1 |
PARKING SPACE MEASURING 649.63 SQM AS SHOWN IN THE APPROVED PLAN SHALL BE STRICLTY ADHERED.
|
10-06-2024
|
IN PROGRESS
|
2 |
THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 9.14 MTR WIDTH DEAD END ROAD
|
10-06-2024
|
IN PROGRESS
|
3 |
20% OF THE LAND SHALL BE UTILIZED FOR PLANTATION
|
10-06-2024
|
IN PROGRESS
|
4 |
THE PERMIT TEE SHALL KEEP THE BeMC BERHAMPUR INFORMED IN WRITING AT LEAST ONE WEEK BEFORE STARTING CONSTRUCTION AS PER REGULATION NO.16 OF THE BDA PLANNING AND BUILDING (STANDARDS) REGULATIONS.
|
10-06-2024
|
COMPLETED
|
5 |
THE CONDITIONS RELATING TO DEVELOPMENT OF ROADS AND DRAINS SHALL BE COMPLIED FIRST BEFORE START OF THE PROJECT AS SUGGESTED BY BeMC BERHAMPUR VIDE LETTER NO.492/BPA-609/2020 DATED 25.03.2021 AND AS PER AFFIDAVIT DATED 08.04.2021.
|
10-06-2024
|
COMPLETED
|
6 |
FOR SAFE DISCHARGE OF EFFLUENT BODS AT 20C SHOULD BE LESS THAN 30 MG/L ONLY BE DISPOSED TO MUNICIPAL DRAIN TO AVOID CONTAMINATION OF SUB-SOIL WATER AND FOR PEROPER DRAINAGE AND SANITATION THE CONDTIONS IMPOSED BY MINUCIPAL COMMISSIONER, BERHAMPUR MUNICIPAL CORPORATION AS PER AFFIDAVIT DATED 08.04.2021 ARE TO BE STRICTLY ADHERED FOR DRAINAGE OF WASTE WATER GENERATED BY THE OCCUPANTS OF THE APARTMENT.
|
10-06-2024
|
IN PROGRESS
|
7 |
UNDER TAKING FOR FIRSE SAFETY MEASURES SUBMITTED BY YOU TO BE FOLLOWED STRICTLY.
|
10-06-2024
|
IN PROGRESS
|
8 |
THE CONDITIONS IMPOSED AND COMMUNICATED BY THE CGWA, NEW DELHI LETTER NO.21-4(597)SER/CGWA/2015-796, DATED 13.05.2025 AS PER AFFIDAVIT DATED 08.04.2021 ARE TO BE ALLOWED TO CATER THE DOMESTIC REQUIREMENTS OF THE OCCUPANTS AND SANITATIONS OF THE PROPSED APARTMENT.
|
10-06-2024
|
IN PROGRESS
|
9 |
THE APARTMENT BUIDLDING S+5 STORIED IS TO BE CONSTRUCTED CONFIRMING TO THE APPROVED PLAN AND STRUCTURAL DESIGN PREPARED BY A REGD. STRUCTURAL ENGINEER AS PER THE PROVISION OF NBC TAKING INTO ACCOUNT THE SAFETY FACTORS LIKE CYCLONE AND EARTHQUAKE ETC. AND IT IS THE COMBINED RESPONSIBILITY OF THE OWNER/ DEVELOPER/ARCHITECT/STRUCTURE ENGINEER IF THERE IS STRUCTURAL FAILURE DUE TO ANY STRUCTURAL DEFECTS FOR WHATSOEVER REASON ENDANGERING THE INTIMATES AND THE PUBLIC.
|
10-06-2024
|
IN PROGRESS
|
10 |
THE PROMOTER SHALL OBTAIN NECESSARY PERMISSION FORM SOUTHCO REGARDING SAFETY FOR ELECTRICAL INSTALLATION AND CONNECTION.
|
10-06-2024
|
IN PROGRESS
|
11 |
THE APPLICANT SHALL NOT OCCUPY OR PERMIT TO OCCUPAY THE BUILDING OR PERMIT TO USE THE BUILDING OR ANY PART THEREOF UNTIL COMPLETION CERTIFICATE IS SUBMITTED TO THIS AUTHORITY AS PER SECTION-20 OF THE ODA ACT AND THE REGULATIONS
|
10-06-2024
|
IN PROGRESS
|
12 |
THIS CORPORATION SHALL STAND INDEMNIFIED AND KEPT HARMLESSS AGAINST ALL PROCEEDING IN ANY COURT OF BEFORE ANY AUTHORITIES AND ALL EXPENSES/ LOSSES CLAIMS WHICH THIS AUTHORITY MAY INCUR OR BECOME LIABLE TO APY AS A RESULT OR IN CONSEQUENCES THEROF.
|
10-06-2024
|
IN PROGRESS
|
13 |
ADEQUATE SAFETY MEASURES SHALL BE ADOPTED FOR TREATMENT AND DISPOSAL OF SEPTIC TANK EFFLUENT UNDER NO CIRCUMSTANCES UNTREATED RIGHT SOIL SHALL BE DISCHARGED IN TO THE DRAINS INVERTED FILTER IF NECESSARY SHALL BE CONSTRUCTED AND THE EFFLUENT FROM THE SEPTIC TANK/SOAK PIT SHALL FLOW THROUGH THEM TO ENSURE REDUCTION OF CONTAMINANT LEVEL TO THE STANDARDS FIXED BY OPCB AND CPCB BEFORE DISCHARGE INTO THE DRAINS.
|
10-06-2024
|
IN PROGRESS
|
14 |
THE S+5 STORIED RESIDNETIAL APARTMENT BUILDING IS TO BE CONSTRUCTED CONFIRMING TO THE APPROVED PLAN AND STRUCTURAL DESIGN PREPARED BY A REGD. STRUCTURAL ENGINEER AS PER THE PROVISION OF NBC TAKING INTO ACCOUNT THE SAFETY FACTORS LIKE CYCLONE AND EARTHQUAKE ETC. AND IT IS THE COMBINED RESPONSIBILITY OF THE OWNER /DEVELOPER/ARCHITECT/STRUCTURE ENGINEER IF THERE IS STRUCTURAL FAILURE DUE TO ANY STRUCTURAL DEFECTS FOR WHATSOEVER REASON ENDANGERING THE INMATES AND THE PUBLIC.
|
10-06-2024
|
IN PROGRESS
|
15 |
NO FURTHER FLOOR IN FUTURE IS ALLOWED BEYOND S+5 CONSIDERING THE GROUND COVERAGE AND SET BACK PROVIDED IN CONSTURCTION OF S+5 STORIED APARTMENT BUILDING.
|
10-06-2024
|
IN PROGRESS
|
16 |
THE DEVELOPER SHALL MAKE OWN ARRANGEMENT FOR SUPPLY OF DRINKING WATER SHALL NOT INSIST UPON PHED FOR PROVIDING WATER FORM THE CITY WATER SUPPLY SYSTEM.
|
10-06-2024
|
IN PROGRESS
|
17 |
THE DEVELOPER WILL HELD RESPONSIBLE FOR ENSURING UNITERRUPTED WATER SUPPLY TO THE INMATES AND THE BeMC IS NO RESPONSIBLE ON THIS FRONT.
|
10-06-2024
|
IN PROGRESS
|
18 |
THE SET BACK AS INDICATED IN THE BUILDING PLAN SHALL BE STRICTLY ADHERED.
|
10-06-2024
|
IN PROGRESS
|
19 |
THE SPACE MEANST FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITINED /CLOSED IN ANY MANNER.
|
10-06-2024
|
IN PROGRESS
|
20 |
25% AREA OF PARKING SPACE SHALL BE EARMARKED FOR VISITORS.
|
10-06-2024
|
IN PROGRESS
|
21 |
HE HAS TO CONSTRUCT GARBAGE STORAGE BIN NOT LESS THAN 100SQM WITHIN HIS PREMISES FOR SMOOTH MANAGEMENT OF SOLID WASTE.
|
10-06-2024
|
IN PROGRESS
|
22 |
THE DEVELOPER HAS TO CONSTRUCT ROOF RAIN WATER HARVESTING STRUCTURE @6 CUM FOR 100 SQM OF TERRACE AREA.
|
10-06-2024
|
IN PROGRESS
|
Updated Changes on 15-07-2023 |
23 |
PARKING SPACE MEASURING 649.63 SQM AS SHOWN IN THE APPROVED PLAN SHALL BE STRICLTY ADHERED.
|
10-06-2024
|
IN PROGRESS
|
24 |
THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 9.14 MTR WIDTH DEAD END ROAD
|
10-06-2024
|
IN PROGRESS
|
25 |
20% OF THE LAND SHALL BE UTILIZED FOR PLANTATION
|
10-06-2024
|
IN PROGRESS
|
26 |
THE PERMIT TEE SHALL KEEP THE BeMC BERHAMPUR INFORMED IN WRITING AT LEAST ONE WEEK BEFORE STARTING CONSTRUCTION AS PER REGULATION NO.16 OF THE BDA PLANNING AND BUILDING (STANDARDS) REGULATIONS.
|
10-06-2024
|
COMPLETED
|
27 |
THE CONDITIONS RELATING TO DEVELOPMENT OF ROADS AND DRAINS SHALL BE COMPLIED FIRST BEFORE START OF THE PROJECT AS SUGGESTED BY BeMC BERHAMPUR VIDE LETTER NO.492/BPA-609/2020 DATED 25.03.2021 AND AS PER AFFIDAVIT DATED 08.04.2021.
|
10-06-2024
|
COMPLETED
|
28 |
FOR SAFE DISCHARGE OF EFFLUENT BODS AT 20C SHOULD BE LESS THAN 30 MG/L ONLY BE DISPOSED TO MUNICIPAL DRAIN TO AVOID CONTAMINATION OF SUB-SOIL WATER AND FOR PEROPER DRAINAGE AND SANITATION THE CONDTIONS IMPOSED BY MINUCIPAL COMMISSIONER, BERHAMPUR MUNICIPAL CORPORATION AS PER AFFIDAVIT DATED 08.04.2021 ARE TO BE STRICTLY ADHERED FOR DRAINAGE OF WASTE WATER GENERATED BY THE OCCUPANTS OF THE APARTMENT.
|
10-06-2024
|
IN PROGRESS
|
29 |
UNDER TAKING FOR FIRSE SAFETY MEASURES SUBMITTED BY YOU TO BE FOLLOWED STRICTLY.
|
10-06-2024
|
IN PROGRESS
|
30 |
THE CONDITIONS IMPOSED AND COMMUNICATED BY THE CGWA, NEW DELHI LETTER NO.21-4(597)SER/CGWA/2015-796, DATED 13.05.2025 AS PER AFFIDAVIT DATED 08.04.2021 ARE TO BE ALLOWED TO CATER THE DOMESTIC REQUIREMENTS OF THE OCCUPANTS AND SANITATIONS OF THE PROPSED APARTMENT.
|
10-06-2024
|
IN PROGRESS
|
31 |
THE APARTMENT BUIDLDING S+5 STORIED IS TO BE CONSTRUCTED CONFIRMING TO THE APPROVED PLAN AND STRUCTURAL DESIGN PREPARED BY A REGD. STRUCTURAL ENGINEER AS PER THE PROVISION OF NBC TAKING INTO ACCOUNT THE SAFETY FACTORS LIKE CYCLONE AND EARTHQUAKE ETC. AND IT IS THE COMBINED RESPONSIBILITY OF THE OWNER/ DEVELOPER/ARCHITECT/STRUCTURE ENGINEER IF THERE IS STRUCTURAL FAILURE DUE TO ANY STRUCTURAL DEFECTS FOR WHATSOEVER REASON ENDANGERING THE INTIMATES AND THE PUBLIC.
|
10-06-2024
|
IN PROGRESS
|
32 |
THE PROMOTER SHALL OBTAIN NECESSARY PERMISSION FORM SOUTHCO REGARDING SAFETY FOR ELECTRICAL INSTALLATION AND CONNECTION.
|
10-06-2024
|
IN PROGRESS
|
33 |
THE APPLICANT SHALL NOT OCCUPY OR PERMIT TO OCCUPAY THE BUILDING OR PERMIT TO USE THE BUILDING OR ANY PART THEREOF UNTIL COMPLETION CERTIFICATE IS SUBMITTED TO THIS AUTHORITY AS PER SECTION-20 OF THE ODA ACT AND THE REGULATIONS
|
10-06-2024
|
IN PROGRESS
|
34 |
THIS CORPORATION SHALL STAND INDEMNIFIED AND KEPT HARMLESSS AGAINST ALL PROCEEDING IN ANY COURT OF BEFORE ANY AUTHORITIES AND ALL EXPENSES/ LOSSES CLAIMS WHICH THIS AUTHORITY MAY INCUR OR BECOME LIABLE TO APY AS A RESULT OR IN CONSEQUENCES THEROF.
|
10-06-2024
|
IN PROGRESS
|
35 |
ADEQUATE SAFETY MEASURES SHALL BE ADOPTED FOR TREATMENT AND DISPOSAL OF SEPTIC TANK EFFLUENT UNDER NO CIRCUMSTANCES UNTREATED RIGHT SOIL SHALL BE DISCHARGED IN TO THE DRAINS INVERTED FILTER IF NECESSARY SHALL BE CONSTRUCTED AND THE EFFLUENT FROM THE SEPTIC TANK/SOAK PIT SHALL FLOW THROUGH THEM TO ENSURE REDUCTION OF CONTAMINANT LEVEL TO THE STANDARDS FIXED BY OPCB AND CPCB BEFORE DISCHARGE INTO THE DRAINS.
|
10-06-2024
|
IN PROGRESS
|
36 |
THE S+5 STORIED RESIDNETIAL APARTMENT BUILDING IS TO BE CONSTRUCTED CONFIRMING TO THE APPROVED PLAN AND STRUCTURAL DESIGN PREPARED BY A REGD. STRUCTURAL ENGINEER AS PER THE PROVISION OF NBC TAKING INTO ACCOUNT THE SAFETY FACTORS LIKE CYCLONE AND EARTHQUAKE ETC. AND IT IS THE COMBINED RESPONSIBILITY OF THE OWNER /DEVELOPER/ARCHITECT/STRUCTURE ENGINEER IF THERE IS STRUCTURAL FAILURE DUE TO ANY STRUCTURAL DEFECTS FOR WHATSOEVER REASON ENDANGERING THE INMATES AND THE PUBLIC.
|
10-06-2024
|
IN PROGRESS
|
37 |
NO FURTHER FLOOR IN FUTURE IS ALLOWED BEYOND S+5 CONSIDERING THE GROUND COVERAGE AND SET BACK PROVIDED IN CONSTURCTION OF S+5 STORIED APARTMENT BUILDING.
|
10-06-2024
|
IN PROGRESS
|
38 |
THE DEVELOPER SHALL MAKE OWN ARRANGEMENT FOR SUPPLY OF DRINKING WATER SHALL NOT INSIST UPON PHED FOR PROVIDING WATER FORM THE CITY WATER SUPPLY SYSTEM.
|
10-06-2024
|
IN PROGRESS
|
39 |
THE DEVELOPER WILL HELD RESPONSIBLE FOR ENSURING UNITERRUPTED WATER SUPPLY TO THE INMATES AND THE BeMC IS NO RESPONSIBLE ON THIS FRONT.
|
10-06-2024
|
IN PROGRESS
|
40 |
THE SET BACK AS INDICATED IN THE BUILDING PLAN SHALL BE STRICTLY ADHERED.
|
10-06-2024
|
IN PROGRESS
|
41 |
THE SPACE MEANST FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITINED /CLOSED IN ANY MANNER.
|
10-06-2024
|
IN PROGRESS
|
42 |
25% AREA OF PARKING SPACE SHALL BE EARMARKED FOR VISITORS.
|
10-06-2024
|
IN PROGRESS
|
43 |
HE HAS TO CONSTRUCT GARBAGE STORAGE BIN NOT LESS THAN 100SQM WITHIN HIS PREMISES FOR SMOOTH MANAGEMENT OF SOLID WASTE.
|
10-06-2024
|
IN PROGRESS
|
44 |
THE DEVELOPER HAS TO CONSTRUCT ROOF RAIN WATER HARVESTING STRUCTURE @6 CUM FOR 100 SQM OF TERRACE AREA.
|
10-06-2024
|
IN PROGRESS
|