Generated by pacms.orera.in on date: 2024-05-17
: M/s LAXMI INFRA VENTURE PVT.LTD | : Private Company |
: U70101OR2011PTC013564 | :View |
NA | : 315, Saheed Nagar, Bhubaneswar-751007, ODISHA |
: 315, Saheed Nagar, Bhubaneswar, Odisha- 751007. | : laxmiinfra@gmail.com |
: 9439201387 | |
: AACCL0256A | :View |
: 10 Years in the field of Development & Construction | : 0 |
: www.laxmiinfra.co.in |
: Rajesh Kumar Nayak | : |
: Managing Director | : AFMPN5217M |
:PAN Card | : laxmiinfra@gmail.com |
: Graduation | : 9439201387 |
: Last 14years experience in the real estate sector | |
: Yes | : NA |
: Rashmita Nayak | : |
: Director | : AMPPN1067M |
:PAN Card | : laxmiinfra@gmail.com |
: Graduation | : 7789841141 |
: Since Last 12 Years in the Field of Real Estate Sector | |
: Yes | : NA |
: New | : LAXMI ANNEX |
: Residential | : ( Residential Project, S+5 & B+S+5 (MIG), No. of Units- 70 ) |
: Khordha | : Bhubaneswar MC |
: 752101 | : Urban Local Body |
: Bhubaneswar Municipal Corporation | |
: S+5 & B+S+5 (MIG) Residential Apartment | : NA |
: Yes |
Serial No. | Particulars of the Person | Land/Plot Details | Share of the Person | Document Attached |
---|---|---|---|---|
1 | Smt. Rajshree Pattnaik, Sri. Sivananda Prasad Nanda, Smt. Reeta Panigrahy | Plot No- 615, 616, Khata No-412/125, Plot no-617, Khata No-412/144, Plot no-620, 621, Khata No-412/124 | 38% | Agreement Copy |
View | View |
Download site plan | 15-10-2024 |
Sl. No. | Description of Conditions | Schedule date of compliance | Present Status |
---|---|---|---|
1 | The building shall be used exclusively for Residential purpose and the use shall not be changed to any other use without prior approval of this authority. | 15-10-2024 | Work in progress |
2 | The development shall be undertaken strictly according to plans enclosed with necessary permission endorsement. | 15-10-2024 | Work in progress |
3 | Parking space measuring 2207.96 sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/ closed in any manner. | 15-10-2024 | Work in progress |
4 | The land over which construction is proposed is accessible by an approved means of access of 9.14M (Nine Point One Four) in width. | 15-10-2024 | Work in progress |
5 | The permission granted under these regulations shall remain valid up to three years from the date of issue. However the permission shall have to be revalidated before the expiry of the above period on payment of such fee as may be prescribed under rules and such revalidation shall be valid for one year | 15-10-2023 | Work in progress |
6 | Rain water from the premises of roof top of the building shall be conveyed and discharged to the rain water recharging pits as per norms of ODA ( Planning & Building Standards) Rules-2020 | 15-10-2024 | Work in progress |
7 | The number of dwelling units so approved shall not be changed in any manner. | 15-10-2024 | Work in progress |
8 | The Owner/ applicant/ Architect/ Structural Engineer are fully and jointly responsible for any structural failure of building due to any earthquake/ cyclone/ any other natural disaster, structural/ construction defects, Authority will be no way be held responsible for the same in what so ever manner | 15-10-2024 | Work in progress |
: Yes | : View |
Point No. | Latitude | Longitude |
---|---|---|
1 | 20°19'04.0"°N | 85°52'59.2"°E |
2 | 20°19'04.4"°N | 85°52'59.5"°E |
3 | 20°19'04.5"°N | 85°52'59.4"°E |
4 | 20°19'05.3"°N | 85°53'00.0"°E |
5 | 20°19'06.2"°N | 85°53'00.7"°E |
6 | 20°19'05.3"°N | 85°53'02.0"°E |
7 | 20°19'04.5"°N | 85°53'01.5"°E |
8 | 20°19'03.6"°N | 85°53'00.8"°E |
9 | 20°19'04.1"°N | 85°53'00.1"°E |
10 | 20°19'03.4"°N | 85°52'59.4"°E |
Description* | Scheduled date of completion | Current Status | Site Images |
---|---|---|---|
Site Development | 26-02-2022 | Work in progress | |
Roof Casting | NA | NA | NA |
Ground Floor/Stilt Floor | 30-04-2022 | Not yet started | NA |
1 Floor | 01-05-2022 | Not yet started | NA |
2 Floor | 30-06-2022 | Not yet started | NA |
3 Floor | 31-07-2022 | Not yet started | NA |
4 Floor | 31-08-2022 | Not yet started | NA |
5 Floor | 30-09-2022 | Not yet started | NA |
Brick Work & Plastering | NA | NA | NA |
Ground Floor/Stilt Floor | 20-09-2022 | Not yet started | NA |
1 Floor | 30-11-2022 | Not yet started | NA |
2 Floor | 31-12-2022 | Not yet started | NA |
3 Floor | 31-01-2023 | Not yet started | NA |
4 Floor | 28-02-2023 | Not yet started | NA |
5 Floor | 30-03-2023 | Not yet started | NA |
Electrical Works | 30-04-2023 | Not yet started | NA |
Concealed Cabling including Plugs & switches | 25-06-2023 | Not yet started | NA |
Installation & Charging of Transformer | 30-07-2023 | Not yet started | NA |
Connection to Flats/Apartments | 20-08-2023 | Not yet started | NA |
PH works | 30-10-2023 | Not yet started | NA |
Laying of concealed Pipes | 15-11-2023 | Not yet started | NA |
PH Fittings | 30-12-2023 | Not yet started | NA |
Overhead Water Tanks | 25-02-2024 | Not yet started | NA |
Water Supply Connection to all units | 01-03-2024 | Not yet started | NA |
STP construction and completion | 01-04-2024 | Not yet started | NA |
Distempering & Colouring of all units and exteriors | 01-06-2024 | Not yet started | NA |
Fixation of doors and windows | 01-8-2024 | Not yet started | NA |
Scheduled Date of handing over possession | 01-09-2024 | Not yet started | NA |
Development of common areas, parks, gardens etc | 01-10-2024 | Not yet started | NA |
Site Development | 26-02-2022 | Work in progress | NA |
NA | NA | NA | NA |
Ground Floor/Stilt Floor | 20-10-2022 | Not yet started | NA |
1 Floor | 30-11-2022 | Not yet started | NA |
2 Floor | 30-06-2022 | Not yet started | NA |
3 Floor | 31-07-2022 | Not yet started | NA |
4 Floor | 31-08-2022 | Not yet started | NA |
5 Floor | 30-09-2022 | Not yet started | NA |
NA | NA | NA | NA |
Ground Floor/Stilt Floor | 20-09-2022 | Not yet started | NA |
1 Floor | 30-11-2022 | Not yet started | NA |
2 Floor | 31-12-2022 | Not yet started | NA |
3 Floor | 31-01-2023 | Not yet started | NA |
4 Floor | 28-02-2023 | Not yet started | NA |
5 Floor | 30-03-2023 | Not yet started | NA |
Electrical Works | 30-04-2023 | Not yet started | NA |
Concealed Cabling including Plugs & switches | 25-06-2023 | Not yet started | NA |
Installation & Charging of Transformer | 30-07-2023 | Not yet started | NA |
Connection to Flats/Apartments | 20-08-2023 | Not yet started | NA |
PH works | 30-10-2023 | Not yet started | NA |
Laying of concealed Pipes | 15-11-2023 | Not yet started | NA |
PH Fittings | 30-12-2023 | Not yet started | NA |
Overhead Water Tanks | 25-02-2024 | Not yet started | NA |
Water Supply Connection to all units | 01-03-2024 | Not yet started | NA |
STP construction and completion | 01-04-2024 | Not yet started | NA |
Distempering & Colouring of all units and exteriors | 01-06-2024 | Not yet started | NA |
Fixation of doors and windows | 01-8-2024 | Not yet started | NA |
Scheduled Date of handing over possession | 01-09-2024 | Not yet started | NA |
Development of common areas, parks, gardens etc | 01-10-2024 | Not yet started | NA |
Site Development | 26-02-2022 | Work in progress | NA |
NA | 14-07-2023 | COMPLETE | NA |
Ground Floor/Stilt Floor | 20-10-2022 | COMPLETE | NA |
1 Floor | 30-11-2022 | COMPLETE | NA |
2 Floor | 30-06-2022 | COMPLETE | NA |
3 Floor | 31-07-2022 | Not yet started | NA |
4 Floor | 31-08-2022 | Not yet started | NA |
5 Floor | 30-09-2022 | Not yet started | NA |
NA | 14-07-2023 | COMPLETE | NA |
Ground Floor/Stilt Floor | 20-09-2022 | COMPLETE | NA |
1 Floor | 30-11-2022 | Not yet started | NA |
2 Floor | 31-12-2022 | Not yet started | NA |
3 Floor | 31-01-2023 | Not yet started | NA |
4 Floor | 28-02-2023 | Not yet started | NA |
5 Floor | 30-03-2023 | Not yet started | NA |
Electrical Works | 30-04-2023 | Not yet started | NA |
Concealed Cabling including Plugs & switches | 25-06-2023 | Not yet started | NA |
Installation & Charging of Transformer | 30-07-2023 | Not yet started | NA |
Connection to Flats/Apartments | 20-08-2023 | Not yet started | NA |
PH works | 30-10-2023 | Not yet started | NA |
Laying of concealed Pipes | 15-11-2023 | Not yet started | NA |
PH Fittings | 30-12-2023 | Not yet started | NA |
Overhead Water Tanks | 25-02-2024 | Not yet started | NA |
Water Supply Connection to all units | 01-03-2024 | Not yet started | NA |
STP construction and completion | 01-04-2024 | Not yet started | NA |
Distempering & Colouring of all units and exteriors | 01-06-2024 | Not yet started | NA |
Fixation of doors and windows | 01-8-2024 | Not yet started | NA |
Scheduled Date of handing over possession | 01-09-2024 | Not yet started | NA |
Development of common areas, parks, gardens etc | 01-10-2024 | Not yet started | NA |
Site Development | 26-02-2022 | Work in progress | NA |
NA | 14-07-2023 | COMPLETE | NA |
Ground Floor/Stilt Floor | 01-01-2023 | COMPLETE | |
1 Floor | 01-04-2023 | COMPLETE | NA |
2 Floor | 01-07-2023 | COMPLETE | NA |
3 Floor | 01-05-2023 | UNDER PROGRESS | |
4 Floor | 01-01-2024 | Not yet started | NA |
5 Floor | 01-02-2024 | Not yet started | NA |
NA | 14-07-2023 | COMPLETE | NA |
Ground Floor/Stilt Floor | 01-04-2023 | COMPLETE | NA |
1 Floor | 01-07-2023 | BRICK WORK STARTED | |
2 Floor | 01-10-2023 | BRICK WORK STARTED | |
3 Floor | 01-12-2023 | Not yet started | NA |
4 Floor | 01-01-2024 | Not yet started | NA |
5 Floor | 01-05-2024 | Not yet started | NA |
Electrical Works | 30-04-2023 | Not yet started | NA |
Concealed Cabling including Plugs & switches | 25-06-2023 | Not yet started | NA |
Installation & Charging of Transformer | 30-07-2023 | Not yet started | NA |
Connection to Flats/Apartments | 20-08-2023 | Not yet started | NA |
PH works | 30-10-2023 | Not yet started | NA |
Laying of concealed Pipes | 15-11-2023 | Not yet started | NA |
PH Fittings | 30-12-2023 | Not yet started | NA |
Overhead Water Tanks | 25-02-2024 | Not yet started | NA |
Water Supply Connection to all units | 01-03-2024 | Not yet started | NA |
STP construction and completion | 01-04-2024 | Not yet started | NA |
Distempering & Colouring of all units and exteriors | 01-06-2024 | Not yet started | NA |
Fixation of doors and windows | 01-8-2024 | Not yet started | NA |
Scheduled Date of handing over possession | 01-09-2024 | Not yet started | NA |
Development of common areas, parks, gardens etc | 01-10-2024 | Not yet started | NA |
Site Development | 26-02-2022 | Work in progress | NA |
NA | 14-07-2023 | COMPLETE | NA |
Ground Floor/Stilt Floor | 01-01-2023 | COMPLETE | |
1 Floor | 01-04-2023 | SLAB CASTING COMPLETE | |
2 Floor | 01-07-2023 | SLAB CASTING COMPLETE | |
3 Floor | 01-05-2023 | SLAB CASTING COMPLETE | |
4 Floor | 01-11-2023 | SLAB CASTING COMPLETE | |
5 Floor | 01-01-2024 | SLAB CASTING COMPLETE | |
NA | 14-07-2023 | COMPLETE | NA |
Ground Floor/Stilt Floor | 01-04-2023 | COMPLETE | NA |
1 Floor | 01-07-2023 | BRICK WORK COMPLETE | |
2 Floor | 01-10-2023 | BRICK WORK COMPLETE | |
3 Floor | 01-12-2023 | BRICK WORK COMPLETE | NA |
4 Floor | 01-01-2024 | BRICK WORK COMPLETE | NA |
5 Floor | 01-05-2024 | UNDER PROGRESS | NA |
Electrical Works | 01-06-2024 | Not yet started | NA |
Concealed Cabling including Plugs & switches | 01-06-2024 | Not yet started | NA |
Installation & Charging of Transformer | 01-06-2024 | Not yet started | NA |
Connection to Flats/Apartments | 01-07-2024 | Not yet started | NA |
PH works | 01-06-2024 | Not yet started | NA |
Laying of concealed Pipes | 01-07-2024 | Not yet started | NA |
PH Fittings | 01-07-2024 | Not yet started | NA |
Overhead Water Tanks | 01-06-2024 | Not yet started | NA |
Water Supply Connection to all units | 01-08-2024 | Not yet started | NA |
STP construction and completion | 01-08-2024 | Not yet started | NA |
Distempering & Colouring of all units and exteriors | 01-06-2024 | Not yet started | NA |
Fixation of doors and windows | 31-08-2024 | Not yet started | NA |
Scheduled Date of handing over possession | 15-10-2024 | Not yet started | NA |
Development of common areas, parks, gardens etc | 01-10-2024 | Not yet started | NA |
Site Development | 26-02-2022 | COMPLETE | NA |
NA | 14-07-2023 | COMPLETE | NA |
Ground Floor/Stilt Floor | 01-01-2023 | COMPLETE | |
1 Floor | 01-04-2023 | SLAB CASTING COMPLETE | |
2 Floor | 01-07-2023 | SLAB CASTING COMPLETE | NA |
3 Floor | 01-05-2023 | SLAB CASTING COMPLETE | NA |
4 Floor | 01-11-2023 | SLAB CASTING COMPLETE | NA |
5 Floor | 01-01-2024 | SLAB CASTING COMPLETE | NA |
NA | 14-07-2023 | COMPLETE | NA |
Ground Floor/Stilt Floor | 01-04-2023 | COMPLETE | NA |
1 Floor | 01-07-2023 | BRICK WORK COMPLETE | |
2 Floor | 01-10-2023 | BRICK WORK COMPLETE | |
3 Floor | 01-12-2023 | BRICK WORK COMPLETE | NA |
4 Floor | 01-01-2024 | BRICK WORK COMPLETE | NA |
5 Floor | 01-05-2024 | BRICK WORK COMPLETE | NA |
Electrical Works | 01-06-2024 | UNDER PROGRESS | NA |
Concealed Cabling including Plugs & switches | 01-06-2024 | UNDER PROGRESS | NA |
Installation & Charging of Transformer | 01-06-2024 | Not yet started | NA |
Connection to Flats/Apartments | 01-07-2024 | Not yet started | NA |
PH works | 01-06-2024 | UNDER PROGRESS | NA |
Laying of concealed Pipes | 01-07-2024 | UNDER PROGRESS | NA |
PH Fittings | 01-07-2024 | UNDER PROGRESS | NA |
Overhead Water Tanks | 01-06-2024 | UNDER PROGRESS | NA |
Water Supply Connection to all units | 01-08-2024 | Not yet started | NA |
STP construction and completion | 01-08-2024 | UNDER PROGRESS | NA |
Distempering & Colouring of all units and exteriors | 01-06-2024 | Not yet started | NA |
Fixation of doors and windows | 31-08-2024 | UNDER PROGRESS | NA |
Scheduled Date of handing over possession | 15-10-2024 | Not yet started | NA |
Development of common areas, parks, gardens etc | 01-10-2024 | Not yet started | NA |
: Residential | |
: 70
|
|
Residential Flats/ House | |||||
---|---|---|---|---|---|
S. No. | Flat No./ House No. | ||||
Area in square metres |
Ownership | ||||
Carpet Area | Balcony Area | Exclusive Open Terrace Area | |||
1 | A-101 | 92.03 | 11.04 | N.A | Promoter |
2 | A-102 | 46.12 | 4.05 | N.A | Promoter |
3 | A-103 | 93.82 | 11.06 | N.A | Promoter |
4 | A-104 | 93.82 | 11.06 | N.A | Promoter |
5 | A-105 | 46.12 | 4.05 | N.A | Promoter |
6 | A-106 | 92.03 | 11.04 | N.A | Promoter |
7 | A-201 | 92.03 | 11.04 | N.A | Promoter |
8 | A-202 | 46.12 | 4.05 | N.A | Promoter |
9 | A-203 | 93.82 | 11.06 | N.A | Promoter |
10 | A-204 | 93.82 | 11.06 | N.A | Promoter |
11 | A-205 | 46.12 | 4.05 | N.A | Promoter |
12 | A-206 | 92.03 | 11.04 | N.A | Promoter |
13 | A-301 | 92.03 | 11.04 | N.A | Promoter |
14 | A-302 | 46.12 | 4.05 | N.A | Promoter |
15 | A-303 | 93.82 | 11.06 | N.A | Promoter |
16 | A-304 | 93.82 | 11.06 | N.A | Land Owner |
17 | A-305 | 46.12 | 4.05 | N.A | Promoter |
18 | A-306 | 92.03 | 11.04 | N.A | Promoter |
19 | A-401 | 92.03 | 11.04 | N.A | Promoter |
20 | A-402 | 46.12 | 4.05 | N.A | Promoter |
21 | A-403 | 93.82 | 11.06 | N.A | Promoter |
22 | A-404 | 93.82 | 11.06 | N.A | Promoter |
23 | A-405 | 46.12 | 4.05 | N.A | Promoter |
24 | A-406 | 92.03 | 11.04 | N.A | Promoter |
25 | A-501 | 92.03 | 11.04 | N.A | Promoter |
26 | A-502 | 46.12 | 4.05 | N.A | Land Owner |
27 | A-503 | 93.82 | 11.06 | N.A | Promoter |
28 | A-504 | 93.82 | 11.06 | N.A | Promoter |
29 | A-505 | 46.12 | 4.05 | N.A | Land Owner |
30 | A-506 | 92.03 | 11.04 | N.A | Promoter |
31 | B-101 | 74.34 | 8.24 | N.A | Promoter |
32 | B-102 | 74.34 | 8.24 | N.A | Promoter |
33 | B-103 | 74.34 | 8.24 | N.A | Promoter |
34 | B-104 | 74.34 | 8.24 | N.A | Promoter |
35 | B-105 | 74.34 | 8.24 | N.A | Promoter |
36 | B-106 | 74.34 | 8.24 | N.A | Promoter |
37 | B-107 | 74.34 | 8.24 | N.A | Promoter |
38 | B-108 | 74.34 | 8.24 | N.A | Promoter |
39 | B-201 | 74.34 | 8.24 | N.A | Promoter |
40 | B-202 | 74.34 | 8.24 | N.A | Promoter |
41 | B-203 | 74.34 | 8.24 | N.A | Promoter |
42 | B-204 | 74.34 | 8.24 | N.A | Promoter |
43 | B-205 | 74.34 | 8.24 | N.A | Promoter |
44 | B-206 | 74.34 | 8.24 | N.A | Promoter |
45 | B-207 | 74.34 | 8.24 | N.A | Promoter |
46 | B-208 | 74.34 | 8.24 | N.A | Promoter |
47 | B-301 | 74.34 | 8.24 | N.A | Promoter |
48 | B-302 | 74.34 | 8.24 | N.A | Promoter |
49 | B-303 | 74.34 | 8.24 | N.A | Promoter |
50 | B-304 | 74.34 | 8.24 | N.A | Land Owner |
51 | B-305 | 74.34 | 8.24 | N.A | Land Owner |
52 | B-306 | 74.34 | 8.24 | N.A | Land Owner |
53 | B-307 | 74.34 | 8.24 | N.A | Promoter |
54 | B-308 | 74.34 | 8.24 | N.A | Promoter |
55 | B-401 | 74.34 | 8.24 | N.A | Promoter |
56 | B-402 | 74.34 | 8.24 | N.A | Promoter |
57 | B-403 | 74.34 | 8.24 | N.A | Promoter |
58 | B-404 | 74.34 | 8.24 | N.A | Promoter |
59 | B-405 | 74.34 | 8.24 | N.A | Land Owner |
60 | B-406 | 74.34 | 8.24 | N.A | Promoter |
61 | B-407 | 74.34 | 8.24 | N.A | Promoter |
62 | B-408 | 74.34 | 8.24 | N.A | Promoter |
63 | B-501 | 74.34 | 8.24 | N.A | Promoter |
64 | B-502 | 74.34 | 8.24 | N.A | Promoter |
65 | B-503 | 74.34 | 8.24 | N.A | Promoter |
66 | B-504 | 74.34 | 8.24 | N.A | Promoter |
67 | B-505 | 74.34 | 8.24 | N.A | Promoter |
68 | B-506 | 74.34 | 8.24 | N.A | Promoter |
69 | B-507 | 74.34 | 8.24 | N.A | Promoter |
70 | B-508 | 74.34 | 8.24 | N.A | Promoter |
Types of garages and parking | ||||||
---|---|---|---|---|---|---|
House No. | Type of Garage/ Parking allotted | Serial No., if any | Dimension (Length x Width) in Metres | Floor area in sq. metres | Garage/Parking area cost is included or additional | |
A-101 | Covered Parking | 01 | 3.00 x 4.20 | 12.60 | Included | A-102 | Covered Parking | 02 | 3.00 x 4.20 | 12.60 | Included | A-103 | Covered Parking | 03 | 3.00 x 4.20 | 12.60 | Included | A-104 | Covered Parking | 04 | 3.00 x 4.20 | 12.60 | Included | A-105 | Covered Parking | 05 | 3.00 x 4.20 | 12.60 | Included | A-106 | Covered Parking | 06 | 3.00 x 4.20 | 12.60 | Included | A-201 | Covered Parking | 07 | 3.00 x 4.20 | 12.60 | Included | A-202 | Covered Parking | 08 | 3.00 x 4.20 | 12.60 | Included | A-203 | Covered Parking | 09 | 3.00 x 4.20 | 12.60 | Included | A-204 | Covered Parking | 10 | 3.00 x 4.20 | 12.60 | Included | A-205 | Covered Parking | 11 | 3.00 x 4.20 | 12.60 | Included | A-206 | Covered Parking | 12 | 3.00 x 4.20 | 12.60 | Included | A-301 | Covered Parking | 13 | 3.00 x 4.20 | 12.60 | Included | A-302 | Covered Parking | 14 | 3.00 x 4.20 | 12.60 | Included | A-303 | Covered Parking | 15 | 3.00 x 4.20 | 12.60 | Included | A-304 | Covered Parking | 16 | 3.00 x 4.20 | 12.60 | Included | A-305 | Covered Parking | 17 | 3.00 x 4.20 | 12.60 | Included | A-306 | Covered Parking | 18 | 3.00 x 4.20 | 12.60 | Included | A-401 | Covered Parking | 19 | 3.00 x 4.20 | 12.60 | Included | A-402 | Covered Parking | 20 | 3.00 x 4.20 | 12.60 | Included | A-403 | Covered Parking | 21 | 3.00 x 4.20 | 12.60 | Included | A-404 | Covered Parking | 22 | 3.00 x 4.20 | 12.60 | Included | A-405 | Covered Parking | 23 | 3.00 x 4.20 | 12.60 | Included | A-406 | Covered Parking | 24 | 3.00 x 4.20 | 12.60 | Included | A-501 | Covered Parking | 25 | 3.00 x 4.20 | 12.60 | Included | A-502 | Covered Parking | 26 | 3.00 x 4.20 | 12.60 | Included | A-503 | Covered Parking | 27 | 3.00 x 4.20 | 12.60 | Included | A-504 | Covered Parking | 28 | 3.00 x 4.20 | 12.60 | Included | A-505 | Covered Parking | 29 | 3.00 x 4.20 | 12.60 | Included | A-506 | Covered Parking | 30 | 3.00 x 4.20 | 12.60 | Included | B-101 | Covered Parking | 31 | 3.00 x 4.20 | 12.60 | Included | B-102 | Covered Parking | 32 | 3.00 x 4.20 | 12.60 | Included | B-103 | Covered Parking | 33 | 3.00 x 4.20 | 12.60 | Included | B-104 | Covered Parking | 34 | 3.00 x 4.20 | 12.60 | Included | B-105 | Covered Parking | 35 | 3.00 x 4.20 | 12.60 | Included | B-106 | Covered Parking | 36 | 3.00 x 4.20 | 12.60 | Included | B-107 | Covered Parking | 37 | 3.00 x 4.20 | 12.60 | Included | B-108 | Covered Parking | 38 | 3.00 x 4.20 | 12.60 | Included | B-201 | Covered Parking | 39 | 3.00 x 4.20 | 12.60 | Included | B-202 | Covered Parking | 40 | 3.00 x 4.20 | 12.60 | Included | B-203 | Covered Parking | 41 | 3.00 x 4.20 | 12.60 | Included | B-204 | Covered Parking | 42 | 3.00 x 4.20 | 12.60 | Included | B-205 | Covered Parking | 43 | 3.00 x 4.20 | 12.60 | Included | B-206 | Covered Parking | 44 | 3.00 x 4.20 | 12.60 | Included | B-207 | Covered Parking | 45 | 3.00 x 4.20 | 12.60 | Included | B-208 | Covered Parking | 46 | 3.00 x 4.20 | 12.60 | Included | B-301 | Covered Parking | 47 | 3.00 x 4.20 | 12.60 | Included | B-302 | Covered Parking | 48 | 3.00 x 4.20 | 12.60 | Included | B-303 | Covered Parking | 49 | 3.00 x 4.20 | 12.60 | Included | B-304 | Covered Parking | 50 | 3.00 x 4.20 | 12.60 | Included | B-305 | Covered Parking | 51 | 3.00 x 4.20 | 12.60 | Included | B-306 | Covered Parking | 52 | 3.00 x 4.20 | 12.60 | Included | B-307 | Covered Parking | 53 | 3.00 x 4.20 | 12.60 | Included | B-308 | Covered Parking | 54 | 3.00 x 4.20 | 12.60 | Included | B-401 | Covered Parking | 55 | 3.00 x 4.20 | 12.60 | Included | B-402 | Covered Parking | 56 | 3.00 x 4.20 | 12.60 | Included | B-403 | Covered Parking | 57 | 3.00 x 4.20 | 12.60 | Included | B-404 | Covered Parking | 58 | 3.00 x 4.20 | 12.60 | Included | B-405 | Covered Parking | 59 | 3.00 x 4.20 | 12.60 | Included | B-406 | Covered Parking | 60 | 3.00 x 4.20 | 12.60 | Included | B-407 | Covered Parking | 61 | 3.00 x 4.20 | 12.60 | Included | B-408 | Covered Parking | 62 | 3.00 x 4.20 | 12.60 | Included | B-501 | Covered Parking | 63 | 3.00 x 4.20 | 12.60 | Included | B-502 | Covered Parking | 64 | 3.00 x 4.20 | 12.60 | Included | B-503 | Covered Parking | 65 | 3.00 x 4.20 | 12.60 | Included | B-504 | Covered Parking | 66 | 3.00 x 4.20 | 12.60 | Included | B-505 | Covered Parking | 67 | 3.00 x 4.20 | 12.60 | Included | B-506 | Covered Parking | 68 | 3.00 x 4.20 | 12.60 | Included | B-507 | Covered Parking | 69 | 3.00 x 4.20 | 12.60 | Included | B-508 | Covered Parking | 70 | 3.00 x 4.20 | 12.60 | Included |
Particulars of Facilities | Status of the facility | Brief description of facility |
---|---|---|
Drinking Water Facility | Ground Water | Copy of Consent Letter |
Fire Fighting Facility | Yes | 15 mtrs in Height from ground level |
Emergency Evacuation Services | Yes | Staircase provided |
Use of Renewable Energy | No | |
Lift Facility | Yes | 1 No. of OTIS brand lift of 6 person capacity with ARD facility |
Market Complex | No | |
Community Hall | Yes | 85.736 Sqm |
Gymnasium | No | |
Swimming Pool | No | |
Play Ground | No | |
Park/Garden | No | |
Plantation Area | Yes | 663.68 Sqm |
Others(Please Specify) | No | |
Internal Road | Yes | 978.165 Sqm internal road with tile flooring |
External Road | Yes | 9.14 MTR wide road with black top |
Elecricity Supply | Yes | Copy of Consent Letter |
Other Amenities | No |
Generated by pacms.orera.in on date: 2024-05-17