Promoter Details
Promoter Name :
HARSH WARDHAN KANDOI
Project Name :
Trinity Crystal
Project Location :
(Residential Project, S+4, No. of Units-16)

Form- I

A. Promoter's Details

:  M/s. Trinity Green Estates LLP :  Partnership
:  AAK-4156 :View
NA :  3rd Floor Kanshree Villa, Gayatri Vihar, Patia, Bhubaneswar
:  3rd floor, Kanshree Villa, Gayatri Vihar, Patia, Bhubaneswar, Dist. Khordha, Odisha :  navalmahajan@outlook.com
:  2311339 :  9437081855
:  AAMFT8825G :View
:  Approx 3 years :  Approx 3 years
:  www.trinityestates.in

B. Details of Board of Directors / Partners / MC Members

:  HARSH WARDHAN KANDOI :  
:  Partner :  APRPK4134R
:PAN Card :  harshwardhankandoi@gmail.com
:  MBA :  9437081855
:  3 years
:  Yes :  NA
:  NAVAL MAHAJAN :  
:  Partner :  ARJPM4352P
:PAN Card :  navalmahajan@outlook.com
:  B.TECH :  9776312020
:  3 years
:  Yes :  NA
:  PRATEEK GUPTA :  
:  Partner :  AWDPG1449A
:PAN Card :  prateekarch08@gmail.com
:  B.ARCH :  9937004761
:  3 year
:  Yes :  NA

Annexure-1

Details of last projects already implemented (Ongoing or Complete)

Annexure-2

Details of the project to be registered

:   New :  Trinity Crystal
:  Residential :  (Residential Project, S+4, No. of Units-16)
:  Khordha :  Bhubaneswar
:  751003 :  Urban Local Body
:  Bhubaneswar Municipal Corporation
:  S+4 storey Residential building :  NA

Land Details of the Project


:  6734 :  1988/985
:  Ghatikia :  595
:  Yes
No :  View
:  View
:  Other Person
:  Sunita Gupta & Kabita Nayak :  The land owner Sunita Gupta & Kabita Nayak executed development agreement with Trinity Green Estates LLP. The promoter is also the power holder over the land.
: No
: Yes
:  11132007999 :  31-12-2020
:  Sub-Registrar, Khandagiri :  Attached

Development Agreement

: Yes
Serial No. Particulars of the Person Land/Plot Details Share of the Person Document Attached
1 Sunita Gupta & Kabita Nayak Plot No.6734, Khata No.1988/985 35%   Agreement Copy

Building Plan

  View   View
  Download site plan 31-07-2024

Conditions of building plan approval

Sl. No. Description of Conditions Schedule date of compliance Present Status
1 Parking space measuring =386.973 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 12-09-2021 Not started
2 The land over which construction is proposed is accessible by an approved means of access of 60.0 Mt(Sixty point Zero)in width. 12-09-2021 Not started
3 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 12-09-2021 Not started
4 Storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per ODA(Planning& Building Standards)Rules,2020. 12-09-2021 Not started
5 Plantation as required under the provision under rule 30 of ODA (Planning & Building Standards)Rules, 2020.shallbe strictly adhered 12-09-2021 Not started

Layout Plan

: Yes :  View

Location Map with geo-coordinates of bend points

Point No. Latitude Longitude
1 20°16'19.1"N 85°45'30.0"E
2 20°16'19.2"N 85°45'30.6"E
3 20°16'19.3"N 85°45'30.9"E
4 20°16'18.7"N 85°45'31.1"E
5 20°16'18.4"N 85°45'30.2"E
View

Milestone of Project Construction

Description* Scheduled date of completion Current Status Site Images
Site Development 31-10-2021 Not yet started
Roof Casting NA NA NA
Ground Floor/Stilt Floor 31-01-2022 Not yet started NA
1 Floor 31-05-2022 Not yet started NA
2 Floor 31-07-2022 Not yet started NA
3 Floor 30-09-2022 Not yet started NA
4 Floor 30-11-2022 Not yet started NA
Brick Work & Plastering NA NA NA
Ground Floor/Stilt Floor 30-09-2022 Not yet started NA
1 Floor 30-11-2022 Not yet started NA
2 Floor 31-01-2023 Not yet started NA
3 Floor 31-03-2023 Not yet started NA
4 Floor 31-05-2023 Not yet started NA
Electrical Works 31-08-2023 Not yet started NA
Concealed Cabling including Plugs & switches 31-07-2023 Not yet started NA
Installation & Charging of Transformer 31-05-2023 Not yet started NA
Connection to Flats/Apartments 31-08-2023 Not yet started NA
PH works 30-11-2023 Not yet started NA
Laying of concealed Pipes 30-09-2023 Not yet started NA
PH Fittings 31-10-2023 Not yet started NA
Overhead Water Tanks 30-11-2023 Not yet started NA
Water Supply Connection to all units 30-11-2023 Not yet started NA
STP construction and completion 31-12-2023 Not yet started NA
Distempering & Colouring of all units and exteriors 18-08-2024 Not yet started NA
Fixation of doors and windows 18-08-2024 Not yet started NA
Scheduled Date of handing over possession 18-08-2024 Not yet started NA
Development of common areas, parks, gardens etc 18-08-2024 Not yet started NA
Site Development 31-10-2021 Ongoing NA
NA NA NA NA
Ground Floor/Stilt Floor 31-01-2022 Completed NA
1 Floor 31-05-2022 Ongoing NA
2 Floor 31-07-2022 Not yet started NA
3 Floor 30-09-2022 Not yet started NA
4 Floor 30-11-2022 Not yet started NA
NA NA NA NA
Ground Floor/Stilt Floor 30-09-2022 Not yet started NA
1 Floor 30-11-2022 Not yet started NA
2 Floor 31-01-2023 Not yet started NA
3 Floor 31-03-2023 Not yet started NA
4 Floor 31-05-2023 Not yet started NA
Electrical Works 31-08-2023 Not yet started NA
Concealed Cabling including Plugs & switches 31-07-2023 Not yet started NA
Installation & Charging of Transformer 31-05-2023 Not yet started NA
Connection to Flats/Apartments 31-08-2023 Not yet started NA
PH works 30-11-2023 Not yet started NA
Laying of concealed Pipes 30-09-2023 Not yet started NA
PH Fittings 31-10-2023 Not yet started NA
Overhead Water Tanks 30-11-2023 Not yet started NA
Water Supply Connection to all units 30-11-2023 Not yet started NA
STP construction and completion 31-12-2023 Not yet started NA
Distempering & Colouring of all units and exteriors 18-08-2024 Not yet started NA
Fixation of doors and windows 18-08-2024 Not yet started NA
Scheduled Date of handing over possession 18-08-2024 Not yet started NA
Development of common areas, parks, gardens etc 18-08-2024 Not yet started NA
Site Development 31-10-2021 Ongoing NA
NA 30-09-2022 ONGOING NA
Ground Floor/Stilt Floor 01-04-2022 Completed NA
1 Floor 31-05-2022 Completed NA
2 Floor 15-09-2022 Completed NA
3 Floor 31-10-2022 Not yet started NA
4 Floor 15-12-2022 Not yet started NA
NA 30-09-2022 ONGOING NA
Ground Floor/Stilt Floor 01-04-2022 Completed NA
1 Floor 31-05-2022 Completed NA
2 Floor 15-09-2022 Completed NA
3 Floor 31-03-2023 Not yet started NA
4 Floor 31-05-2023 Not yet started NA
Electrical Works 31-08-2023 Not yet started NA
Concealed Cabling including Plugs & switches 31-07-2023 Not yet started NA
Installation & Charging of Transformer 31-05-2023 Not yet started NA
Connection to Flats/Apartments 31-08-2023 Not yet started NA
PH works 30-11-2023 Not yet started NA
Laying of concealed Pipes 30-09-2023 Not yet started NA
PH Fittings 31-10-2023 Not yet started NA
Overhead Water Tanks 30-11-2023 Not yet started NA
Water Supply Connection to all units 30-11-2023 Not yet started NA
STP construction and completion 31-12-2023 Not yet started NA
Distempering & Colouring of all units and exteriors 18-08-2024 Not yet started NA
Fixation of doors and windows 18-08-2024 Not yet started NA
Scheduled Date of handing over possession 18-08-2024 Not yet started NA
Development of common areas, parks, gardens etc 18-08-2024 Not yet started NA
Site Development 31-10-2021 Ongoing NA
NA 30-09-2022 ONGOING NA
Ground Floor/Stilt Floor 01-04-2022 Completed NA
1 Floor 31-05-2022 Completed NA
2 Floor 15-09-2022 Completed NA
3 Floor 31-10-2022 Completed NA
4 Floor 28-12-2022 Completed NA
NA 28-12-2022 Completed NA
Ground Floor/Stilt Floor 01-04-2022 Completed NA
1 Floor 31-05-2022 Completed NA
2 Floor 15-09-2022 Completed NA
3 Floor 31-10-2022 Completed NA
4 Floor 28-12-2022 Completed NA
Electrical Works 31-08-2023 Ongoing NA
Concealed Cabling including Plugs & switches 31-07-2023 Ongoing NA
Installation & Charging of Transformer 31-05-2023 Not yet started NA
Connection to Flats/Apartments 31-08-2023 Not yet started NA
PH works 30-11-2023 Not yet started NA
Laying of concealed Pipes 30-09-2023 Ongoing NA
PH Fittings 31-10-2023 Not yet started NA
Overhead Water Tanks 30-11-2023 Completed NA
Water Supply Connection to all units 30-11-2023 Not yet started NA
STP construction and completion 31-12-2023 Completed NA
Distempering & Colouring of all units and exteriors 18-08-2024 Not yet started NA
Fixation of doors and windows 18-08-2024 Not yet started NA
Scheduled Date of handing over possession 18-08-2024 Not yet started NA
Development of common areas, parks, gardens etc 18-08-2024 Not yet started NA
Site Development 31-10-2021 Ongoing NA
NA 30-09-2022 ONGOING NA
Ground Floor/Stilt Floor 01-04-2022 Completed NA
1 Floor 31-05-2022 Completed NA
2 Floor 15-09-2022 Completed NA
3 Floor 31-10-2022 Completed NA
4 Floor 28-12-2022 Completed NA
NA 28-12-2022 Completed NA
Ground Floor/Stilt Floor 01-04-2022 Completed NA
1 Floor 31-05-2022 Completed NA
2 Floor 15-09-2022 Completed NA
3 Floor 31-10-2022 Completed NA
4 Floor 28-12-2022 Completed NA
Electrical Works 31-08-2023 Ongoing NA
Concealed Cabling including Plugs & switches 31-07-2023 Ongoing NA
Installation & Charging of Transformer 31-05-2023 Not yet started NA
Connection to Flats/Apartments 31-08-2023 Not yet started NA
PH works 30-11-2023 Ongoing NA
Laying of concealed Pipes 30-09-2023 Ongoing NA
PH Fittings 31-10-2023 Not yet started NA
Overhead Water Tanks 30-11-2023 Completed NA
Water Supply Connection to all units 30-11-2023 Not yet started NA
STP construction and completion 31-12-2023 Completed NA
Distempering & Colouring of all units and exteriors 18-08-2024 Ongoing NA
Fixation of doors and windows 18-08-2024 Ongoing NA
Scheduled Date of handing over possession 18-08-2024 18-08-2024 NA
Development of common areas, parks, gardens etc 18-08-2024 Not yet started NA
Site Development 31-10-2021 Ongoing NA
NA 30-09-2022 ONGOING NA
Ground Floor/Stilt Floor 01-04-2022 Completed NA
1 Floor 31-05-2022 Completed NA
2 Floor 15-09-2022 Completed NA
3 Floor 31-10-2022 Completed NA
4 Floor 28-12-2022 Completed NA
NA 28-12-2022 Completed NA
Ground Floor/Stilt Floor 01-04-2022 Completed NA
1 Floor 31-05-2022 Completed NA
2 Floor 15-09-2022 Completed NA
3 Floor 31-10-2022 Completed NA
4 Floor 28-12-2022 Completed NA
Electrical Works 31-08-2023 Ongoing NA
Concealed Cabling including Plugs & switches 31-07-2023 Ongoing NA
Installation & Charging of Transformer 31-05-2023 Not yet started NA
Connection to Flats/Apartments 31-08-2023 Not yet started NA
PH works 30-11-2023 Ongoing NA
Laying of concealed Pipes 30-09-2023 Completed NA
PH Fittings 31-10-2023 Completed NA
Overhead Water Tanks 30-11-2023 Completed NA
Water Supply Connection to all units 30-11-2023 Completed NA
STP construction and completion 31-12-2023 Completed NA
Distempering & Colouring of all units and exteriors 18-08-2024 Completed NA
Fixation of doors and windows 18-08-2024 Completed NA
Scheduled Date of handing over possession 18-08-2024 18-08-2024 NA
Development of common areas, parks, gardens etc 18-08-2024 Ongoing NA
Site Development 31-10-2021 COMPLETE NA
NA 30-09-2022 COMPLETE NA
Ground Floor/Stilt Floor 01-04-2022 Completed NA
1 Floor 31-05-2022 Completed NA
2 Floor 15-09-2022 Completed NA
3 Floor 31-10-2022 Completed NA
4 Floor 28-12-2022 Completed NA
NA 28-12-2022 Completed NA
Ground Floor/Stilt Floor 01-04-2022 Completed NA
1 Floor 31-05-2022 Completed NA
2 Floor 15-09-2022 Completed NA
3 Floor 31-10-2022 Completed NA
4 Floor 28-12-2022 Completed NA
Electrical Works 31-08-2023 COMPLETE NA
Concealed Cabling including Plugs & switches 31-07-2023 COMPLETE NA
Installation & Charging of Transformer 31-05-2023 Under Process NA
Connection to Flats/Apartments 31-08-2023 Under Process NA
PH works 30-11-2023 COMPLETE NA
Laying of concealed Pipes 30-09-2023 Completed NA
PH Fittings 31-10-2023 Completed NA
Overhead Water Tanks 30-11-2023 Completed NA
Water Supply Connection to all units 30-11-2023 Completed NA
STP construction and completion 31-12-2023 Completed NA
Distempering & Colouring of all units and exteriors 18-08-2024 Completed NA
Fixation of doors and windows 18-08-2024 Completed NA
Scheduled Date of handing over possession 18-08-2024 18-08-2024 NA
Development of common areas, parks, gardens etc 18-08-2024 COMPLETE NA

Category and no. of units to be developed

:  Residential
:  
:  16
:  
:  
:  
Residential Flats/ House
S. No. Flat No./ House No.

Area in square metres

Ownership
Carpet Area Balcony Area Exclusive Open Terrace Area
1 1A 83 7.16 Nil Land Owner
2 2A 83 7.16 Nil Land Owner
3 3A 83 7.16 Nil Promoter
4 4A 83 7.16 Nil Promoter
5 1B 84.60 8.92 Nil Promoter
6 2B 84.60 8.92 Nil Promoter
7 3B 84.60 8.92 Nil Promoter
8 4B 84.60 8.92 Nil Promoter
9 1C 82.55 7.16 Nil Promoter
10 2C 82.55 7.16 Nil Land Owner
11 3C 82.55 7.16 Nil Land Owner
12 4C 82.55 7.16 Nil Promoter
13 1D 93.97 7.16 Nil Land Owner
14 2D 93.97 7.16 Nil Land Owner
15 3D 93.97 7.16 Nil Promoter
16 4D 77.50 2.97 Nil Promoter
Types of garages and parking
House No. Type of Garage/ Parking allotted Serial No., if any Dimension (Length x Width) in Metres Floor area in sq. metres Garage/Parking area cost is included or additional
1A Covered Parking 1A 6.07X2.54 15.41 Included
2A Covered Parking 2A 6.07X2.54 15.41 Included
3A Covered Parking 3A 6.07X2.54 15.41 Included
4A Covered Parking 4A 6.07X2.54 15.41 Included
1B Covered Parking 1B 6.07X2.54 15.41 Included
2B Covered Parking 2B 6.07X2.54 15.41 Included
3B Covered Parking 3B 6.07X2.54 15.41 Included
4B Covered Parking 4B 6.07X2.54 15.41 Included
1C Covered Parking 1C 6.07X2.54 15.41 Included
2C Covered Parking 2C 6.07X2.54 15.41 Included
3C Covered Parking 3C 6.07X2.54 15.41 Included
4C Covered Parking 4C 6.07X2.54 15.41 Included
1D Covered Parking 1D 6.07X2.54 15.41 Included
2D Covered Parking 2D 6.07X2.54 15.41 Included
3D Covered Parking 3D 6.07X2.54 15.41 Included
4D Covered Parking 4D 6.07X2.54 15.41 Included
Yes

Facilities to be provided

Particulars of Facilities Status of the facility Brief description of facility
Drinking Water Facility Ground Water Copy of Consent Letter
Fire Fighting Facility Yes Staircase
Emergency Evacuation Services Yes Staircase
Use of Renewable Energy No
Lift Facility Yes 1 No. of OTIS brand lift of 6 passenger capacity with ARD facility
Market Complex No
Community Hall Yes 18.75 sqm community hall with tile flooring
Gymnasium No
Swimming Pool No
Play Ground No
Park/Garden No
Plantation Area Yes 119.43 sqm
Others(Please Specify) No
Internal Road Yes 2 mtr width & 81.68 mtr length internal road with concrete flooring
External Road Yes 60 mtr wide road with blacktop
Elecricity Supply Yes Copy of Consent Letter
Other Amenities No

Bank Particulars of the Project

  ICICI BANK
  COLLEGE SQUARE CUTTACK BRANCH
  243305002668
  ICIC0002433
   View
  2321664
  9692667770

Particulars of Architect/Construction Engineer/Contractor/Chartered Accountant

Name position Address with mobile number and email address Registration number Key real estate projects Is active Effective date
PRATEEK GUPTA Architect FLAT NO-3A,PLOT NO-181, GAYATRI VIHAR, NEAR IOCL,PATIA,9937004761, Email-prateekarch08@gmail.com CA/2009/45972 TRINITY KALINGA
NAGENDRA KUMAR PARIDA Construction Engineer NILAKANTHA NAGAR, BHUBANESWAR,9437013988, Email-nagendraparida@gmail.com SER/015/BDA TRINITY KALINGA
ARUN KUMAR BHAWSINKA Chartered Accountant MATA MATH,CANTONMENT ROAD,CUTTACK,9437027722, Email-sbn.ctc@gmail.com M.No.057589 TRINITY KALINGA

Financial Details

:  358.09 :   View
  31-12-2024 :  150
:  208.09 :  0

Documents Attached

Description of Document Option Documents
Fire Safety Certificate Undertaking Attached
Affidavit in Form-A as per clause-l of sub-section-2 of section-4 of the Act Yes Attached
Allotment letter format Yes Attached
Conveyance Deed Format Yes Attached
Affidavit to adopt agreement for sale format as per Rule-8(1) of ORE (R and D) Rules, 2017 Yes Attached
Annual Report 2019-20 Attached
Annual Report 2020-21 Attached
Annual Report 2021-22 Attached
IT Return 2019-20 Attached
IT Return 2020-21 Attached
IT Return 2021-22 Attached
Audit Report 2019-20 Attached
Audit Report 2020-21 Attached
Audit Report 2021-22 Attached


Other documents

“I undertake that the information submitted by me in this application are correct and true to best my knowledge. I also understand that providing false or wrong information is punishable under the Section-60 of the Real Estate (Regulation & Development) Act, 2016. I also further understand that furnishing wrong or false information will lead to rejection of my application registration of the project with forfeiture of registration fee and other charges deposited by me.”
  

Construction Progress

Updated Construction Progress

SL NO. Description Scheduled date of completion Current Status Remarks
1 Site Development 31-10-2021 Not yet started
2 Roof Casting NA NA NA
3 Ground Floor/Stilt Floor 31-01-2022 Not yet started NA
4 1 Floor 31-05-2022 Not yet started NA
5 2 Floor 31-07-2022 Not yet started NA
6 3 Floor 30-09-2022 Not yet started NA
7 4 Floor 30-11-2022 Not yet started NA
8 Brick Work & Plastering NA NA NA
9 Ground Floor/Stilt Floor 30-09-2022 Not yet started NA
10 1 Floor 30-11-2022 Not yet started NA
11 2 Floor 31-01-2023 Not yet started NA
12 3 Floor 31-03-2023 Not yet started NA
13 4 Floor 31-05-2023 Not yet started NA
14 Electrical Works 31-08-2023 Not yet started NA
15 Concealed Cabling including Plugs & switches 31-07-2023 Not yet started NA
16 Installation & Charging of Transformer 31-05-2023 Not yet started NA
17 Connection to Flats/Apartments 31-08-2023 Not yet started NA
18 PH works 30-11-2023 Not yet started NA
19 Laying of concealed Pipes 30-09-2023 Not yet started NA
20 PH Fittings 31-10-2023 Not yet started NA
21 Overhead Water Tanks 30-11-2023 Not yet started NA
22 Water Supply Connection to all units 30-11-2023 Not yet started NA
23 STP construction and completion 31-12-2023 Not yet started NA
24 Distempering & Colouring of all units and exteriors 18-08-2024 Not yet started NA
25 Fixation of doors and windows 18-08-2024 Not yet started NA
26 Scheduled Date of handing over possession 18-08-2024 Not yet started NA
27 Development of common areas, parks, gardens etc 18-08-2024 Not yet started NA
Updated Changes on 02-07-2022
28 Site Development 31-10-2021 Ongoing NA
29 NA NA NA NA
30 Ground Floor/Stilt Floor 31-01-2022 Completed NA
31 1 Floor 31-05-2022 Ongoing NA
32 2 Floor 31-07-2022 Not yet started NA
33 3 Floor 30-09-2022 Not yet started NA
34 4 Floor 30-11-2022 Not yet started NA
35 NA NA NA NA
36 Ground Floor/Stilt Floor 30-09-2022 Not yet started NA
37 1 Floor 30-11-2022 Not yet started NA
38 2 Floor 31-01-2023 Not yet started NA
39 3 Floor 31-03-2023 Not yet started NA
40 4 Floor 31-05-2023 Not yet started NA
41 Electrical Works 31-08-2023 Not yet started NA
42 Concealed Cabling including Plugs & switches 31-07-2023 Not yet started NA
43 Installation & Charging of Transformer 31-05-2023 Not yet started NA
44 Connection to Flats/Apartments 31-08-2023 Not yet started NA
45 PH works 30-11-2023 Not yet started NA
46 Laying of concealed Pipes 30-09-2023 Not yet started NA
47 PH Fittings 31-10-2023 Not yet started NA
48 Overhead Water Tanks 30-11-2023 Not yet started NA
49 Water Supply Connection to all units 30-11-2023 Not yet started NA
50 STP construction and completion 31-12-2023 Not yet started NA
51 Distempering & Colouring of all units and exteriors 18-08-2024 Not yet started NA
52 Fixation of doors and windows 18-08-2024 Not yet started NA
53 Scheduled Date of handing over possession 18-08-2024 Not yet started NA
54 Development of common areas, parks, gardens etc 18-08-2024 Not yet started NA
Updated Changes on 30-09-2022
55 Site Development 31-10-2021 Ongoing NA
56 NA 30-09-2022 ONGOING NA
57 Ground Floor/Stilt Floor 01-04-2022 Completed NA
58 1 Floor 31-05-2022 Completed NA
59 2 Floor 15-09-2022 Completed NA
60 3 Floor 31-10-2022 Not yet started NA
61 4 Floor 15-12-2022 Not yet started NA
62 NA 30-09-2022 ONGOING NA
63 Ground Floor/Stilt Floor 01-04-2022 Completed NA
64 1 Floor 31-05-2022 Completed NA
65 2 Floor 15-09-2022 Completed NA
66 3 Floor 31-03-2023 Not yet started NA
67 4 Floor 31-05-2023 Not yet started NA
68 Electrical Works 31-08-2023 Not yet started NA
69 Concealed Cabling including Plugs & switches 31-07-2023 Not yet started NA
70 Installation & Charging of Transformer 31-05-2023 Not yet started NA
71 Connection to Flats/Apartments 31-08-2023 Not yet started NA
72 PH works 30-11-2023 Not yet started NA
73 Laying of concealed Pipes 30-09-2023 Not yet started NA
74 PH Fittings 31-10-2023 Not yet started NA
75 Overhead Water Tanks 30-11-2023 Not yet started NA
76 Water Supply Connection to all units 30-11-2023 Not yet started NA
77 STP construction and completion 31-12-2023 Not yet started NA
78 Distempering & Colouring of all units and exteriors 18-08-2024 Not yet started NA
79 Fixation of doors and windows 18-08-2024 Not yet started NA
80 Scheduled Date of handing over possession 18-08-2024 Not yet started NA
81 Development of common areas, parks, gardens etc 18-08-2024 Not yet started NA
Updated Changes on 14-07-2023
82 Site Development 31-10-2021 Ongoing NA
83 NA 30-09-2022 ONGOING NA
84 Ground Floor/Stilt Floor 01-04-2022 Completed NA
85 1 Floor 31-05-2022 Completed NA
86 2 Floor 15-09-2022 Completed NA
87 3 Floor 31-10-2022 Completed NA
88 4 Floor 28-12-2022 Completed NA
89 NA 28-12-2022 Completed NA
90 Ground Floor/Stilt Floor 01-04-2022 Completed NA
91 1 Floor 31-05-2022 Completed NA
92 2 Floor 15-09-2022 Completed NA
93 3 Floor 31-10-2022 Completed NA
94 4 Floor 28-12-2022 Completed NA
95 Electrical Works 31-08-2023 Ongoing NA
96 Concealed Cabling including Plugs & switches 31-07-2023 Ongoing NA
97 Installation & Charging of Transformer 31-05-2023 Not yet started NA
98 Connection to Flats/Apartments 31-08-2023 Not yet started NA
99 PH works 30-11-2023 Not yet started NA
100 Laying of concealed Pipes 30-09-2023 Ongoing NA
101 PH Fittings 31-10-2023 Not yet started NA
102 Overhead Water Tanks 30-11-2023 Completed NA
103 Water Supply Connection to all units 30-11-2023 Not yet started NA
104 STP construction and completion 31-12-2023 Completed NA
105 Distempering & Colouring of all units and exteriors 18-08-2024 Not yet started NA
106 Fixation of doors and windows 18-08-2024 Not yet started NA
107 Scheduled Date of handing over possession 18-08-2024 Not yet started NA
108 Development of common areas, parks, gardens etc 18-08-2024 Not yet started NA
Updated Changes on 12-10-2023
109 Site Development 31-10-2021 Ongoing NA
110 NA 30-09-2022 ONGOING NA
111 Ground Floor/Stilt Floor 01-04-2022 Completed NA
112 1 Floor 31-05-2022 Completed NA
113 2 Floor 15-09-2022 Completed NA
114 3 Floor 31-10-2022 Completed NA
115 4 Floor 28-12-2022 Completed NA
116 NA 28-12-2022 Completed NA
117 Ground Floor/Stilt Floor 01-04-2022 Completed NA
118 1 Floor 31-05-2022 Completed NA
119 2 Floor 15-09-2022 Completed NA
120 3 Floor 31-10-2022 Completed NA
121 4 Floor 28-12-2022 Completed NA
122 Electrical Works 31-08-2023 Ongoing NA
123 Concealed Cabling including Plugs & switches 31-07-2023 Ongoing NA
124 Installation & Charging of Transformer 31-05-2023 Not yet started NA
125 Connection to Flats/Apartments 31-08-2023 Not yet started NA
126 PH works 30-11-2023 Ongoing NA
127 Laying of concealed Pipes 30-09-2023 Ongoing NA
128 PH Fittings 31-10-2023 Not yet started NA
129 Overhead Water Tanks 30-11-2023 Completed NA
130 Water Supply Connection to all units 30-11-2023 Not yet started NA
131 STP construction and completion 31-12-2023 Completed NA
132 Distempering & Colouring of all units and exteriors 18-08-2024 Ongoing NA
133 Fixation of doors and windows 18-08-2024 Ongoing NA
134 Scheduled Date of handing over possession 18-08-2024 18-08-2024 NA
135 Development of common areas, parks, gardens etc 18-08-2024 Not yet started NA
Updated Changes on 15-01-2024
136 Site Development 31-10-2021 Ongoing NA
137 NA 30-09-2022 ONGOING NA
138 Ground Floor/Stilt Floor 01-04-2022 Completed NA
139 1 Floor 31-05-2022 Completed NA
140 2 Floor 15-09-2022 Completed NA
141 3 Floor 31-10-2022 Completed NA
142 4 Floor 28-12-2022 Completed NA
143 NA 28-12-2022 Completed NA
144 Ground Floor/Stilt Floor 01-04-2022 Completed NA
145 1 Floor 31-05-2022 Completed NA
146 2 Floor 15-09-2022 Completed NA
147 3 Floor 31-10-2022 Completed NA
148 4 Floor 28-12-2022 Completed NA
149 Electrical Works 31-08-2023 Ongoing NA
150 Concealed Cabling including Plugs & switches 31-07-2023 Ongoing NA
151 Installation & Charging of Transformer 31-05-2023 Not yet started NA
152 Connection to Flats/Apartments 31-08-2023 Not yet started NA
153 PH works 30-11-2023 Ongoing NA
154 Laying of concealed Pipes 30-09-2023 Completed NA
155 PH Fittings 31-10-2023 Completed NA
156 Overhead Water Tanks 30-11-2023 Completed NA
157 Water Supply Connection to all units 30-11-2023 Completed NA
158 STP construction and completion 31-12-2023 Completed NA
159 Distempering & Colouring of all units and exteriors 18-08-2024 Completed NA
160 Fixation of doors and windows 18-08-2024 Completed NA
161 Scheduled Date of handing over possession 18-08-2024 18-08-2024 NA
162 Development of common areas, parks, gardens etc 18-08-2024 Ongoing NA
Updated Changes on 13-04-2024
163 Site Development 31-10-2021 COMPLETE NA
164 NA 30-09-2022 COMPLETE NA
165 Ground Floor/Stilt Floor 01-04-2022 Completed NA
166 1 Floor 31-05-2022 Completed NA
167 2 Floor 15-09-2022 Completed NA
168 3 Floor 31-10-2022 Completed NA
169 4 Floor 28-12-2022 Completed NA
170 NA 28-12-2022 Completed NA
171 Ground Floor/Stilt Floor 01-04-2022 Completed NA
172 1 Floor 31-05-2022 Completed NA
173 2 Floor 15-09-2022 Completed NA
174 3 Floor 31-10-2022 Completed NA
175 4 Floor 28-12-2022 Completed NA
176 Electrical Works 31-08-2023 COMPLETE NA
177 Concealed Cabling including Plugs & switches 31-07-2023 COMPLETE NA
178 Installation & Charging of Transformer 31-05-2023 Under Process NA
179 Connection to Flats/Apartments 31-08-2023 Under Process NA
180 PH works 30-11-2023 COMPLETE NA
181 Laying of concealed Pipes 30-09-2023 Completed NA
182 PH Fittings 31-10-2023 Completed NA
183 Overhead Water Tanks 30-11-2023 Completed NA
184 Water Supply Connection to all units 30-11-2023 Completed NA
185 STP construction and completion 31-12-2023 Completed NA
186 Distempering & Colouring of all units and exteriors 18-08-2024 Completed NA
187 Fixation of doors and windows 18-08-2024 Completed NA
188 Scheduled Date of handing over possession 18-08-2024 18-08-2024 NA
189 Development of common areas, parks, gardens etc 18-08-2024 COMPLETE NA

Booking Status

Residential Flats/ House
S. No. Flat No./ House No.

Area in square metres

Ownership Status
Carpet Area Balcony Area Exclusive Open Terrace Area
1 1A 83 7.16 Nil Land Owner
2 2A 83 7.16 Nil Land Owner
3 3A 83 7.16 Nil Promoter
4 4A 83 7.16 Nil Promoter
5 1B 84.60 8.92 Nil Promoter
6 2B 84.60 8.92 Nil Promoter
7 3B 84.60 8.92 Nil Promoter
8 4B 84.60 8.92 Nil Promoter
9 1C 82.55 7.16 Nil Promoter
10 2C 82.55 7.16 Nil Land Owner
11 3C 82.55 7.16 Nil Land Owner
12 4C 82.55 7.16 Nil Promoter
13 1D 93.97 7.16 Nil Land Owner
14 2D 93.97 7.16 Nil Land Owner
15 3D 93.97 7.16 Nil Promoter
16 4D 77.50 2.97 Nil Promoter

Financial Status

SL No. Funds Collected from the Allottees Funds Borrowed from Financial Institutions Funds Employed from Own Sources Expenditure As On Date Status
1 18829988 0 2897310 17924350 30-06-2022 Ongoing
2 57449568 0 2100000 51759738 30-06-2023 Omgoing
3 57449568 0 2100000 57112050 30-09-2023 ONGOING
4 62672256 0 2100000 59112050 31-12-2023 Ongoing
5 62672256 0 2100000 58912050 31-03-2024 Almost Complete

Updated Conditions of building plan approval

Sl. No. Description of Conditions Schedule date of compliance Present Status
1 Parking space measuring =386.973 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 12-09-2021 Not started
2 The land over which construction is proposed is accessible by an approved means of access of 60.0 Mt(Sixty point Zero)in width. 12-09-2021 Not started
3 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 12-09-2021 Not started
4 Storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per ODA(Planning& Building Standards)Rules,2020. 12-09-2021 Not started
5 Plantation as required under the provision under rule 30 of ODA (Planning & Building Standards)Rules, 2020.shallbe strictly adhered 12-09-2021 Not started
Updated Changes on 30-06-2022
6 Parking space measuring =386.973 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 12-09-2021 Completed
7 The land over which construction is proposed is accessible by an approved means of access of 60.0 Mt(Sixty point Zero)in width. 12-09-2021 Connected With the Road
8 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 12-09-2021 Not started
9 Storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per ODA(Planning& Building Standards)Rules,2020. 12-09-2021 Not started
10 Plantation as required under the provision under rule 30 of ODA (Planning & Building Standards)Rules, 2020.shallbe strictly adhered 12-09-2021 Not started
Updated Changes on 02-07-2022
11 Parking space measuring =386.973 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 12-09-2021 Completed
12 The land over which construction is proposed is accessible by an approved means of access of 60.0 Mt(Sixty point Zero)in width. 12-09-2021 Connected With the Road
13 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 12-09-2021 Not started
14 Storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per ODA(Planning& Building Standards)Rules,2020. 12-09-2021 Not started
15 Plantation as required under the provision under rule 30 of ODA (Planning & Building Standards)Rules, 2020.shallbe strictly adhered 12-09-2021 Not started
Updated Changes on 14-07-2023
16 Parking space measuring =386.973 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 12-09-2021 Completed
17 The land over which construction is proposed is accessible by an approved means of access of 60.0 Mt(Sixty point Zero)in width. 12-09-2021 Connected With the Road
18 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 12-09-2021 Not started
19 Storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per ODA(Planning& Building Standards)Rules,2020. 12-09-2021 Not started
20 Plantation as required under the provision under rule 30 of ODA (Planning & Building Standards)Rules, 2020.shallbe strictly adhered 12-09-2021 Not started
Updated Changes on 12-10-2023
21 Parking space measuring =386.973 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 12-09-2021 Completed
22 The land over which construction is proposed is accessible by an approved means of access of 60.0 Mt(Sixty point Zero)in width. 12-09-2021 Connected With the Road
23 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 12-09-2021 Not started
24 Storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per ODA(Planning& Building Standards)Rules,2020. 12-09-2021 Not started
25 Plantation as required under the provision under rule 30 of ODA (Planning & Building Standards)Rules, 2020.shallbe strictly adhered 12-09-2021 Not started
Updated Changes on 15-01-2024
26 Parking space measuring =386.973 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 12-09-2021 Completed
27 The land over which construction is proposed is accessible by an approved means of access of 60.0 Mt(Sixty point Zero)in width. 12-09-2021 Connected With the Road
28 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 12-09-2021 Not started
29 Storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per ODA(Planning& Building Standards)Rules,2020. 12-09-2021 Ongoing
30 Plantation as required under the provision under rule 30 of ODA (Planning & Building Standards)Rules, 2020.shallbe strictly adhered 12-09-2021 Ongoing
Updated Changes on 13-04-2024
31 Parking space measuring =386.973 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 12-09-2021 Completed
32 The land over which construction is proposed is accessible by an approved means of access of 60.0 Mt(Sixty point Zero)in width. 12-09-2021 Connected With the Road
33 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 12-09-2021 Applied For
34 Storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per ODA(Planning& Building Standards)Rules,2020. 12-09-2021 Ongoing
35 Plantation as required under the provision under rule 30 of ODA (Planning & Building Standards)Rules, 2020.shallbe strictly adhered 12-09-2021 Ongoing

Updated Project Documents

Sl. No. Title of the document Upload Document
1 Quarter 4 Proforma 1
2 Quarter 1 (22-23) Proforma 1
3 Quarter 4 Proforma 2
4 Quarter 1 (22-23) Proforma 2
5 Quarter 2 (22-23) Proforma I
6 Quarter 2 (22-23) Proforma II
7 Quarter 3 (22-23) Proforma I
8 Quarter 3 (22-23) Proforma II
9 Quarter 4 (22-23) Proforma I
10 Quarter 4 (22-23) Proforma II
11 Quarter 1 (23-24) Proforma I
12 Quarter 1 (23-24) Proforma II
13 Quarter 2 (23-24) Proforma I
14 Quarter 2 (23-24) Proforma II
15 Annual Audit Certificate(AAC) - Crystal 22-23
16 Quarter 3 (23-24) Proforma I
17 Quarter 3 (23-24) Proforma II
18 Quarter 4 (23-24) Proforma I
19 Quarter 4 (23-24) Proforma II
20 Annual Audit Certificate(AAC) - Crystal 23-24
:  HARSH WARDHAN KANDOI :  
NA :  APRPK4134R
:PAN Card :  harshwardhankandoi@gmail.com
:  MBA :  9437081855
:  3 years
:  Yes :  NA
:  NAVAL MAHAJAN :  
NA :  ARJPM4352P
:PAN Card :  navalmahajan@outlook.com
:  B.TECH :  9776312020
:  3 years
:  Yes :  NA
:  PRATEEK GUPTA :  
NA :  AWDPG1449A
:PAN Card :  prateekarch08@gmail.com
:  B.ARCH :  9937004761
:  3 year
:  Yes :  NA

Particulars of Architect/Construction Engineer/Contractor/Chartered Accountant

Name position Address with mobile number and email address Registration number Key real estate projects Is active Effective date
PRATEEK GUPTA Architect FLAT NO-3A,PLOT NO-181, GAYATRI VIHAR, NEAR IOCL,PATIA,9937004761, Email-prateekarch08@gmail.com CA/2009/45972 TRINITY KALINGA
NAGENDRA KUMAR PARIDA Construction Engineer NILAKANTHA NAGAR, BHUBANESWAR,9437013988, Email-nagendraparida@gmail.com SER/015/BDA TRINITY KALINGA
ARUN KUMAR BHAWSINKA Chartered Accountant MATA MATH,CANTONMENT ROAD,CUTTACK,9437027722, Email-sbn.ctc@gmail.com M.No.057589 TRINITY KALINGA

Updated Units

House No. Type of Garage/ Parking allotted Serial No., if any Dimension (Length x Width) in Metres Floor area in sq. metres Garage/Parking area cost is included or additional
Updated Changes
1A Covered Parking 1A 6.07X2.54 15.41 Included
2A Covered Parking 2A 6.07X2.54 15.41 Included
3A Covered Parking 3A 6.07X2.54 15.41 Included
4A Covered Parking 4A 6.07X2.54 15.41 Included
1B Covered Parking 1B 6.07X2.54 15.41 Included
2B Covered Parking 2B 6.07X2.54 15.41 Included
3B Covered Parking 3B 6.07X2.54 15.41 Included
4B Covered Parking 4B 6.07X2.54 15.41 Included
1C Covered Parking 1C 6.07X2.54 15.41 Included
2C Covered Parking 2C 6.07X2.54 15.41 Included
3C Covered Parking 3C 6.07X2.54 15.41 Included
4C Covered Parking 4C 6.07X2.54 15.41 Included
1D Covered Parking 1D 6.07X2.54 15.41 Included
2D Covered Parking 2D 6.07X2.54 15.41 Included
3D Covered Parking 3D 6.07X2.54 15.41 Included
4D Covered Parking 4D 6.07X2.54 15.41 Included
Updated Changes
1A Covered Parking 1A 6.07X2.54 15.41 Included
2A Covered Parking 2A 6.07X2.54 15.41 Included
3A Covered Parking 3A 6.07X2.54 15.41 Included
4A Covered Parking 4A 6.07X2.54 15.41 Included
1B Covered Parking 1B 6.07X2.54 15.41 Included
2B Covered Parking 2B 6.07X2.54 15.41 Included
3B Covered Parking 3B 6.07X2.54 15.41 Included
4B Covered Parking 4B 6.07X2.54 15.41 Included
1C Covered Parking 1C 6.07X2.54 15.41 Included
2C Covered Parking 2C 6.07X2.54 15.41 Included
3C Covered Parking 3C 6.07X2.54 15.41 Included
4C Covered Parking 4C 6.07X2.54 15.41 Included
1D Covered Parking 1D 6.07X2.54 15.41 Included
2D Covered Parking 2D 6.07X2.54 15.41 Included
3D Covered Parking 3D 6.07X2.54 15.41 Included
4D Covered Parking 4D 6.07X2.54 15.41 Included
1A Covered Parking 1A 6.07X2.54 15.41 Included
2A Covered Parking 2A 6.07X2.54 15.41 Included
3A Covered Parking 3A 6.07X2.54 15.41 Included
4A Covered Parking 4A 6.07X2.54 15.41 Included
1B Covered Parking 1B 6.07X2.54 15.41 Included
2B Covered Parking 2B 6.07X2.54 15.41 Included
3B Covered Parking 3B 6.07X2.54 15.41 Included
4B Covered Parking 4B 6.07X2.54 15.41 Included
1C Covered Parking 1C 6.07X2.54 15.41 Included
2C Covered Parking 2C 6.07X2.54 15.41 Included
3C Covered Parking 3C 6.07X2.54 15.41 Included
4C Covered Parking 4C 6.07X2.54 15.41 Included
1D Covered Parking 1D 6.07X2.54 15.41 Included
2D Covered Parking 2D 6.07X2.54 15.41 Included
3D Covered Parking 3D 6.07X2.54 15.41 Included
4D Covered Parking 4D 6.07X2.54 15.41 Included
1A Covered Parking 1A 6.07X2.54 15.41 Included
2A Covered Parking 2A 6.07X2.54 15.41 Included
3A Covered Parking 3A 6.07X2.54 15.41 Included
4A Covered Parking 4A 6.07X2.54 15.41 Included
1B Covered Parking 1B 6.07X2.54 15.41 Included
2B Covered Parking 2B 6.07X2.54 15.41 Included
3B Covered Parking 3B 6.07X2.54 15.41 Included
4B Covered Parking 4B 6.07X2.54 15.41 Included
1C Covered Parking 1C 6.07X2.54 15.41 Included
2C Covered Parking 2C 6.07X2.54 15.41 Included
3C Covered Parking 3C 6.07X2.54 15.41 Included
4C Covered Parking 4C 6.07X2.54 15.41 Included
1D Covered Parking 1D 6.07X2.54 15.41 Included
2D Covered Parking 2D 6.07X2.54 15.41 Included
3D Covered Parking 3D 6.07X2.54 15.41 Included
4D Covered Parking 4D 6.07X2.54 15.41 Included
1A Covered Parking 1A 6.07X2.54 15.41 Included
2A Covered Parking 2A 6.07X2.54 15.41 Included
3A Covered Parking 3A 6.07X2.54 15.41 Included
4A Covered Parking 4A 6.07X2.54 15.41 Included
1B Covered Parking 1B 6.07X2.54 15.41 Included
2B Covered Parking 2B 6.07X2.54 15.41 Included
3B Covered Parking 3B 6.07X2.54 15.41 Included
4B Covered Parking 4B 6.07X2.54 15.41 Included
1C Covered Parking 1C 6.07X2.54 15.41 Included
2C Covered Parking 2C 6.07X2.54 15.41 Included
3C Covered Parking 3C 6.07X2.54 15.41 Included
4C Covered Parking 4C 6.07X2.54 15.41 Included
1D Covered Parking 1D 6.07X2.54 15.41 Included
2D Covered Parking 2D 6.07X2.54 15.41 Included
3D Covered Parking 3D 6.07X2.54 15.41 Included
4D Covered Parking 4D 6.07X2.54 15.41 Included
1A Covered Parking 1A 6.07X2.54 15.41 Included
2A Covered Parking 2A 6.07X2.54 15.41 Included
3A Covered Parking 3A 6.07X2.54 15.41 Included
4A Covered Parking 4A 6.07X2.54 15.41 Included
1B Covered Parking 1B 6.07X2.54 15.41 Included
2B Covered Parking 2B 6.07X2.54 15.41 Included
3B Covered Parking 3B 6.07X2.54 15.41 Included
4B Covered Parking 4B 6.07X2.54 15.41 Included
1C Covered Parking 1C 6.07X2.54 15.41 Included
2C Covered Parking 2C 6.07X2.54 15.41 Included
3C Covered Parking 3C 6.07X2.54 15.41 Included
4C Covered Parking 4C 6.07X2.54 15.41 Included
1D Covered Parking 1D 6.07X2.54 15.41 Included
2D Covered Parking 2D 6.07X2.54 15.41 Included
3D Covered Parking 3D 6.07X2.54 15.41 Included
4D Covered Parking 4D 6.07X2.54 15.41 Included