: M/S. SKYIES INFRAHOME(OPC) PVT. LTD. | : Private Company |
: U45500OR2017OPC027479 | :View |
NA | : Plot NO-89, Kharvelnagar, Bhubaneswar-751001 |
: HIG-1/14, BDA Colony, Kapilaprasad, Bhubaneswar-751002, Dist. Khordha, Odisha | : skyiesinfra@gmail.com |
: 239455 | : 9337909110 |
: AAZCS0674E | :View |
: 2 Years Experiences in Building line | : NO |
: www.info@skyiesinfra.com |
: Animesh Swain | : |
: Managing Director | : BTWPS6162H |
:PAN Card | : skyiesinfra@gmail.com |
: 2 Years Experiences in Building line | : 9337909110 |
: No | |
: Yes | : NA |
: New | : Swarna Bhumi |
: Residential | : (Residential Project, Duplex, No. of Units-24) |
: Khordha | : Jatni |
: 751002 | : Development Authority |
: Bhubaneswar Development Authority | |
: Duplex | : NA |
: 2057 | : 469/63 |
: Panchagaon, Bhubaneswar | : 3056 |
: Yes | |
Yes | : View |
: View | |
: Other Person | |
: Rajaniprabha Pradhan Pradyumna Kumar Pradhan | : Rajaniprtava Pradhan & Pradyumna Kumar Pradhan, to give GPA promoter Skyies Infra Home(OPC) Pvt. Ltd |
: No | |
: Yes | |
: 11121802374 | : 02-06-2018 |
: Bhubaneswar Tahasil | : Attached |
: 2056 | : 469/63 |
: Panchagaon, Bhubaneswar | : 1093 |
: Yes | |
Yes | : View |
: View | |
: Other Person | |
: Rajaniprabha Pradhan Pradyumna Kumar Pradhan | : Rajaniprtava Pradhan & Pradyumna Kumar Pradhan, to give GPA promoter Skyies Infra Home(OPC) Pvt. Ltd |
: No | |
: Yes | |
: 11121801707 | : 21-04-2018 |
: Bhubaneswar Tahasil | : Attached |
: 2055 | : 469/63 |
: Panchagaon, Bhubaneswar | : 405 |
: Yes | |
Yes | : View |
: View | |
: Other Person | |
: Rajaniprabha pradhan Pradyumna Kumar Pradhan | : Rajaniprtava Pradhan & Pradyumna Kumar Pradhan, to give GPA promoter Skyies Infra Home(OPC) Pvt. Ltd |
: No | |
: Yes | |
: 11121801707 | : 21-04-2018 |
: Bhubaneswar Tahasil | : Attached |
: 2054 | : 469/63 |
: Panchagaon, Bhubaneswar | : 242 |
: Yes | |
Yes | : View |
: View | |
: Other Person | |
: Rajaniprabha Pradhan Pradyumna Kumar Pradhan | : Rajaniprtava Pradhan & Pradyumna Kumar Pradhan, to give GPA promoter Skyies Infra Home(OPC) Pvt. Ltd |
: No | |
: Yes | |
: 11121801707 | : 21-04-2018 |
: Bhubaneswar Tahasil | : Attached |
: 2053 | : 469/261 |
: Panchagaon, Bhubaneswar | : 1335 |
: Yes | |
Yes | : View |
: View | |
: Other Person | |
: Rajaniprava Pradhan, Pradyumna Kumar Pradhan, Puspita Pradhan | : Rajaniprava Pradhan, Pradyumna Kumar Pradhan, Puspita Pradhan to give GPA promoter Skyies Infra Home(OPC) Pvt. Ltd |
: No | |
: Yes | |
: 11121801708 | : 21-04-2018 |
: Bhubaneswar Tahasil | : Attached |
: Yes |
Serial No. | Particulars of the Person | Land/Plot Details | Share of the Person | Document Attached |
---|---|---|---|---|
1 | Rajaniprabha Pradhan Pradyumna Kumar Pradhan | 2057 | 35 | Agreement Copy |
2 | Rajaniprabha Pradhan Pradyumna Kumar Pradh | 2056 | 35 | Agreement Copy |
3 | Rajaniprabha Pradhan Pradyumna Kumar Pradh | 2055 | 35 | Agreement Copy |
4 | Rajaniprabha Pradhan Pradyumna Kumar Pradh | 2054 | 35 | Agreement Copy |
5 | Rajaniprava Pradhan, Pradyumna Kumar Pradhan, Puspita Pradhan | 2053 | 35 | Agreement Copy |
View | View |
Download site plan | 08-01-2023 |
Sl. No. | Description of Conditions | Schedule date of compliance | Present Status |
---|---|---|---|
1 | The Sub-division of land with house shall be used exclusively for Residential purpose and the uses shall not be changed to any other use without prior approval of the Authority | 10-11-2022 | Not yet work |
2 | The Development shall be undertaking strictly according to plan(enclosed) | 10-11-2022 | Not yet work |
3 | The land over which Sub-division layout is proposed accessible by an approved means of access of 12.00 mtr in width | 10-11-2022 | Not yet work |
4 | The land in question must be in lawful ownership and peaceful possession of the applicant. | 10-11-2022 | Not yet work |
5 | The permission is valid for aperiod of three years with effect from the date of its issue. | 10-11-2022 | Not yet work |
6 | The road and open spaces civic amenties area shown in the gift deed shall be developed by the applicant at their own cost which was executed between GPA holder and BDA for public through fare. | 05-12-2022 | Not yet work |
7 | Water supply Electricity are to be provided in the layout area by the applicant at their own cost and transferred to respect Govt agencies for further maintenance.. | 14-12-2022 | Not yet work |
8 | Plantation in the open spaces and along the internal roads is to be made before delivering the sub-plots. | 15-12-2022 | Not yet work |
9 | All roadside drains are to be developed maintaining proper slope as to convey strom water to the public drain with intimation to BDA for verification. | 16-12-2022 | Not yet work |
: Yes | : View |
Point No. | Latitude | Longitude |
---|---|---|
1 | 85°47'43.8''E | 20°10'31.5''N |
2 | 85°47'44.3''E | 20°10'31.2''N |
3 | 85°47'44.5''E | 20°10'31.2''N |
4 | 85°47'44.7''E | 20°10'31.1''N |
5 | 85°47'45.0''E | 20°10'31.4''N |
6 | 85°47'45.6''E | 20°10'30.9''N |
7 | 85°47'46.7''E | 20°10'30.6''N |
8 | 85°47'46.6''E | 20°10'30.1''N |
9 | 85°47'46.5''E | 20°10'29.8''N |
10 | 85°47'46.3''E | 20°10'29.2''N |
11 | 85°47''46.4''E | 20°10'29.2''N |
12 | 85°47'46.3''E | 20°10'28.7''N |
13 | 85°47'46.1''E | 20°10'28.6''N |
14 | 85°47'45.3''E | 20°1028.8'N |
15 | 85°47'44.9''E | 20°10'28.8''N |
16 | 85°47'45.3''E | 20°10'28.7''N |
17 | 85°47'44.6''E | 20°10'28.0''N |
18 | 85°47'44.1''E | 20°10'28.2''N |
19 | 85°47'43.7''E | 20°10'29.2''N |
20 | 85°47'43.8''E | 20°10'29.2''N |
21 | 85°47'43.6''E | 20°10'29.9''N |
22 | 85°47'44.0''E | 20°10'30.4''N |
23 | 85°47'43.6''E | 20°10'30.8''N |
24 | ''85°47'43.5''E | 20°10'31.1''N |
25 | 85°47'43.7''E | 20°10'31.4''N |
Description* | Scheduled date of completion | Current Status | Site Images |
---|---|---|---|
Site Development | 20-10-2020 | Not yet Work | |
Roof Casting | NA | NA | NA |
Ground Floor/Stilt Floor | 20-10-2020 | Not yet Work | |
1 Floor | 12-02-2021 | Not yet Work | |
2 Floor | 20-08-2020 | NA | |
3 Floor | 20-08-2020 | NA | |
Brick Work & Plastering | NA | NA | NA |
Ground Floor/Stilt Floor | 20-02-2021 | Not yet Work | |
1 Floor | 15-03-2021 | Not yet Work | |
Electrical Works | 16-12-2022 | Not yet Work | |
Concealed Cabling including Plugs & switches | 18-12-2022 | Not yet Work | |
Installation & Charging of Transformer | 21-12-2022 | Not yet Work | |
Connection to Flats/Apartments | 22-12-2022 | Not yet Work | |
PH works | 12-12-2022 | Not yet Work | |
Laying of concealed Pipes | 18-12-2022 | Not yet Work | |
PH Fittings | 20-12-2022 | Not yet Work | |
Overhead Water Tanks | 20-12-2022 | Not yet Work | |
Water Supply Connection to all units | 25-12-2022 | Not yet Work | |
STP construction and completion | 25-12-2022 | Not yet Work | |
Distempering & Colouring of all units and exteriors | 26-12-2022 | Not yet Work | |
Fixation of doors and windows | 28-12-2022 | Not yet Work | |
Scheduled Date of handing over possession | 30-12-2022 | Not yet Work | |
Development of common areas, parks, gardens etc | 30-12-2022 | Not yet Work | |
Site Development | 20-10-2020 | finish | NA |
NA | NA | NA | NA |
Ground Floor/Stilt Floor | 20-10-2020 | finish | NA |
1 Floor | 12-02-2021 | Not yet Work | NA |
2 Floor | 20-08-2020 | NA | NA |
3 Floor | 20-08-2020 | NA | NA |
NA | NA | NA | NA |
Ground Floor/Stilt Floor | 20-02-2021 | Not yet Work | NA |
1 Floor | 15-03-2021 | Not yet Work | NA |
Electrical Works | 16-12-2022 | Not yet Work | NA |
Concealed Cabling including Plugs & switches | 18-12-2022 | Not yet Work | NA |
Installation & Charging of Transformer | 21-12-2022 | Not yet Work | NA |
Connection to Flats/Apartments | 22-12-2022 | Not yet Work | NA |
PH works | 12-12-2022 | Not yet Work | NA |
Laying of concealed Pipes | 18-12-2022 | Not yet Work | NA |
PH Fittings | 20-12-2022 | Not yet Work | NA |
Overhead Water Tanks | 20-12-2022 | Not yet Work | NA |
Water Supply Connection to all units | 25-12-2022 | Not yet Work | NA |
STP construction and completion | 25-12-2022 | Not yet Work | NA |
Distempering & Colouring of all units and exteriors | 26-12-2022 | Not yet Work | NA |
Fixation of doors and windows | 28-12-2022 | Not yet Work | NA |
Scheduled Date of handing over possession | 30-12-2022 | Not yet Work | NA |
Development of common areas, parks, gardens etc | 30-12-2022 | Not yet Work | NA |
Site Development | 20-10-2020 | COMPLETED | |
NA | 25-01-2024 | NA | |
Ground Floor/Stilt Floor | 20-10-2020 | COMPLETED | |
1 Floor | 12-02-2021 | COMPLETED | |
2 Floor | 20-08-2020 | NA | NA |
3 Floor | 20-08-2020 | NA | NA |
NA | 22-03-2024 | NA | NA |
Ground Floor/Stilt Floor | 20-02-2021 | COMPLETED | NA |
1 Floor | 15-03-2021 | COMPLETED | NA |
Electrical Works | 16-12-2022 | COMPLETED | NA |
Concealed Cabling including Plugs & switches | 18-12-2022 | COMPLETED | NA |
Installation & Charging of Transformer | 21-12-2022 | COMPLETED | NA |
Connection to Flats/Apartments | 22-12-2022 | COMPLETED | NA |
PH works | 12-12-2022 | COMPLETED | NA |
Laying of concealed Pipes | 18-12-2022 | COMPLETED | NA |
PH Fittings | 20-12-2022 | COMPLETED | NA |
Overhead Water Tanks | 20-12-2022 | COMPLETED | NA |
Water Supply Connection to all units | 25-12-2022 | COMPLETED | NA |
STP construction and completion | 25-12-2022 | COMPLETED | NA |
Distempering & Colouring of all units and exteriors | 26-12-2022 | COMPLETED | NA |
Fixation of doors and windows | 28-12-2022 | COMPLETED | NA |
Scheduled Date of handing over possession | 30-12-2022 | COMPLETED | NA |
Development of common areas, parks, gardens etc | 30-12-2022 | COMPLETED | NA |
Site Development | 20-10-2020 | COMPLETED | NA |
NA | 25-01-2024 | NA | NA |
Ground Floor/Stilt Floor | 20-10-2020 | COMPLETED | NA |
1 Floor | 12-02-2021 | COMPLETED | NA |
2 Floor | 20-08-2020 | NA | NA |
3 Floor | 20-08-2020 | NA | NA |
NA | 22-03-2024 | NA | NA |
Ground Floor/Stilt Floor | 20-02-2021 | COMPLETED | NA |
1 Floor | 15-03-2021 | COMPLETED | NA |
Electrical Works | 16-12-2022 | COMPLETED | NA |
Concealed Cabling including Plugs & switches | 18-12-2022 | COMPLETED | NA |
Installation & Charging of Transformer | 21-12-2022 | COMPLETED | NA |
Connection to Flats/Apartments | 22-12-2022 | COMPLETED | NA |
PH works | 12-12-2022 | COMPLETED | NA |
Laying of concealed Pipes | 18-12-2022 | COMPLETED | NA |
PH Fittings | 20-12-2022 | COMPLETED | NA |
Overhead Water Tanks | 20-12-2022 | COMPLETED | NA |
Water Supply Connection to all units | 25-12-2022 | COMPLETED | NA |
STP construction and completion | 25-12-2022 | COMPLETED | NA |
Distempering & Colouring of all units and exteriors | 26-12-2022 | COMPLETED | NA |
Fixation of doors and windows | 28-12-2022 | COMPLETED | NA |
Scheduled Date of handing over possession | 30-12-2022 | COMPLETED | NA |
Development of common areas, parks, gardens etc | 30-12-2022 | COMPLETED | NA |
: Residential | |
: 24
|
|
Residential Flats/ House | |||||
---|---|---|---|---|---|
S. No. | Flat No./ House No. | ||||
Area in square metres |
Ownership | ||||
Carpet Area | Balcony Area | Exclusive Open Terrace Area | |||
1 | 1 | 51.29 | 13.56 | 22.77 | Promoter |
2 | 2 | 51.29 | 13.56 | 22.77 | Promoter |
3 | 3 | 51.29 | 13.56 | 22.77 | Promoter |
4 | 4 | 51.29 | 13.56 | 22.77 | Land Owner |
5 | 5 | 51.29 | 13.56 | 22.77 | Land Owner |
6 | 6 | 51.29 | 13.56 | 22.77 | Promoter |
7 | 7 | 51.29 | 13.56 | 22.77 | Promoter |
8 | 8 | 64.63 | 15.96 | 4.12 | Promoter |
9 | 9 | 51.29 | 13.56 | 22.77 | Promoter |
10 | 10 | 51.29 | 13.56 | 22.77 | Promoter |
11 | 11 | 51.29 | 13.56 | 22.77 | Promoter |
12 | 12 | 51.29 | 13.56 | 22.77 | Promoter |
13 | 13 | 51.29 | 13.56 | 22.77 | Promoter |
14 | 14 | 51.29 | 13.56 | 22.77 | Promoter |
15 | 15 | 51.29 | 13.56 | 22.77 | Promoter |
16 | 16 | 51.29 | 13.56 | 22.77 | Land Owner |
17 | 17 | 51.29 | 13.56 | 22.77 | Land Owner |
18 | 18 | 51.29 | 13.56 | 22.77 | Land Owner |
19 | 19 | 51.29 | 13.56 | 22.77 | Land Owner |
20 | 20 | 51.29 | 13.56 | 22.77 | Land Owner |
21 | 21 | 64.63 | 15.96 | 4.12 | Land Owner |
22 | 22 | 64.63 | 15.96 | 4.12 | Promoter |
23 | 23 | 51.29 | 13.56 | 22.77 | Promoter |
24 | 24 | 51.29 | 13.56 | 22.77 | Promoter |
Types of garages and parking | ||||||
---|---|---|---|---|---|---|
House No. | Type of Garage/ Parking allotted | Serial No., if any | Dimension (Length x Width) in Metres | Floor area in sq. metres | Garage/Parking area cost is included or additional | |
1 | Covered Parking | 1 | 12.3*3.21 | 36.36 | Included | 2 | Covered Parking | 2 | 12.3*3.21 | 36.36 | Included | 3 | Covered Parking | 3 | 12.3*3.21 | 36.36 | Included | 4 | Covered Parking | 4 | 12.3*3.21 | 36.36 | Included | 5 | Covered Parking | 5 | 12.3*3.21 | 36.36 | Included | 6 | Covered Parking | 6 | 12.3*3.21 | 36.36 | Included | 7 | Covered Parking | 7 | 12.3*3.21 | 36.36 | Included | 8 | Covered Parking | 8 | 12.3*3.21 | 36.36 | Included | 9 | Covered Parking | 9 | 12.3*3.21 | 36.36 | Included | 10 | Covered Parking | 10 | 12.3*3.21 | 36.36 | Included | 11 | Covered Parking | 11 | 12.3*3.21 | 36.36 | Included | 12 | Covered Parking | 12 | 12.3*3.21 | 36.36 | Included | 13 | Covered Parking | 13 | 12.3*3.21 | 36.36 | Included | 14 | Covered Parking | 14 | 12.3*3.21 | 36.36 | Included | 15 | Covered Parking | 15 | 12.3*3.21 | 36.36 | Included | 16 | Covered Parking | 16 | 12.3*3.21 | 36.36 | Included | 17 | Covered Parking | 17 | 12.3*3.21 | 36.36 | Included | 18 | Covered Parking | 18 | 12.3*3.21 | 36.36 | Included | 19 | Covered Parking | 19 | 12.3*3.21 | 36.36 | Included | 20 | Covered Parking | 20 | 12.3*3.21 | 36.36 | Included | 21 | Covered Parking | 21 | 12.3*3.21 | 36.36 | Included | 22 | Covered Parking | 22 | 12.3*3.21 | 36.36 | Included | 23 | Covered Parking | 23 | 12.3*3.21 | 36.36 | Included | 24 | Covered Parking | 24 | 12.3*3.21 | 36.36 | Included |
Particulars of Facilities | Status of the facility | Brief description of facility |
---|---|---|
Drinking Water Facility | Ground Water | Copy of Consent Letter |
Fire Fighting Facility | No | all side |
Emergency Evacuation Services | No | |
Use of Renewable Energy | No | |
Lift Facility | No | |
Market Complex | No | |
Community Hall | No | yes |
Gymnasium | No | |
Swimming Pool | No | |
Play Ground | No | |
Park/Garden | No | |
Plantation Area | Yes | Both side |
Others(Please Specify) | Yes | DG Backup |
Internal Road | Yes | Internal road for the above project 9.14 mt wide and the development of the road is to be done by the promoter by inter lucking paver tiles, |
External Road | Yes | Eternal road of the above project 9.14 mt wide public road the development of the road by the concert Authority. |
Elecricity Supply | Yes | Copy of Consent Letter |
Other Amenities | Yes | Dg Back up |