31-01-2022 IN PROGRESS NA
Connection to Flats/Apartments 31-01-2022 IN PROGRESS NA
PH works 30-06-2022 IN PROGRESS NA
Laying of concealed Pipes 30-06-2022 COMPLETED NA
PH Fittings 30-06-2022 IN PROGRESS NA
Overhead Water Tanks 30-06-2022 IN PROGRESS NA
Water Supply Connection to all units 30-06-2022 IN PROGRESS NA
STP construction and completion 30-06-2022 IN PROGRESS NA
Distempering & Colouring of all units and exteriors 30-09-2022 IN PROGRESS NA
Fixation of doors and windows 31-01-2023 NOT STARTED NA
Scheduled Date of handing over possession 31-05-2023 NOT STARTED NA
Development of common areas, parks, gardens etc 30-04-2023 NOT STARTED NA
Site Development 13-02-2019 COMPLETED NA
NA NA NA NA
Ground Floor/Stilt Floor 30-06-2019 COMPLETED NA
1 Floor 30-09-2019 COMPLETED NA
2 Floor 31-12-2019 COMPLETED NA
3 Floor 31-03-2020 COMPLETED NA
4 Floor 31-07-2020 COMPLETED NA
NA NA NA NA
Ground Floor/Stilt Floor 31-07-2020 COMPLETED NA
1 Floor 30-09-2020 COMPLETED NA
2 Floor 30-11-2020 COMPLETED NA
3 Floor 31-01-2021 COMPLETED NA
4 Floor 31-03-2021 COMPLETED NA
Electrical Works 31-01-2022 IN PROGRESS NA
Concealed Cabling including Plugs & switches 31-01-2022 COMPLETED NA
Installation & Charging of Transformer 31-01-2022 IN PROGRESS NA
Connection to Flats/Apartments 31-01-2022 IN PROGRESS NA
PH works 30-06-2022 IN PROGRESS NA
Laying of concealed Pipes 30-06-2022 COMPLETED NA
PH Fittings 30-06-2022 IN PROGRESS NA
Overhead Water Tanks 30-06-2022 IN PROGRESS NA
Water Supply Connection to all units 30-06-2022 IN PROGRESS NA
STP construction and completion 30-06-2022 IN PROGRESS NA
Distempering & Colouring of all units and exteriors 30-09-2022 IN PROGRESS NA
Fixation of doors and windows 31-01-2023 NOT STARTED NA
Scheduled Date of handing over possession 31-05-2023 NOT STARTED NA
Development of common areas, parks, gardens etc 30-04-2023 NOT STARTED NA
Site Development 13-02-2019 COMPLETED NA
NA 13-02-2019 COMPLETED NA
Ground Floor/Stilt Floor 30-06-2019 COMPLETED NA
1 Floor 30-09-2019 COMPLETED NA
2 Floor 31-12-2019 COMPLETED NA
3 Floor 31-03-2020 COMPLETED NA
4 Floor 31-07-2020 COMPLETED NA
NA 31-07-2020 COMPLETED NA
Ground Floor/Stilt Floor 31-07-2020 COMPLETED NA
1 Floor 30-09-2020 COMPLETED NA
2 Floor 30-11-2020 COMPLETED NA
3 Floor 31-01-2021 COMPLETED NA
4 Floor 31-03-2021 COMPLETED NA
Electrical Works 31-01-2022 IN PROGRESS NA
Concealed Cabling including Plugs & switches 31-01-2022 COMPLETED NA
Installation & Charging of Transformer 31-01-2022 IN PROGRESS NA
Connection to Flats/Apartments 31-01-2022 IN PROGRESS NA
PH works 30-06-2022 IN PROGRESS NA
Laying of concealed Pipes 30-06-2022 COMPLETED NA
PH Fittings 30-06-2022 IN PROGRESS NA
Overhead Water Tanks 30-06-2022 IN PROGRESS NA
Water Supply Connection to all units 30-06-2022 IN PROGRESS NA
STP construction and completion 30-06-2022 IN PROGRESS NA
Distempering & Colouring of all units and exteriors 30-09-2022 IN PROGRESS NA
Fixation of doors and windows 31-01-2023 IN PROGRESS NA
Scheduled Date of handing over possession 31-05-2023 NOT STARTED NA
Development of common areas, parks, gardens etc 30-04-2023 NOT STARTED NA
Site Development 13-02-2019 COMPLETED NA
NA 13-02-2019 COMPLETED NA
Ground Floor/Stilt Floor 30-06-2019 COMPLETED NA
1 Floor 30-09-2019 COMPLETED NA
2 Floor 31-12-2019 COMPLETED NA
3 Floor 31-03-2020 COMPLETED NA
4 Floor 31-07-2020 COMPLETED NA
NA 31-07-2020 COMPLETED NA
Ground Floor/Stilt Floor 31-07-2020 COMPLETED NA
1 Floor 30-09-2020 COMPLETED NA
2 Floor 30-11-2020 COMPLETED NA
3 Floor 31-01-2021 COMPLETED NA
4 Floor 31-03-2021 COMPLETED NA
Electrical Works 31-01-2022 IN PROGRESS NA
Concealed Cabling including Plugs & switches 31-01-2022 COMPLETED NA
Installation & Charging of Transformer 31-01-2022 IN PROGRESS NA
Connection to Flats/Apartments 31-01-2022 IN PROGRESS NA
PH works 30-06-2022 IN PROGRESS NA
Laying of concealed Pipes 30-06-2022 COMPLETED NA
PH Fittings 30-06-2022 IN PROGRESS NA
Overhead Water Tanks 30-06-2022 IN PROGRESS NA
Water Supply Connection to all units 30-06-2022 IN PROGRESS NA
STP construction and completion 30-06-2022 IN PROGRESS NA
Distempering & Colouring of all units and exteriors 30-09-2022 IN PROGRESS NA
Fixation of doors and windows 31-01-2023 IN PROGRESS NA
Scheduled Date of handing over possession 31-05-2023 NOT STARTED NA
Development of common areas, parks, gardens etc 30-04-2023 NOT STARTED NA
Site Development 13-02-2019 COMPLETED NA
NA 13-02-2019 COMPLETED NA
Ground Floor/Stilt Floor 30-06-2019 COMPLETED NA
1 Floor 30-09-2019 COMPLETED NA
2 Floor 31-12-2019 COMPLETED NA
3 Floor 31-03-2020 COMPLETED NA
4 Floor 31-07-2020 COMPLETED NA
NA 31-07-2020 COMPLETED NA
Ground Floor/Stilt Floor 31-07-2020 COMPLETED NA
1 Floor 30-09-2020 COMPLETED NA
2 Floor 30-11-2020 COMPLETED NA
3 Floor 31-01-2021 COMPLETED NA
4 Floor 31-03-2021 COMPLETED NA
Electrical Works 31-01-2022 IN PROGRESS NA
Concealed Cabling including Plugs & switches 31-01-2022 COMPLETED NA
Installation & Charging of Transformer 31-01-2022 IN PROGRESS NA
Connection to Flats/Apartments 31-01-2022 IN PROGRESS NA
PH works 30-06-2022 IN PROGRESS NA
Laying of concealed Pipes 30-06-2022 COMPLETED NA
PH Fittings 30-06-2022 IN PROGRESS NA
Overhead Water Tanks 30-06-2022 IN PROGRESS NA
Water Supply Connection to all units 30-06-2022 IN PROGRESS NA
STP construction and completion 30-06-2022 IN PROGRESS NA
Distempering & Colouring of all units and exteriors 30-09-2022 IN PROGRESS NA
Fixation of doors and windows 31-01-2023 IN PROGRESS NA
Scheduled Date of handing over possession 31-05-2023 NOT STARTED NA
Development of common areas, parks, gardens etc 30-04-2023 NOT STARTED NA

Category and no. of units to be developed

:  Residential
:  
:  12
:  
:  
:  
Residential Flats/ House
S. No. Flat No./ House No.

Area in square metres

Ownership
Carpet Area Balcony Area Exclusive Open Terrace Area
1 101 74.60 8.00 0 Promoter
2 102 72.00 8.90 0 Promoter
3 103 100.20 12.20 0 Promoter
4 201 74.60 8.00 0 Land Owner
5 202 72.00 8.90 0 Promoter
6 203 100.20 12.20 0 Land Owner
7 301 74.60 8.00 0 Land Owner
8 302 72.00 8.90 0 Promoter
9 303 100.20 12.20 0 Land Owner
10 401 63.56 8.00 0 Promoter
11 402 72.00 8.90 0 Promoter
12 403 100.20 12.20 0 Promoter
Types of garages and parking
House No. Type of Garage/ Parking allotted Serial No., if any Dimension (Length x Width) in Metres Floor area in sq. metres Garage/Parking area cost is included or additional
101 Covered Parking 1 4.57 M x 2.49 M 11.40 SQM Included
102 Covered Parking 2 4.57 M x 2.49 M 11.40 SQM Included
103 Covered Parking 3 4.57 M x 3.24 M 14.80 SQM Included
201 Covered Parking 4 4.57 M x 3.46 M 15.80 SQM Included
202 Covered Parking 5 4.57 M x 2.04 M 9.30 SQM Included
203 Covered Parking 6 4.57 M x 2.04 M 9.30 SQM Included
301 Covered Parking 7 4.57 M x 3.29 M 15.00 SQM Included
302 Covered Parking 8 5.32 M x 3.24 M 17.30 SQM Included
303 Covered Parking 9 5.32 M x 3.46 M 18.40 SQM Included
401 Covered Parking 10 5.32 M x 3.47 M 18.50 SQM Included
402 Covered Parking 11 4.00 M x 2.66 M 11.30 SQM Included
403 Covered Parking 12 4.00 M x 2.66 M 11.30 SQM Included
Yes

Facilities to be provided

Particulars of Facilities Status of the facility Brief description of facility
Drinking Water Facility Ground Water Copy of Consent Letter
Fire Fighting Facility No
Emergency Evacuation Services Yes STAIRCASE
Use of Renewable Energy No
Lift Facility Yes 1 NO. OF LIFT OF JHONSON/OTIS/ETC BRAND OF 6 PASSENGER CAPACITY WITH ARD FACILITY
Market Complex No
Community Hall Yes 12.04 SQM COMMUNITY HALL WITH FAN
Gymnasium No
Swimming Pool No
Play Ground No
Park/Garden No
Plantation Area Yes 64.00 SQM
Others(Please Specify) No
Internal Road Yes 3.63 MTR WIDE & 87.15 MTR LENGTH INTERNAL ROAD WITH CONCRETE FLOORING
External Road Yes 12.20 MTR WIDE EXTERNAL ROAD ADJACENT TO PROJECT PLOT
Elecricity Supply Yes Copy of Consent Letter
Other Amenities No

Bank Particulars of the Project

  ICICI BANK
  Nayapalli
  028405008682
  ICICOO00284
   View
  2362006
  7894450610

Particulars of Architect/Construction Engineer/Contractor/Chartered Accountant

Name position Address with mobile number and email address Registration number Key real estate projects Is active Effective date
RUPAK PANDA Architect PLOT NO-491/2,SAHEEDNAGAR,BBSR-7.MOB-9437008609.MAIL-office@rpassociates.in CA/96/20438 NA
Er.Pitabas Panda Construction Engineer 491/2, Sahid Nagar, Bhubaneswar- 751007, Email-rupak@rpassociates.in,Mob-9437017543 RTP/DTP(ST.ER)-155/2019 NA
NIRANJAN MISHRA Chartered Accountant PLOT NO-214/1342,BEHIND ANDHRA BANK,LAXMISAGAR CHHAK,,BHUBANESWAR-751006.MAIL-caniranjan123@gmail.com,MOB-9438311800 M.NO-302454 NA

Financial Details

:  364.67124 :   View
  21-11-2025 :  200
:  164.67124 :  0

Documents Attached

Description of Document Option Documents
Fire Safety Certificate Undertaking Attached
Affidavit in Form-A as per clause-l of sub-section-2 of section-4 of the Act Yes Attached
Allotment letter format Yes Attached
Conveyance Deed Format Yes Attached
Affidavit to adopt agreement for sale format as per Rule-8(1) of ORE (R and D) Rules, 2017 Yes Attached
Annual Report 2020-21 Attached
Annual Report 2021-22 Attached
Annual Report 2022-23 Attached
IT Return 2020-21 Attached
IT Return 2021-22 Attached
IT Return 2022-23 Attached
Audit Report 2020-21 Attached
Audit Report 2021-22 Attached
Audit Report 2022-23 Attached

Additional Documents Attached

Sl. No. Title of the document Upload Document
1 AUTHORISATION
2 2/3rd consent of allottees
3 CLARIFICATION ON BUILDING PLAN & APPROVAL LETTER

Other documents

“I undertake that the information submitted by me in this application are correct and true to best my knowledge. I also understand that providing false or wrong information is punishable under the Section-60 of the Real Estate (Regulation & Development) Act, 2016. I also further understand that furnishing wrong or false information will lead to rejection of my application registration of the project with forfeiture of registration fee and other charges deposited by me.”
  

Construction Progress

Updated Construction Progress

SL NO. Description Scheduled date of completion Current Status Remarks
1 Site Development 13-02-2019 COMPLETED
2 Roof Casting NA NA NA
3 Ground Floor/Stilt Floor 30-06-2019 COMPLETED
4 1 Floor 30-09-2019 COMPLETED
5 2 Floor 31-12-2019 COMPLETED
6 3 Floor 31-03-2020 COMPLETED
7 4 Floor 31-07-2020 COMPLETED
8 Brick Work & Plastering NA NA NA
9 Ground Floor/Stilt Floor 31-07-2020 COMPLETED
10 1 Floor 30-09-2020 COMPLETED
11 2 Floor 30-11-2020 COMPLETED
12 3 Floor 31-01-2021 COMPLETED
13 4 Floor 31-03-2021 COMPLETED
14 Electrical Works 31-01-2022 IN PROGRESS NA
15 Concealed Cabling including Plugs & switches 31-01-2022 IN PROGRESS NA
16 Installation & Charging of Transformer 31-01-2022 IN PROGRESS NA
17 Connection to Flats/Apartments 31-01-2022 IN PROGRESS NA
18 PH works 30-06-2022 IN PROGRESS NA
19 Laying of concealed Pipes 30-06-2022 IN PROGRESS NA
20 PH Fittings 30-06-2022 IN PROGRESS NA
21 Overhead Water Tanks 30-06-2022 IN PROGRESS NA
22 Water Supply Connection to all units 30-06-2022 IN PROGRESS NA
23 STP construction and completion 30-06-2022 IN PROGRESS NA
24 Distempering & Colouring of all units and exteriors 30-09-2022 IN PROGRESS NA
25 Fixation of doors and windows 31-01-2023 NOT STARTED NA
26 Scheduled Date of handing over possession 31-05-2023 NOT STARTED NA
27 Development of common areas, parks, gardens etc 30-04-2023 NOT STARTED NA
Updated Changes on 15-07-2023
28 Site Development 13-02-2019 COMPLETED NA
29 NA NA NA NA
30 Ground Floor/Stilt Floor 30-06-2019 COMPLETED NA
31 1 Floor 30-09-2019 COMPLETED NA
32 2 Floor 31-12-2019 COMPLETED NA
33 3 Floor 31-03-2020 COMPLETED NA
34 4 Floor 31-07-2020 COMPLETED NA
35 NA NA NA NA
36 Ground Floor/Stilt Floor 31-07-2020 COMPLETED NA
37 1 Floor 30-09-2020 COMPLETED NA
38 2 Floor 30-11-2020 COMPLETED NA
39 3 Floor 31-01-2021 COMPLETED NA
40 4 Floor 31-03-2021 COMPLETED NA
41 Electrical Works 31-01-2022 IN PROGRESS NA
42 Concealed Cabling including Plugs & switches 31-01-2022 IN PROGRESS NA
43 Installation & Charging of Transformer 31-01-2022 IN PROGRESS NA
44 Connection to Flats/Apartments 31-01-2022 IN PROGRESS NA
45 PH works 30-06-2022 IN PROGRESS NA
46 Laying of concealed Pipes 30-06-2022 IN PROGRESS NA
47 PH Fittings 30-06-2022 IN PROGRESS NA
48 Overhead Water Tanks 30-06-2022 IN PROGRESS NA
49 Water Supply Connection to all units 30-06-2022 IN PROGRESS NA
50 STP construction and completion 30-06-2022 IN PROGRESS NA
51 Distempering & Colouring of all units and exteriors 30-09-2022 IN PROGRESS NA
52 Fixation of doors and windows 31-01-2023 NOT STARTED NA
53 Scheduled Date of handing over possession 31-05-2023 NOT STARTED NA
54 Development of common areas, parks, gardens etc 30-04-2023 NOT STARTED NA
Updated Changes on 14-10-2023
55 Site Development 13-02-2019 COMPLETED NA
56 NA NA NA NA
57 Ground Floor/Stilt Floor 30-06-2019 COMPLETED NA
58 1 Floor 30-09-2019 COMPLETED NA
59 2 Floor 31-12-2019 COMPLETED NA
60 3 Floor 31-03-2020 COMPLETED NA
61 4 Floor 31-07-2020 COMPLETED NA
62 NA NA NA NA
63 Ground Floor/Stilt Floor 31-07-2020 COMPLETED NA
64 1 Floor 30-09-2020 COMPLETED NA
65 2 Floor 30-11-2020 COMPLETED NA
66 3 Floor 31-01-2021 COMPLETED NA
67 4 Floor 31-03-2021 COMPLETED NA
68 Electrical Works 31-01-2022 IN PROGRESS NA
69 Concealed Cabling including Plugs & switches 31-01-2022 COMPLETED NA
70 Installation & Charging of Transformer 31-01-2022 IN PROGRESS NA
71 Connection to Flats/Apartments 31-01-2022 IN PROGRESS NA
72 PH works 30-06-2022 IN PROGRESS NA
73 Laying of concealed Pipes 30-06-2022 COMPLETED NA
74 PH Fittings 30-06-2022 IN PROGRESS NA
75 Overhead Water Tanks 30-06-2022 IN PROGRESS NA
76 Water Supply Connection to all units 30-06-2022 IN PROGRESS NA
77 STP construction and completion 30-06-2022 IN PROGRESS NA
78 Distempering & Colouring of all units and exteriors 30-09-2022 IN PROGRESS NA
79 Fixation of doors and windows 31-01-2023 NOT STARTED NA
80 Scheduled Date of handing over possession 31-05-2023 NOT STARTED NA
81 Development of common areas, parks, gardens etc 30-04-2023 NOT STARTED NA
Updated Changes on 15-01-2024
82 Site Development 13-02-2019 COMPLETED NA
83 NA NA NA NA
84 Ground Floor/Stilt Floor 30-06-2019 COMPLETED NA
85 1 Floor 30-09-2019 COMPLETED NA
86 2 Floor 31-12-2019 COMPLETED NA
87 3 Floor 31-03-2020 COMPLETED NA
88 4 Floor 31-07-2020 COMPLETED NA
89 NA NA NA NA
90 Ground Floor/Stilt Floor 31-07-2020 COMPLETED NA
91 1 Floor 30-09-2020 COMPLETED NA
92 2 Floor 30-11-2020 COMPLETED NA
93 3 Floor 31-01-2021 COMPLETED NA
94 4 Floor 31-03-2021 COMPLETED NA
95 Electrical Works 31-01-2022 IN PROGRESS NA
96 Concealed Cabling including Plugs & switches 31-01-2022 COMPLETED NA
97 Installation & Charging of Transformer 31-01-2022 IN PROGRESS NA
98 Connection to Flats/Apartments 31-01-2022 IN PROGRESS NA
99 PH works 30-06-2022 IN PROGRESS NA
100 Laying of concealed Pipes 30-06-2022 COMPLETED NA
101 PH Fittings 30-06-2022 IN PROGRESS NA
102 Overhead Water Tanks 30-06-2022 IN PROGRESS NA
103 Water Supply Connection to all units 30-06-2022 IN PROGRESS NA
104 STP construction and completion 30-06-2022 IN PROGRESS NA
105 Distempering & Colouring of all units and exteriors 30-09-2022 IN PROGRESS NA
106 Fixation of doors and windows 31-01-2023 NOT STARTED NA
107 Scheduled Date of handing over possession 31-05-2023 NOT STARTED NA
108 Development of common areas, parks, gardens etc 30-04-2023 NOT STARTED NA
Updated Changes on 15-04-2024
109 Site Development 13-02-2019 COMPLETED NA
110 NA 13-02-2019 COMPLETED NA
111 Ground Floor/Stilt Floor 30-06-2019 COMPLETED NA
112 1 Floor 30-09-2019 COMPLETED NA
113 2 Floor 31-12-2019 COMPLETED NA
114 3 Floor 31-03-2020 COMPLETED NA
115 4 Floor 31-07-2020 COMPLETED NA
116 NA 31-07-2020 COMPLETED NA
117 Ground Floor/Stilt Floor 31-07-2020 COMPLETED NA
118 1 Floor 30-09-2020 COMPLETED NA
119 2 Floor 30-11-2020 COMPLETED NA
120 3 Floor 31-01-2021 COMPLETED NA
121 4 Floor 31-03-2021 COMPLETED NA
122 Electrical Works 31-01-2022 IN PROGRESS NA
123 Concealed Cabling including Plugs & switches 31-01-2022 COMPLETED NA
124 Installation & Charging of Transformer 31-01-2022 IN PROGRESS NA
125 Connection to Flats/Apartments 31-01-2022 IN PROGRESS NA
126 PH works 30-06-2022 IN PROGRESS NA
127 Laying of concealed Pipes 30-06-2022 COMPLETED NA
128 PH Fittings 30-06-2022 IN PROGRESS NA
129 Overhead Water Tanks 30-06-2022 IN PROGRESS NA
130 Water Supply Connection to all units 30-06-2022 IN PROGRESS NA
131 STP construction and completion 30-06-2022 IN PROGRESS NA
132 Distempering & Colouring of all units and exteriors 30-09-2022 IN PROGRESS NA
133 Fixation of doors and windows 31-01-2023 IN PROGRESS NA
134 Scheduled Date of handing over possession 31-05-2023 NOT STARTED NA
135 Development of common areas, parks, gardens etc 30-04-2023 NOT STARTED NA
Updated Changes on 14-07-2024
136 Site Development 13-02-2019 COMPLETED NA
137 NA 13-02-2019 COMPLETED NA
138 Ground Floor/Stilt Floor 30-06-2019 COMPLETED NA
139 1 Floor 30-09-2019 COMPLETED NA
140 2 Floor 31-12-2019 COMPLETED NA
141 3 Floor 31-03-2020 COMPLETED NA
142 4 Floor 31-07-2020 COMPLETED NA
143 NA 31-07-2020 COMPLETED NA
144 Ground Floor/Stilt Floor 31-07-2020 COMPLETED NA
145 1 Floor 30-09-2020 COMPLETED NA
146 2 Floor 30-11-2020 COMPLETED NA
147 3 Floor 31-01-2021 COMPLETED NA
148 4 Floor 31-03-2021 COMPLETED NA
149 Electrical Works 31-01-2022 IN PROGRESS NA
150 Concealed Cabling including Plugs & switches 31-01-2022 COMPLETED NA
151 Installation & Charging of Transformer 31-01-2022 IN PROGRESS NA
152 Connection to Flats/Apartments 31-01-2022 IN PROGRESS NA
153 PH works 30-06-2022 IN PROGRESS NA
154 Laying of concealed Pipes 30-06-2022 COMPLETED NA
155 PH Fittings 30-06-2022 IN PROGRESS NA
156 Overhead Water Tanks 30-06-2022 IN PROGRESS NA
157 Water Supply Connection to all units 30-06-2022 IN PROGRESS NA
158 STP construction and completion 30-06-2022 IN PROGRESS NA
159 Distempering & Colouring of all units and exteriors 30-09-2022 IN PROGRESS NA
160 Fixation of doors and windows 31-01-2023 IN PROGRESS NA
161 Scheduled Date of handing over possession 31-05-2023 NOT STARTED NA
162 Development of common areas, parks, gardens etc 30-04-2023 NOT STARTED NA
Updated Changes on 14-07-2024
163 Site Development 13-02-2019 COMPLETED NA
164 NA 13-02-2019 COMPLETED NA
165 Ground Floor/Stilt Floor 30-06-2019 COMPLETED NA
166 1 Floor 30-09-2019 COMPLETED NA
167 2 Floor 31-12-2019 COMPLETED NA
168 3 Floor 31-03-2020 COMPLETED NA
169 4 Floor 31-07-2020 COMPLETED NA
170 NA 31-07-2020 COMPLETED NA
171 Ground Floor/Stilt Floor 31-07-2020 COMPLETED NA
172 1 Floor 30-09-2020 COMPLETED NA
173 2 Floor 30-11-2020 COMPLETED NA
174 3 Floor 31-01-2021 COMPLETED NA
175 4 Floor 31-03-2021 COMPLETED NA
176 Electrical Works 31-01-2022 IN PROGRESS NA
177 Concealed Cabling including Plugs & switches 31-01-2022 COMPLETED NA
178 Installation & Charging of Transformer 31-01-2022 IN PROGRESS NA
179 Connection to Flats/Apartments 31-01-2022 IN PROGRESS NA
180 PH works 30-06-2022 IN PROGRESS NA
181 Laying of concealed Pipes 30-06-2022 COMPLETED NA
182 PH Fittings 30-06-2022 IN PROGRESS NA
183 Overhead Water Tanks 30-06-2022 IN PROGRESS NA
184 Water Supply Connection to all units 30-06-2022 IN PROGRESS NA
185 STP construction and completion 30-06-2022 IN PROGRESS NA
186 Distempering & Colouring of all units and exteriors 30-09-2022 IN PROGRESS NA
187 Fixation of doors and windows 31-01-2023 IN PROGRESS NA
188 Scheduled Date of handing over possession 31-05-2023 NOT STARTED NA
189 Development of common areas, parks, gardens etc 30-04-2023 NOT STARTED NA

Booking Status

Residential Flats/ House
S. No. Flat No./ House No.

Area in square metres

Ownership Status
Carpet Area Balcony Area Exclusive Open Terrace Area
1 101 74.60 8.00 0 Promoter
2 102 72.00 8.90 0 Promoter
3 103 100.20 12.20 0 Promoter
4 201 74.60 8.00 0 Land Owner
5 202 72.00 8.90 0 Promoter
6 203 100.20 12.20 0 Land Owner
7 301 74.60 8.00 0 Land Owner
8 302 72.00 8.90 0 Promoter
9 303 100.20 12.20 0 Land Owner
10 401 63.56 8.00 0 Promoter
11 402 72.00 8.90 0 Promoter
12 403 100.20 12.20 0 Promoter

Financial Status

SL No. Funds Collected from the Allottees Funds Borrowed from Financial Institutions Funds Employed from Own Sources Expenditure As On Date Status
1 0 0 10500000 10500000 30-06-2023 in progress
2 8500000 0 10500000 12088521 30-09-2023 IN PROGRESS
3 8520000 0 10500000 18455281 31-12-2023 IN PROGRESS
4 0 0 10500000 18492399 31-03-2024 IN PROGRESS
5 13720000 0 10500000 19196429 30-06-2024 IN PROGRESS

Updated Conditions of building plan approval

Sl. No. Description of Conditions Schedule date of compliance Present Status
1 PARKING SPACE MEASURING 297.31 SQM (STILT FLOOR) AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE. 21-11-2025 IN PROGRESS
2 THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 12.20 MTR IN WIDTH. 21-11-2025 IN PROGRESS
3 PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS. 21-11-2025 IN PROGRESS
4 OBTAIN WHEREEVER APPLICABLE FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK. 21-11-2025 IN PROGRESS
5 OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART. 21-11-2025 IN PROGRESS
6 ENSURE COMPLIANCE OF PROVISION OF VARIOUS ACTS, RULES, REGULATIONS AND CODES WHICH CONTROL OR PROVIDE FOR VARIOUS NORMS GOVERNING DEVELOPMENT INCLUDING BUT NOT LIMITED TO PLANNING NORMS FIRE SAFTEY ENVIRONMENTAL NORMS AS APPLICABLE IN EACH CASE. 21-11-2025 IN PROGRESS
7 WHEREEVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY. 21-11-2025 IN PROGRESS
8 STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE-47 OF ODA (PLANNING & BUILDING STANDARDS) RULES 2020. 21-11-2025 IN PROGRESS
9 THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED /CLOSED IN ANY MANNER. 21-11-2025 IN PROGRESS
10 AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER RULE 37 OF ODA (P&BS) RULES 2020. 21-11-2025 IN PROGRESS
11 AT LEAST 50% OF THE OPEN SPACE SHALL BE PREVIOUS AND PLANTATION @ ONE TREE PER 80 SQM OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES,2020. 21-11-2025 IN PROGRESS
12 RAIN WATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER. 21-11-2025 IN PROGRESS
13 GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA. 21-11-2025 IN PROGRESS
14 ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FOR ABSORPTION OF RAIN WATER AND SEEPAGE IN TO THE GROUND. 21-11-2025 IN PROGRESS
15 HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR SPACE PER FLAT SHALL BE PROIVDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN 12 SQUARE METERS. 21-11-2025 IN PROGRESS
16 THE BUILDING SHALL NOT BE PUT TO ANY USE OTHER THAN THE PURPOSE FOR WHICH THE PERMISSION IS ACCORDED. 21-11-2025 IN PROGRESS
17 ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS) RULES 2020. 21-11-2025 IN PROGRESS
18 THE APPLICANT SHALL PROVIDE MICRO-COMPOSTING SITE/PLANT WITHIN THE PROJECT PREMISES TO MAKE OWN ARRANGEMENT OF SOLID WASTE MANAGEMENT. 21-11-2025 IN PROGRESS
19 THE OWNER/APPLICANT/TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/ CLEARANCE OF PUBLIC HEALTH ENGINEERING DIVISION (PHED) VIDE LETTER NO.13108 ON DT.25.06.2015, NOC FROM BMC VIDE LETTER NO.9111 DATED.28.05.2016,NOC CGWA VIDE LETTER NO.CGWA/NOC/INF/ORIG/2020/7414 DATED 17.02.2020, NOC FROM CESU VIDE LETTER NO.7002(4) DATED 27.05.2020. 21-11-2025 IN PROGRESS
20 ALL THE FIRE FIGHTING INSTALLATION ETC ARE TO BE ENSURED AND MAINTAINED BY THE APPLICANT AS PER NBC-2016. 21-11-2025 IN PROGRESS
21 NO STORM WATER/WATER SHALL BE DISCHARGED TO THE PUBLIC ROAD/PUBLIC PREMISES AND OTHER ADJOINING PLOTS. 21-11-2025 NOT STARTED
22 ADHERE TO THE PROVISIONS OF ODA (PLANNING & BUILDING STANDARDS) RULES 2020 STRICTLY AND CONDITIONS THERETO. 21-11-2025 NOT STARTED
23 THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER. 21-11-2025 IN PROGRESS
24 THE APPLICANT ON ITS OWN COST SHALL DEVELOP THE EXISTING APPROACH ROAD WITH BLACK TO PUP TO THE PROJECT SITE BOOUNDARY. 21-11-2025 NOT STARTED
25 THE APPLICANT DURING THE COURSE OF CONSTRUCTION AND TILL ISSUE OF OCCUPANCY CERTIFICATE SHALL KEEP PASTED IN A CONSPICUOUS PLACE A COPY OF THE BUILDING PERMIT AND COPY OF APPROVED DRAWING AND SHALL PLACE A DISPLAY BOARD ON SITE WITH DETAILS AND DECLARATION AS GIVEN AT ANNEXURE-I. 21-11-2025 NOT STARTED
Updated Changes on 15-07-2023
26 PARKING SPACE MEASURING 297.31 SQM (STILT FLOOR) AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE. 21-11-2025 IN PROGRESS
27 THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 12.20 MTR IN WIDTH. 21-11-2025 IN PROGRESS
28 PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS. 21-11-2025 IN PROGRESS
29 OBTAIN WHEREEVER APPLICABLE FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK. 21-11-2025 IN PROGRESS
30 OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART. 21-11-2025 IN PROGRESS
31 ENSURE COMPLIANCE OF PROVISION OF VARIOUS ACTS, RULES, REGULATIONS AND CODES WHICH CONTROL OR PROVIDE FOR VARIOUS NORMS GOVERNING DEVELOPMENT INCLUDING BUT NOT LIMITED TO PLANNING NORMS FIRE SAFTEY ENVIRONMENTAL NORMS AS APPLICABLE IN EACH CASE. 21-11-2025 IN PROGRESS
32 WHEREEVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY. 21-11-2025 IN PROGRESS
33 STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE-47 OF ODA (PLANNING & BUILDING STANDARDS) RULES 2020. 21-11-2025 IN PROGRESS
34 THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED /CLOSED IN ANY MANNER. 21-11-2025 IN PROGRESS
35 AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER RULE 37 OF ODA (P&BS) RULES 2020. 21-11-2025 IN PROGRESS
36 AT LEAST 50% OF THE OPEN SPACE SHALL BE PREVIOUS AND PLANTATION @ ONE TREE PER 80 SQM OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES,2020. 21-11-2025 IN PROGRESS
37 RAIN WATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER. 21-11-2025 IN PROGRESS
38 GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA. 21-11-2025 IN PROGRESS
39 ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FOR ABSORPTION OF RAIN WATER AND SEEPAGE IN TO THE GROUND. 21-11-2025 IN PROGRESS
40 HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR SPACE PER FLAT SHALL BE PROIVDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN 12 SQUARE METERS. 21-11-2025 IN PROGRESS
41 THE BUILDING SHALL NOT BE PUT TO ANY USE OTHER THAN THE PURPOSE FOR WHICH THE PERMISSION IS ACCORDED. 21-11-2025 IN PROGRESS
42 ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS) RULES 2020. 21-11-2025 IN PROGRESS
43 THE APPLICANT SHALL PROVIDE MICRO-COMPOSTING SITE/PLANT WITHIN THE PROJECT PREMISES TO MAKE OWN ARRANGEMENT OF SOLID WASTE MANAGEMENT. 21-11-2025 IN PROGRESS
44 THE OWNER/APPLICANT/TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/ CLEARANCE OF PUBLIC HEALTH ENGINEERING DIVISION (PHED) VIDE LETTER NO.13108 ON DT.25.06.2015, NOC FROM BMC VIDE LETTER NO.9111 DATED.28.05.2016,NOC CGWA VIDE LETTER NO.CGWA/NOC/INF/ORIG/2020/7414 DATED 17.02.2020, NOC FROM CESU VIDE LETTER NO.7002(4) DATED 27.05.2020. 21-11-2025 IN PROGRESS
45 ALL THE FIRE FIGHTING INSTALLATION ETC ARE TO BE ENSURED AND MAINTAINED BY THE APPLICANT AS PER NBC-2016. 21-11-2025 IN PROGRESS
46 NO STORM WATER/WATER SHALL BE DISCHARGED TO THE PUBLIC ROAD/PUBLIC PREMISES AND OTHER ADJOINING PLOTS. 21-11-2025 NOT STARTED
47 ADHERE TO THE PROVISIONS OF ODA (PLANNING & BUILDING STANDARDS) RULES 2020 STRICTLY AND CONDITIONS THERETO. 21-11-2025 NOT STARTED
48 THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER. 21-11-2025 IN PROGRESS
49 THE APPLICANT ON ITS OWN COST SHALL DEVELOP THE EXISTING APPROACH ROAD WITH BLACK TO PUP TO THE PROJECT SITE BOOUNDARY. 21-11-2025 NOT STARTED
50 THE APPLICANT DURING THE COURSE OF CONSTRUCTION AND TILL ISSUE OF OCCUPANCY CERTIFICATE SHALL KEEP PASTED IN A CONSPICUOUS PLACE A COPY OF THE BUILDING PERMIT AND COPY OF APPROVED DRAWING AND SHALL PLACE A DISPLAY BOARD ON SITE WITH DETAILS AND DECLARATION AS GIVEN AT ANNEXURE-I. 21-11-2025 NOT STARTED
Updated Changes on 14-10-2023
51 PARKING SPACE MEASURING 297.31 SQM (STILT FLOOR) AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE. 21-11-2025 IN PROGRESS
52 THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 12.20 MTR IN WIDTH. 21-11-2025 IN PROGRESS
53 PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS. 21-11-2025 WILL BE COMPLIED AS PER THE CONDTION
54 OBTAIN WHEREEVER APPLICABLE FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK. 21-11-2025 IN PROGRESS
55 OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART. 21-11-2025 IN PROGRESS
56 ENSURE COMPLIANCE OF PROVISION OF VARIOUS ACTS, RULES, REGULATIONS AND CODES WHICH CONTROL OR PROVIDE FOR VARIOUS NORMS GOVERNING DEVELOPMENT INCLUDING BUT NOT LIMITED TO PLANNING NORMS FIRE SAFTEY ENVIRONMENTAL NORMS AS APPLICABLE IN EACH CASE. 21-11-2025 IN PROGRESS
57 WHEREEVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY. 21-11-2025 IN PROGRESS
58 STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE-47 OF ODA (PLANNING & BUILDING STANDARDS) RULES 2020. 21-11-2025 IN PROGRESS
59 THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED /CLOSED IN ANY MANNER. 21-11-2025 IN PROGRESS
60 AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER RULE 37 OF ODA (P&BS) RULES 2020. 21-11-2025 IN PROGRESS
61 AT LEAST 50% OF THE OPEN SPACE SHALL BE PREVIOUS AND PLANTATION @ ONE TREE PER 80 SQM OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES,2020. 21-11-2025 IN PROGRESS
62 RAIN WATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER. 21-11-2025 IN PROGRESS
63 GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA. 21-11-2025 IN PROGRESS
64 ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FOR ABSORPTION OF RAIN WATER AND SEEPAGE IN TO THE GROUND. 21-11-2025 IN PROGRESS
65 HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR SPACE PER FLAT SHALL BE PROIVDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN 12 SQUARE METERS. 21-11-2025 IN PROGRESS
66 THE BUILDING SHALL NOT BE PUT TO ANY USE OTHER THAN THE PURPOSE FOR WHICH THE PERMISSION IS ACCORDED. 21-11-2025 IN PROGRESS
67 ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS) RULES 2020. 21-11-2025 IN PROGRESS
68 THE APPLICANT SHALL PROVIDE MICRO-COMPOSTING SITE/PLANT WITHIN THE PROJECT PREMISES TO MAKE OWN ARRANGEMENT OF SOLID WASTE MANAGEMENT. 21-11-2025 IN PROGRESS
69 THE OWNER/APPLICANT/TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/ CLEARANCE OF PUBLIC HEALTH ENGINEERING DIVISION (PHED) VIDE LETTER NO.13108 ON DT.25.06.2015, NOC FROM BMC VIDE LETTER NO.9111 DATED.28.05.2016,NOC CGWA VIDE LETTER NO.CGWA/NOC/INF/ORIG/2020/7414 DATED 17.02.2020, NOC FROM CESU VIDE LETTER NO.7002(4) DATED 27.05.2020. 21-11-2025 IN PROGRESS
70 ALL THE FIRE FIGHTING INSTALLATION ETC ARE TO BE ENSURED AND MAINTAINED BY THE APPLICANT AS PER NBC-2016. 21-11-2025 IN PROGRESS
71 NO STORM WATER/WATER SHALL BE DISCHARGED TO THE PUBLIC ROAD/PUBLIC PREMISES AND OTHER ADJOINING PLOTS. 21-11-2025 NOT STARTED
72 ADHERE TO THE PROVISIONS OF ODA (PLANNING & BUILDING STANDARDS) RULES 2020 STRICTLY AND CONDITIONS THERETO. 21-11-2025 NOT STARTED
73 THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER. 21-11-2025 IN PROGRESS
74 THE APPLICANT ON ITS OWN COST SHALL DEVELOP THE EXISTING APPROACH ROAD WITH BLACK TO PUP TO THE PROJECT SITE BOOUNDARY. 21-11-2025 NOT STARTED
75 THE APPLICANT DURING THE COURSE OF CONSTRUCTION AND TILL ISSUE OF OCCUPANCY CERTIFICATE SHALL KEEP PASTED IN A CONSPICUOUS PLACE A COPY OF THE BUILDING PERMIT AND COPY OF APPROVED DRAWING AND SHALL PLACE A DISPLAY BOARD ON SITE WITH DETAILS AND DECLARATION AS GIVEN AT ANNEXURE-I. 21-11-2025 NOT STARTED
Updated Changes on 15-01-2024
76 PARKING SPACE MEASURING 297.31 SQM (STILT FLOOR) AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE. 21-11-2025 IN PROGRESS
77 THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 12.20 MTR IN WIDTH. 21-11-2025 IN PROGRESS
78 PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS. 21-11-2025 WILL BE COMPLIED AS PER THE CONDTION
79 OBTAIN WHEREEVER APPLICABLE FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK. 21-11-2025 IN PROGRESS
80 OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART. 21-11-2025 IN PROGRESS
81 ENSURE COMPLIANCE OF PROVISION OF VARIOUS ACTS, RULES, REGULATIONS AND CODES WHICH CONTROL OR PROVIDE FOR VARIOUS NORMS GOVERNING DEVELOPMENT INCLUDING BUT NOT LIMITED TO PLANNING NORMS FIRE SAFTEY ENVIRONMENTAL NORMS AS APPLICABLE IN EACH CASE. 21-11-2025 IN PROGRESS
82 WHEREEVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY. 21-11-2025 IN PROGRESS
83 STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE-47 OF ODA (PLANNING & BUILDING STANDARDS) RULES 2020. 21-11-2025 IN PROGRESS
84 THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED /CLOSED IN ANY MANNER. 21-11-2025 IN PROGRESS
85 AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER RULE 37 OF ODA (P&BS) RULES 2020. 21-11-2025 IN PROGRESS
86 AT LEAST 50% OF THE OPEN SPACE SHALL BE PREVIOUS AND PLANTATION @ ONE TREE PER 80 SQM OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES,2020. 21-11-2025 IN PROGRESS
87 RAIN WATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER. 21-11-2025 IN PROGRESS
88 GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA. 21-11-2025 IN PROGRESS
89 ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FOR ABSORPTION OF RAIN WATER AND SEEPAGE IN TO THE GROUND. 21-11-2025 IN PROGRESS
90 HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR SPACE PER FLAT SHALL BE PROIVDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN 12 SQUARE METERS. 21-11-2025 IN PROGRESS
91 THE BUILDING SHALL NOT BE PUT TO ANY USE OTHER THAN THE PURPOSE FOR WHICH THE PERMISSION IS ACCORDED. 21-11-2025 IN PROGRESS
92 ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS) RULES 2020. 21-11-2025 IN PROGRESS
93 THE APPLICANT SHALL PROVIDE MICRO-COMPOSTING SITE/PLANT WITHIN THE PROJECT PREMISES TO MAKE OWN ARRANGEMENT OF SOLID WASTE MANAGEMENT. 21-11-2025 IN PROGRESS
94 THE OWNER/APPLICANT/TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/ CLEARANCE OF PUBLIC HEALTH ENGINEERING DIVISION (PHED) VIDE LETTER NO.13108 ON DT.25.06.2015, NOC FROM BMC VIDE LETTER NO.9111 DATED.28.05.2016,NOC CGWA VIDE LETTER NO.CGWA/NOC/INF/ORIG/2020/7414 DATED 17.02.2020, NOC FROM CESU VIDE LETTER NO.7002(4) DATED 27.05.2020. 21-11-2025 IN PROGRESS
95 ALL THE FIRE FIGHTING INSTALLATION ETC ARE TO BE ENSURED AND MAINTAINED BY THE APPLICANT AS PER NBC-2016. 21-11-2025 IN PROGRESS
96 NO STORM WATER/WATER SHALL BE DISCHARGED TO THE PUBLIC ROAD/PUBLIC PREMISES AND OTHER ADJOINING PLOTS. 21-11-2025 NOT STARTED
97 ADHERE TO THE PROVISIONS OF ODA (PLANNING & BUILDING STANDARDS) RULES 2020 STRICTLY AND CONDITIONS THERETO. 21-11-2025 NOT STARTED
98 THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER. 21-11-2025 IN PROGRESS
99 THE APPLICANT ON ITS OWN COST SHALL DEVELOP THE EXISTING APPROACH ROAD WITH BLACK TO PUP TO THE PROJECT SITE BOOUNDARY. 21-11-2025 NOT STARTED
100 THE APPLICANT DURING THE COURSE OF CONSTRUCTION AND TILL ISSUE OF OCCUPANCY CERTIFICATE SHALL KEEP PASTED IN A CONSPICUOUS PLACE A COPY OF THE BUILDING PERMIT AND COPY OF APPROVED DRAWING AND SHALL PLACE A DISPLAY BOARD ON SITE WITH DETAILS AND DECLARATION AS GIVEN AT ANNEXURE-I. 21-11-2025 NOT STARTED
Updated Changes on 15-04-2024
101 PARKING SPACE MEASURING 297.31 SQM (STILT FLOOR) AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE. 21-11-2025 IN PROGRESS
102 THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 12.20 MTR IN WIDTH. 21-11-2025 IN PROGRESS
103 PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS. 21-11-2025 WILL BE COMPLIED AS PER THE CONDTION
104 OBTAIN WHEREEVER APPLICABLE FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK. 21-11-2025 IN PROGRESS
105 OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART. 21-11-2025 IN PROGRESS
106 ENSURE COMPLIANCE OF PROVISION OF VARIOUS ACTS, RULES, REGULATIONS AND CODES WHICH CONTROL OR PROVIDE FOR VARIOUS NORMS GOVERNING DEVELOPMENT INCLUDING BUT NOT LIMITED TO PLANNING NORMS FIRE SAFTEY ENVIRONMENTAL NORMS AS APPLICABLE IN EACH CASE. 21-11-2025 IN PROGRESS
107 WHEREEVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY. 21-11-2025 IN PROGRESS
108 STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE-47 OF ODA (PLANNING & BUILDING STANDARDS) RULES 2020. 21-11-2025 IN PROGRESS
109 THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED /CLOSED IN ANY MANNER. 21-11-2025 IN PROGRESS
110 AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER RULE 37 OF ODA (P&BS) RULES 2020. 21-11-2025 IN PROGRESS
111 AT LEAST 50% OF THE OPEN SPACE SHALL BE PREVIOUS AND PLANTATION @ ONE TREE PER 80 SQM OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES,2020. 21-11-2025 IN PROGRESS
112 RAIN WATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER. 21-11-2025 IN PROGRESS
113 GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA. 21-11-2025 IN PROGRESS
114 ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FOR ABSORPTION OF RAIN WATER AND SEEPAGE IN TO THE GROUND. 21-11-2025 IN PROGRESS
115 HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR SPACE PER FLAT SHALL BE PROIVDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN 12 SQUARE METERS. 21-11-2025 IN PROGRESS
116 THE BUILDING SHALL NOT BE PUT TO ANY USE OTHER THAN THE PURPOSE FOR WHICH THE PERMISSION IS ACCORDED. 21-11-2025 IN PROGRESS
117 ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS) RULES 2020. 21-11-2025 IN PROGRESS
118 THE APPLICANT SHALL PROVIDE MICRO-COMPOSTING SITE/PLANT WITHIN THE PROJECT PREMISES TO MAKE OWN ARRANGEMENT OF SOLID WASTE MANAGEMENT. 21-11-2025 IN PROGRESS
119 THE OWNER/APPLICANT/TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/ CLEARANCE OF PUBLIC HEALTH ENGINEERING DIVISION (PHED) VIDE LETTER NO.13108 ON DT.25.06.2015, NOC FROM BMC VIDE LETTER NO.9111 DATED.28.05.2016,NOC CGWA VIDE LETTER NO.CGWA/NOC/INF/ORIG/2020/7414 DATED 17.02.2020, NOC FROM CESU VIDE LETTER NO.7002(4) DATED 27.05.2020. 21-11-2025 IN PROGRESS
120 ALL THE FIRE FIGHTING INSTALLATION ETC ARE TO BE ENSURED AND MAINTAINED BY THE APPLICANT AS PER NBC-2016. 21-11-2025 IN PROGRESS
121 NO STORM WATER/WATER SHALL BE DISCHARGED TO THE PUBLIC ROAD/PUBLIC PREMISES AND OTHER ADJOINING PLOTS. 21-11-2025 NOT STARTED
122 ADHERE TO THE PROVISIONS OF ODA (PLANNING & BUILDING STANDARDS) RULES 2020 STRICTLY AND CONDITIONS THERETO. 21-11-2025 NOT STARTED
123 THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER. 21-11-2025 IN PROGRESS
124 THE APPLICANT ON ITS OWN COST SHALL DEVELOP THE EXISTING APPROACH ROAD WITH BLACK TO PUP TO THE PROJECT SITE BOOUNDARY. 21-11-2025 NOT STARTED
125 THE APPLICANT DURING THE COURSE OF CONSTRUCTION AND TILL ISSUE OF OCCUPANCY CERTIFICATE SHALL KEEP PASTED IN A CONSPICUOUS PLACE A COPY OF THE BUILDING PERMIT AND COPY OF APPROVED DRAWING AND SHALL PLACE A DISPLAY BOARD ON SITE WITH DETAILS AND DECLARATION AS GIVEN AT ANNEXURE-I. 21-11-2025 NOT STARTED
Updated Changes on 14-07-2024
126 PARKING SPACE MEASURING 297.31 SQM (STILT FLOOR) AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE. 21-11-2025 IN PROGRESS
127 THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 12.20 MTR IN WIDTH. 21-11-2025 IN PROGRESS
128 PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS. 21-11-2025 WILL BE COMPLIED AS PER THE CONDTION
129 OBTAIN WHEREEVER APPLICABLE FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK. 21-11-2025 IN PROGRESS
130 OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART. 21-11-2025 IN PROGRESS
131 ENSURE COMPLIANCE OF PROVISION OF VARIOUS ACTS, RULES, REGULATIONS AND CODES WHICH CONTROL OR PROVIDE FOR VARIOUS NORMS GOVERNING DEVELOPMENT INCLUDING BUT NOT LIMITED TO PLANNING NORMS FIRE SAFTEY ENVIRONMENTAL NORMS AS APPLICABLE IN EACH CASE. 21-11-2025 IN PROGRESS
132 WHEREEVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY. 21-11-2025 IN PROGRESS
133 STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE-47 OF ODA (PLANNING & BUILDING STANDARDS) RULES 2020. 21-11-2025 IN PROGRESS
134 THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED /CLOSED IN ANY MANNER. 21-11-2025 IN PROGRESS
135 AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER RULE 37 OF ODA (P&BS) RULES 2020. 21-11-2025 IN PROGRESS
136 AT LEAST 50% OF THE OPEN SPACE SHALL BE PREVIOUS AND PLANTATION @ ONE TREE PER 80 SQM OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES,2020. 21-11-2025 IN PROGRESS
137 RAIN WATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER. 21-11-2025 IN PROGRESS
138 GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA. 21-11-2025 IN PROGRESS
139 ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FOR ABSORPTION OF RAIN WATER AND SEEPAGE IN TO THE GROUND. 21-11-2025 IN PROGRESS
140 HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR SPACE PER FLAT SHALL BE PROIVDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN 12 SQUARE METERS. 21-11-2025 IN PROGRESS
141 THE BUILDING SHALL NOT BE PUT TO ANY USE OTHER THAN THE PURPOSE FOR WHICH THE PERMISSION IS ACCORDED. 21-11-2025 IN PROGRESS
142 ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS) RULES 2020. 21-11-2025 IN PROGRESS
143 THE APPLICANT SHALL PROVIDE MICRO-COMPOSTING SITE/PLANT WITHIN THE PROJECT PREMISES TO MAKE OWN ARRANGEMENT OF SOLID WASTE MANAGEMENT. 21-11-2025 IN PROGRESS
144 THE OWNER/APPLICANT/TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/ CLEARANCE OF PUBLIC HEALTH ENGINEERING DIVISION (PHED) VIDE LETTER NO.13108 ON DT.25.06.2015, NOC FROM BMC VIDE LETTER NO.9111 DATED.28.05.2016,NOC CGWA VIDE LETTER NO.CGWA/NOC/INF/ORIG/2020/7414 DATED 17.02.2020, NOC FROM CESU VIDE LETTER NO.7002(4) DATED 27.05.2020. 21-11-2025 IN PROGRESS
145 ALL THE FIRE FIGHTING INSTALLATION ETC ARE TO BE ENSURED AND MAINTAINED BY THE APPLICANT AS PER NBC-2016. 21-11-2025 IN PROGRESS
146 NO STORM WATER/WATER SHALL BE DISCHARGED TO THE PUBLIC ROAD/PUBLIC PREMISES AND OTHER ADJOINING PLOTS. 21-11-2025 NOT STARTED
147 ADHERE TO THE PROVISIONS OF ODA (PLANNING & BUILDING STANDARDS) RULES 2020 STRICTLY AND CONDITIONS THERETO. 21-11-2025 NOT STARTED
148 THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER. 21-11-2025 IN PROGRESS
149 THE APPLICANT ON ITS OWN COST SHALL DEVELOP THE EXISTING APPROACH ROAD WITH BLACK TO PUP TO THE PROJECT SITE BOOUNDARY. 21-11-2025 NOT STARTED
150 THE APPLICANT DURING THE COURSE OF CONSTRUCTION AND TILL ISSUE OF OCCUPANCY CERTIFICATE SHALL KEEP PASTED IN A CONSPICUOUS PLACE A COPY OF THE BUILDING PERMIT AND COPY OF APPROVED DRAWING AND SHALL PLACE A DISPLAY BOARD ON SITE WITH DETAILS AND DECLARATION AS GIVEN AT ANNEXURE-I. 21-11-2025 NOT STARTED
Updated Changes on 14-07-2024
151 PARKING SPACE MEASURING 297.31 SQM (STILT FLOOR) AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE. 21-11-2025 IN PROGRESS
152 THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 12.20 MTR IN WIDTH. 21-11-2025 IN PROGRESS
153 PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS. 21-11-2025 WILL BE COMPLIED AS PER THE CONDTION
154 OBTAIN WHEREEVER APPLICABLE FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK. 21-11-2025 IN PROGRESS
155 OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART. 21-11-2025 IN PROGRESS
156 ENSURE COMPLIANCE OF PROVISION OF VARIOUS ACTS, RULES, REGULATIONS AND CODES WHICH CONTROL OR PROVIDE FOR VARIOUS NORMS GOVERNING DEVELOPMENT INCLUDING BUT NOT LIMITED TO PLANNING NORMS FIRE SAFTEY ENVIRONMENTAL NORMS AS APPLICABLE IN EACH CASE. 21-11-2025 IN PROGRESS
157 WHEREEVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY. 21-11-2025 IN PROGRESS
158 STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE-47 OF ODA (PLANNING & BUILDING STANDARDS) RULES 2020. 21-11-2025 IN PROGRESS
159 THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED /CLOSED IN ANY MANNER. 21-11-2025 IN PROGRESS
160 AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER RULE 37 OF ODA (P&BS) RULES 2020. 21-11-2025 IN PROGRESS
161 AT LEAST 50% OF THE OPEN SPACE SHALL BE PREVIOUS AND PLANTATION @ ONE TREE PER 80 SQM OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES,2020. 21-11-2025 IN PROGRESS
162 RAIN WATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER. 21-11-2025 IN PROGRESS
163 GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA. 21-11-2025 IN PROGRESS
164 ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FOR ABSORPTION OF RAIN WATER AND SEEPAGE IN TO THE GROUND. 21-11-2025 IN PROGRESS
165 HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR SPACE PER FLAT SHALL BE PROIVDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN 12 SQUARE METERS. 21-11-2025 IN PROGRESS
166 THE BUILDING SHALL NOT BE PUT TO ANY USE OTHER THAN THE PURPOSE FOR WHICH THE PERMISSION IS ACCORDED. 21-11-2025 IN PROGRESS
167 ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS) RULES 2020. 21-11-2025 IN PROGRESS
168 THE APPLICANT SHALL PROVIDE MICRO-COMPOSTING SITE/PLANT WITHIN THE PROJECT PREMISES TO MAKE OWN ARRANGEMENT OF SOLID WASTE MANAGEMENT. 21-11-2025 IN PROGRESS
169 THE OWNER/APPLICANT/TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/ CLEARANCE OF PUBLIC HEALTH ENGINEERING DIVISION (PHED) VIDE LETTER NO.13108 ON DT.25.06.2015, NOC FROM BMC VIDE LETTER NO.9111 DATED.28.05.2016,NOC CGWA VIDE LETTER NO.CGWA/NOC/INF/ORIG/2020/7414 DATED 17.02.2020, NOC FROM CESU VIDE LETTER NO.7002(4) DATED 27.05.2020. 21-11-2025 IN PROGRESS
170 ALL THE FIRE FIGHTING INSTALLATION ETC ARE TO BE ENSURED AND MAINTAINED BY THE APPLICANT AS PER NBC-2016. 21-11-2025 IN PROGRESS
171 NO STORM WATER/WATER SHALL BE DISCHARGED TO THE PUBLIC ROAD/PUBLIC PREMISES AND OTHER ADJOINING PLOTS. 21-11-2025 NOT STARTED
172 ADHERE TO THE PROVISIONS OF ODA (PLANNING & BUILDING STANDARDS) RULES 2020 STRICTLY AND CONDITIONS THERETO. 21-11-2025 NOT STARTED
173 THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER. 21-11-2025 IN PROGRESS
174 THE APPLICANT ON ITS OWN COST SHALL DEVELOP THE EXISTING APPROACH ROAD WITH BLACK TO PUP TO THE PROJECT SITE BOOUNDARY. 21-11-2025 NOT STARTED
175 THE APPLICANT DURING THE COURSE OF CONSTRUCTION AND TILL ISSUE OF OCCUPANCY CERTIFICATE SHALL KEEP PASTED IN A CONSPICUOUS PLACE A COPY OF THE BUILDING PERMIT AND COPY OF APPROVED DRAWING AND SHALL PLACE A DISPLAY BOARD ON SITE WITH DETAILS AND DECLARATION AS GIVEN AT ANNEXURE-I. 21-11-2025 NOT STARTED

Updated Project Documents

Sl. No. Title of the document Upload Document
1 PROFORMA -I & II (APR, 2023 TO JUN, 2023)
2 PROFORMA-III
3 PROFORMA -I & II (JUL, 2023 TO SEPT, 2023)
4 SALE AGREEMENTS (JUL, 2023 TO SEPT, 2023)
5 BANK STATEMENT (JUL, 2023 TO SEPT, 2023)
6 PROFORMA-I QUARTER ENDED DEC, 2023
7 PROFORMA-II QUARTER ENDED DEC, 2023
8 BANK STATEMENT (70%) QUARTER ENDED DEC, 2023
9 BANK STATEMENT (100%) QUARTER ENDED DEC, 2023
10 PROFORMA-III
11 PR0FORMA -1( JAN,2024 TO MAR,24)
12 PROFORMA -11(JAN ,2024 TO MAR,24)
13 PROFORMA-111
14 BANK STATEMENT( JAN,24 TO MAR,24)
15 BANK 100%( JAN,24 TO MAR, 24)
16 BANK 70% (JAN ,24 TO MAR, 24)
17 PROFORMA-1 ( APRIL, 24 TO JUNE,24)
18 PROFORMA-11(APRIL,24 TO JUNE,24)
19 PROFORMA-111(APRIL,24 TO JUNE,24)
20 MAA SANTOSHI ENGINEERS PVT LTD- GALAXY ENCLAVE
21 BANK STATEMENT( APRIL,24 TO JUNE 24) 100%
22 BANK STATEMENT ( APRIL,24 TO JUNE,24) 70%
23 PROFORMA-1( APRIL,24 TO JUNE,24)
24 PROFORMA-11( APRIL,24 TO JUNE,24)
25 PROFORMA-111(APRIL,24 TO JUNE,24)
26 BANK STATEMENT MAA SANTOSHI ENGINEERS PVT LTD GALAXY ENCLAVE( APRIL,24 TO JUNE,24)
27 BANK STATEMENT( APRIL,24 TO JUNE,24) 70%
28 BANK STATEMENT(APRIL,24 TO JUNE,24) 100%
:  TAPAS KUMAR :  
NA :  BCHPK8221K
:PAN Card :  tapas3691@gmail.com
:  B.TECH :  9438204580
:  14 YEARS OF EXPERIENCE
:  Yes :  NA
:  PRATAP SEN SWAIN :  
NA :  AQPPS3126C
:PAN Card :  msengineers2009@yahoo.com
:  GRADUATION :  7681099308
:  13 YEARS OF EXPERIENCE
:  Yes :  NA
:  SUSANTA KUMAR MISHRA :  
NA :  BBQPM4359G
:PAN Card :  msengineers2009@yahoo.com
:  GRADUATION :  9238509809
:  13 YEARS OF EXPERIENCE
:  Yes :  NA

Particulars of Architect/Construction Engineer/Contractor/Chartered Accountant

Name position Address with mobile number and email address Registration number Key real estate projects Is active Effective date
RUPAK PANDA Architect PLOT NO-491/2,SAHEEDNAGAR,BBSR-7.MOB-9437008609.MAIL-office@rpassociates.in CA/96/20438 NA
Er.Pitabas Panda Construction Engineer 491/2, Sahid Nagar, Bhubaneswar- 751007, Email-rupak@rpassociates.in,Mob-9437017543 RTP/DTP(ST.ER)-155/2019 NA
NIRANJAN MISHRA Chartered Accountant PLOT NO-214/1342,BEHIND ANDHRA BANK,LAXMISAGAR CHHAK,,BHUBANESWAR-751006.MAIL-caniranjan123@gmail.com,MOB-9438311800 M.NO-302454 NA

Updated Units

House No. Type of Garage/ Parking allotted Serial No., if any Dimension (Length x Width) in Metres Floor area in sq. metres Garage/Parking area cost is included or additional
Updated Changes
101 Covered Parking 1 4.57 M x 2.49 M 11.40 SQM Included
102 Covered Parking 2 4.57 M x 2.49 M 11.40 SQM Included
103 Covered Parking 3 4.57 M x 3.24 M 14.80 SQM Included
201 Covered Parking 4 4.57 M x 3.46 M 15.80 SQM Included
202 Covered Parking 5 4.57 M x 2.04 M 9.30 SQM Included
203 Covered Parking 6 4.57 M x 2.04 M 9.30 SQM Included
301 Covered Parking 7 4.57 M x 3.29 M 15.00 SQM Included
302 Covered Parking 8 5.32 M x 3.24 M 17.30 SQM Included
303 Covered Parking 9 5.32 M x 3.46 M 18.40 SQM Included
401 Covered Parking 10 5.32 M x 3.47 M 18.50 SQM Included
402 Covered Parking 11 4.00 M x 2.66 M 11.30 SQM Included
403 Covered Parking 12 4.00 M x 2.66 M 11.30 SQM Included
Updated Changes
101 Covered Parking 1 4.57 M x 2.49 M 11.40 SQM Included
102 Covered Parking 2 4.57 M x 2.49 M 11.40 SQM Included
103 Covered Parking 3 4.57 M x 3.24 M 14.80 SQM Included
201 Covered Parking 4 4.57 M x 3.46 M 15.80 SQM Included
202 Covered Parking 5 4.57 M x 2.04 M 9.30 SQM Included
203 Covered Parking 6 4.57 M x 2.04 M 9.30 SQM Included
301 Covered Parking 7 4.57 M x 3.29 M 15.00 SQM Included
302 Covered Parking 8 5.32 M x 3.24 M 17.30 SQM Included
303 Covered Parking 9 5.32 M x 3.46 M 18.40 SQM Included
401 Covered Parking 10 5.32 M x 3.47 M 18.50 SQM Included
402 Covered Parking 11 4.00 M x 2.66 M 11.30 SQM Included
403 Covered Parking 12 4.00 M x 2.66 M 11.30 SQM Included
101 Covered Parking 1 4.57 M x 2.49 M 11.40 SQM Included
102 Covered Parking 2 4.57 M x 2.49 M 11.40 SQM Included
103 Covered Parking 3 4.57 M x 3.24 M 14.80 SQM Included
201 Covered Parking 4 4.57 M x 3.46 M 15.80 SQM Included
202 Covered Parking 5 4.57 M x 2.04 M 9.30 SQM Included
203 Covered Parking 6 4.57 M x 2.04 M 9.30 SQM Included
301 Covered Parking 7 4.57 M x 3.29 M 15.00 SQM Included
302 Covered Parking 8 5.32 M x 3.24 M 17.30 SQM Included
303 Covered Parking 9 5.32 M x 3.46 M 18.40 SQM Included
401 Covered Parking 10 5.32 M x 3.47 M 18.50 SQM Included
402 Covered Parking 11 4.00 M x 2.66 M 11.30 SQM Included
403 Covered Parking 12 4.00 M x 2.66 M 11.30 SQM Included

Generated by pacms.orera.in on date: 2024-07-22