1 |
Site Development
|
31-10-2021
|
Not yet started
|
|
2 |
Roof Casting
|
NA
|
NA
|
NA |
3 |
Ground Floor/Stilt Floor
|
31-01-2022
|
Not yet started
|
NA |
4 |
1 Floor
|
31-05-2022
|
Not yet started
|
NA |
5 |
2 Floor
|
31-07-2022
|
Not yet started
|
NA |
6 |
3 Floor
|
30-09-2022
|
Not yet started
|
NA |
7 |
4 Floor
|
30-11-2022
|
Not yet started
|
NA |
8 |
Brick Work & Plastering
|
NA
|
NA
|
NA |
9 |
Ground Floor/Stilt Floor
|
30-09-2022
|
Not yet started
|
NA |
10 |
1 Floor
|
30-11-2022
|
Not yet started
|
NA |
11 |
2 Floor
|
31-01-2023
|
Not yet started
|
NA |
12 |
3 Floor
|
31-03-2023
|
Not yet started
|
NA |
13 |
4 Floor
|
31-05-2023
|
Not yet started
|
NA |
14 |
Electrical Works
|
31-08-2023
|
Not yet started
|
NA |
15 |
Concealed Cabling including Plugs & switches
|
31-07-2023
|
Not yet started
|
NA |
16 |
Installation & Charging of Transformer
|
31-05-2023
|
Not yet started
|
NA |
17 |
Connection to Flats/Apartments
|
31-08-2023
|
Not yet started
|
NA |
18 |
PH works
|
30-11-2023
|
Not yet started
|
NA |
19 |
Laying of concealed Pipes
|
30-09-2023
|
Not yet started
|
NA |
20 |
PH Fittings
|
31-10-2023
|
Not yet started
|
NA |
21 |
Overhead Water Tanks
|
30-11-2023
|
Not yet started
|
NA |
22 |
Water Supply Connection to all units
|
30-11-2023
|
Not yet started
|
NA |
23 |
STP construction and completion
|
31-12-2023
|
Not yet started
|
NA |
24 |
Distempering & Colouring of all units and exteriors
|
18-08-2024
|
Not yet started
|
NA |
25 |
Fixation of doors and windows
|
18-08-2024
|
Not yet started
|
NA |
26 |
Scheduled Date of handing over possession
|
18-08-2024
|
Not yet started
|
NA |
27 |
Development of common areas, parks, gardens etc
|
18-08-2024
|
Not yet started
|
NA |
Updated Changes on 02-07-2022 |
28 |
Site Development
|
31-10-2021
|
Ongoing
|
NA |
29 |
NA
|
NA
|
NA
|
NA |
30 |
Ground Floor/Stilt Floor
|
31-01-2022
|
Completed
|
NA |
31 |
1 Floor
|
31-05-2022
|
Ongoing
|
NA |
32 |
2 Floor
|
31-07-2022
|
Not yet started
|
NA |
33 |
3 Floor
|
30-09-2022
|
Not yet started
|
NA |
34 |
4 Floor
|
30-11-2022
|
Not yet started
|
NA |
35 |
NA
|
NA
|
NA
|
NA |
36 |
Ground Floor/Stilt Floor
|
30-09-2022
|
Not yet started
|
NA |
37 |
1 Floor
|
30-11-2022
|
Not yet started
|
NA |
38 |
2 Floor
|
31-01-2023
|
Not yet started
|
NA |
39 |
3 Floor
|
31-03-2023
|
Not yet started
|
NA |
40 |
4 Floor
|
31-05-2023
|
Not yet started
|
NA |
41 |
Electrical Works
|
31-08-2023
|
Not yet started
|
NA |
42 |
Concealed Cabling including Plugs & switches
|
31-07-2023
|
Not yet started
|
NA |
43 |
Installation & Charging of Transformer
|
31-05-2023
|
Not yet started
|
NA |
44 |
Connection to Flats/Apartments
|
31-08-2023
|
Not yet started
|
NA |
45 |
PH works
|
30-11-2023
|
Not yet started
|
NA |
46 |
Laying of concealed Pipes
|
30-09-2023
|
Not yet started
|
NA |
47 |
PH Fittings
|
31-10-2023
|
Not yet started
|
NA |
48 |
Overhead Water Tanks
|
30-11-2023
|
Not yet started
|
NA |
49 |
Water Supply Connection to all units
|
30-11-2023
|
Not yet started
|
NA |
50 |
STP construction and completion
|
31-12-2023
|
Not yet started
|
NA |
51 |
Distempering & Colouring of all units and exteriors
|
18-08-2024
|
Not yet started
|
NA |
52 |
Fixation of doors and windows
|
18-08-2024
|
Not yet started
|
NA |
53 |
Scheduled Date of handing over possession
|
18-08-2024
|
Not yet started
|
NA |
54 |
Development of common areas, parks, gardens etc
|
18-08-2024
|
Not yet started
|
NA |
Updated Changes on 30-09-2022 |
55 |
Site Development
|
31-10-2021
|
Ongoing
|
NA |
56 |
NA
|
30-09-2022
|
ONGOING
|
NA |
57 |
Ground Floor/Stilt Floor
|
01-04-2022
|
Completed
|
NA |
58 |
1 Floor
|
31-05-2022
|
Completed
|
NA |
59 |
2 Floor
|
15-09-2022
|
Completed
|
NA |
60 |
3 Floor
|
31-10-2022
|
Not yet started
|
NA |
61 |
4 Floor
|
15-12-2022
|
Not yet started
|
NA |
62 |
NA
|
30-09-2022
|
ONGOING
|
NA |
63 |
Ground Floor/Stilt Floor
|
01-04-2022
|
Completed
|
NA |
64 |
1 Floor
|
31-05-2022
|
Completed
|
NA |
65 |
2 Floor
|
15-09-2022
|
Completed
|
NA |
66 |
3 Floor
|
31-03-2023
|
Not yet started
|
NA |
67 |
4 Floor
|
31-05-2023
|
Not yet started
|
NA |
68 |
Electrical Works
|
31-08-2023
|
Not yet started
|
NA |
69 |
Concealed Cabling including Plugs & switches
|
31-07-2023
|
Not yet started
|
NA |
70 |
Installation & Charging of Transformer
|
31-05-2023
|
Not yet started
|
NA |
71 |
Connection to Flats/Apartments
|
31-08-2023
|
Not yet started
|
NA |
72 |
PH works
|
30-11-2023
|
Not yet started
|
NA |
73 |
Laying of concealed Pipes
|
30-09-2023
|
Not yet started
|
NA |
74 |
PH Fittings
|
31-10-2023
|
Not yet started
|
NA |
75 |
Overhead Water Tanks
|
30-11-2023
|
Not yet started
|
NA |
76 |
Water Supply Connection to all units
|
30-11-2023
|
Not yet started
|
NA |
77 |
STP construction and completion
|
31-12-2023
|
Not yet started
|
NA |
78 |
Distempering & Colouring of all units and exteriors
|
18-08-2024
|
Not yet started
|
NA |
79 |
Fixation of doors and windows
|
18-08-2024
|
Not yet started
|
NA |
80 |
Scheduled Date of handing over possession
|
18-08-2024
|
Not yet started
|
NA |
81 |
Development of common areas, parks, gardens etc
|
18-08-2024
|
Not yet started
|
NA |
Updated Changes on 14-07-2023 |
82 |
Site Development
|
31-10-2021
|
Ongoing
|
NA |
83 |
NA
|
30-09-2022
|
ONGOING
|
NA |
84 |
Ground Floor/Stilt Floor
|
01-04-2022
|
Completed
|
NA |
85 |
1 Floor
|
31-05-2022
|
Completed
|
NA |
86 |
2 Floor
|
15-09-2022
|
Completed
|
NA |
87 |
3 Floor
|
31-10-2022
|
Completed
|
NA |
88 |
4 Floor
|
28-12-2022
|
Completed
|
NA |
89 |
NA
|
28-12-2022
|
Completed
|
NA |
90 |
Ground Floor/Stilt Floor
|
01-04-2022
|
Completed
|
NA |
91 |
1 Floor
|
31-05-2022
|
Completed
|
NA |
92 |
2 Floor
|
15-09-2022
|
Completed
|
NA |
93 |
3 Floor
|
31-10-2022
|
Completed
|
NA |
94 |
4 Floor
|
28-12-2022
|
Completed
|
NA |
95 |
Electrical Works
|
31-08-2023
|
Ongoing
|
NA |
96 |
Concealed Cabling including Plugs & switches
|
31-07-2023
|
Ongoing
|
NA |
97 |
Installation & Charging of Transformer
|
31-05-2023
|
Not yet started
|
NA |
98 |
Connection to Flats/Apartments
|
31-08-2023
|
Not yet started
|
NA |
99 |
PH works
|
30-11-2023
|
Not yet started
|
NA |
100 |
Laying of concealed Pipes
|
30-09-2023
|
Ongoing
|
NA |
101 |
PH Fittings
|
31-10-2023
|
Not yet started
|
NA |
102 |
Overhead Water Tanks
|
30-11-2023
|
Completed
|
NA |
103 |
Water Supply Connection to all units
|
30-11-2023
|
Not yet started
|
NA |
104 |
STP construction and completion
|
31-12-2023
|
Completed
|
NA |
105 |
Distempering & Colouring of all units and exteriors
|
18-08-2024
|
Not yet started
|
NA |
106 |
Fixation of doors and windows
|
18-08-2024
|
Not yet started
|
NA |
107 |
Scheduled Date of handing over possession
|
18-08-2024
|
Not yet started
|
NA |
108 |
Development of common areas, parks, gardens etc
|
18-08-2024
|
Not yet started
|
NA |
Updated Changes on 12-10-2023 |
109 |
Site Development
|
31-10-2021
|
Ongoing
|
NA |
110 |
NA
|
30-09-2022
|
ONGOING
|
NA |
111 |
Ground Floor/Stilt Floor
|
01-04-2022
|
Completed
|
NA |
112 |
1 Floor
|
31-05-2022
|
Completed
|
NA |
113 |
2 Floor
|
15-09-2022
|
Completed
|
NA |
114 |
3 Floor
|
31-10-2022
|
Completed
|
NA |
115 |
4 Floor
|
28-12-2022
|
Completed
|
NA |
116 |
NA
|
28-12-2022
|
Completed
|
NA |
117 |
Ground Floor/Stilt Floor
|
01-04-2022
|
Completed
|
NA |
118 |
1 Floor
|
31-05-2022
|
Completed
|
NA |
119 |
2 Floor
|
15-09-2022
|
Completed
|
NA |
120 |
3 Floor
|
31-10-2022
|
Completed
|
NA |
121 |
4 Floor
|
28-12-2022
|
Completed
|
NA |
122 |
Electrical Works
|
31-08-2023
|
Ongoing
|
NA |
123 |
Concealed Cabling including Plugs & switches
|
31-07-2023
|
Ongoing
|
NA |
124 |
Installation & Charging of Transformer
|
31-05-2023
|
Not yet started
|
NA |
125 |
Connection to Flats/Apartments
|
31-08-2023
|
Not yet started
|
NA |
126 |
PH works
|
30-11-2023
|
Ongoing
|
NA |
127 |
Laying of concealed Pipes
|
30-09-2023
|
Ongoing
|
NA |
128 |
PH Fittings
|
31-10-2023
|
Not yet started
|
NA |
129 |
Overhead Water Tanks
|
30-11-2023
|
Completed
|
NA |
130 |
Water Supply Connection to all units
|
30-11-2023
|
Not yet started
|
NA |
131 |
STP construction and completion
|
31-12-2023
|
Completed
|
NA |
132 |
Distempering & Colouring of all units and exteriors
|
18-08-2024
|
Ongoing
|
NA |
133 |
Fixation of doors and windows
|
18-08-2024
|
Ongoing
|
NA |
134 |
Scheduled Date of handing over possession
|
18-08-2024
|
18-08-2024
|
NA |
135 |
Development of common areas, parks, gardens etc
|
18-08-2024
|
Not yet started
|
NA |
Updated Changes on 15-01-2024 |
136 |
Site Development
|
31-10-2021
|
Ongoing
|
NA |
137 |
NA
|
30-09-2022
|
ONGOING
|
NA |
138 |
Ground Floor/Stilt Floor
|
01-04-2022
|
Completed
|
NA |
139 |
1 Floor
|
31-05-2022
|
Completed
|
NA |
140 |
2 Floor
|
15-09-2022
|
Completed
|
NA |
141 |
3 Floor
|
31-10-2022
|
Completed
|
NA |
142 |
4 Floor
|
28-12-2022
|
Completed
|
NA |
143 |
NA
|
28-12-2022
|
Completed
|
NA |
144 |
Ground Floor/Stilt Floor
|
01-04-2022
|
Completed
|
NA |
145 |
1 Floor
|
31-05-2022
|
Completed
|
NA |
146 |
2 Floor
|
15-09-2022
|
Completed
|
NA |
147 |
3 Floor
|
31-10-2022
|
Completed
|
NA |
148 |
4 Floor
|
28-12-2022
|
Completed
|
NA |
149 |
Electrical Works
|
31-08-2023
|
Ongoing
|
NA |
150 |
Concealed Cabling including Plugs & switches
|
31-07-2023
|
Ongoing
|
NA |
151 |
Installation & Charging of Transformer
|
31-05-2023
|
Not yet started
|
NA |
152 |
Connection to Flats/Apartments
|
31-08-2023
|
Not yet started
|
NA |
153 |
PH works
|
30-11-2023
|
Ongoing
|
NA |
154 |
Laying of concealed Pipes
|
30-09-2023
|
Completed
|
NA |
155 |
PH Fittings
|
31-10-2023
|
Completed
|
NA |
156 |
Overhead Water Tanks
|
30-11-2023
|
Completed
|
NA |
157 |
Water Supply Connection to all units
|
30-11-2023
|
Completed
|
NA |
158 |
STP construction and completion
|
31-12-2023
|
Completed
|
NA |
159 |
Distempering & Colouring of all units and exteriors
|
18-08-2024
|
Completed
|
NA |
160 |
Fixation of doors and windows
|
18-08-2024
|
Completed
|
NA |
161 |
Scheduled Date of handing over possession
|
18-08-2024
|
18-08-2024
|
NA |
162 |
Development of common areas, parks, gardens etc
|
18-08-2024
|
Ongoing
|
NA |
Updated Changes on 13-04-2024 |
163 |
Site Development
|
31-10-2021
|
COMPLETE
|
NA |
164 |
NA
|
30-09-2022
|
COMPLETE
|
NA |
165 |
Ground Floor/Stilt Floor
|
01-04-2022
|
Completed
|
NA |
166 |
1 Floor
|
31-05-2022
|
Completed
|
NA |
167 |
2 Floor
|
15-09-2022
|
Completed
|
NA |
168 |
3 Floor
|
31-10-2022
|
Completed
|
NA |
169 |
4 Floor
|
28-12-2022
|
Completed
|
NA |
170 |
NA
|
28-12-2022
|
Completed
|
NA |
171 |
Ground Floor/Stilt Floor
|
01-04-2022
|
Completed
|
NA |
172 |
1 Floor
|
31-05-2022
|
Completed
|
NA |
173 |
2 Floor
|
15-09-2022
|
Completed
|
NA |
174 |
3 Floor
|
31-10-2022
|
Completed
|
NA |
175 |
4 Floor
|
28-12-2022
|
Completed
|
NA |
176 |
Electrical Works
|
31-08-2023
|
COMPLETE
|
NA |
177 |
Concealed Cabling including Plugs & switches
|
31-07-2023
|
COMPLETE
|
NA |
178 |
Installation & Charging of Transformer
|
31-05-2023
|
Under Process
|
NA |
179 |
Connection to Flats/Apartments
|
31-08-2023
|
Under Process
|
NA |
180 |
PH works
|
30-11-2023
|
COMPLETE
|
NA |
181 |
Laying of concealed Pipes
|
30-09-2023
|
Completed
|
NA |
182 |
PH Fittings
|
31-10-2023
|
Completed
|
NA |
183 |
Overhead Water Tanks
|
30-11-2023
|
Completed
|
NA |
184 |
Water Supply Connection to all units
|
30-11-2023
|
Completed
|
NA |
185 |
STP construction and completion
|
31-12-2023
|
Completed
|
NA |
186 |
Distempering & Colouring of all units and exteriors
|
18-08-2024
|
Completed
|
NA |
187 |
Fixation of doors and windows
|
18-08-2024
|
Completed
|
NA |
188 |
Scheduled Date of handing over possession
|
18-08-2024
|
18-08-2024
|
NA |
189 |
Development of common areas, parks, gardens etc
|
18-08-2024
|
COMPLETE
|
NA |