: M/s. Mason Estate (India) Pvt. Ltd | : Private Company |
: U70109OR2006PTC009040 | :View |
NA | : Plot No-458, Madhusudan Nagar, Nayapalli, Bhubaneswar-751012 |
: Plot No. 458, Madhusudan Nagar, Nayapalli, Bhubaneswar-751012, Dist. Khordha, Odisha. | : masonestate@yahoo.com |
: 2540133 | : 9438731040 |
: AAFCM0207P | :View |
: 14 Years of Experiences | : NO |
: www.masonestateindia.com |
: New | : Mason Paradise Phase-I |
: Residential | : (Residential Project, Duplex, No. of Units-12) |
: Khordha | : Bhubaneswar |
: 751012 | : Development Authority |
: Bhubaneswar Development Authority | |
: Duplex Project | : Duplex project |
: No |
Serial No. | Particulars of the Person | Land/Plot Details | Share of the Person | Document Attached |
---|---|---|---|---|
1 | 2.Benudhar Rout | 1395/1838 | considerration with amount-Rs-1500000 | Agreement Copy |
View | View |
Download site plan | 30-12-2022 |
Sl. No. | Description of Conditions | Schedule date of compliance | Present Status |
---|---|---|---|
1 | The Sub-divisionof land with housing shall be exclusively for residential purpose and the uses shall not be changed to any other use without prior approval of this Authority. | 12-02-2020 | Not yet start |
2 | The development shall be undertaken strictly according to plan(enclosed) | 20-02-2020 | Not yet start |
3 | The land over with Sub-division layout is proposed accessible by an approved means of access of 9.14 mtr in width | 22-02-2020 | Not yet start |
4 | The land in question must be in lawful ownership and peaceful possession of the applicant. | 27-02-2020 | Not yet start |
5 | The permission is valid for a period of three years with effect from the date of its issue | 14-02-2020 | Not yet start |
6 | Permission accorded under the provision of section 16 of ODA Act can not be construed as an evidence in respect of right title interest of plot over which the plan is approved | 22-02-2020 | Not yet start |
7 | Any disput arising out of land record or in respect of right title interest after this approved the plan shall be treated automatically cancelled during the period of disput, | 26-02-2020 | Not yet start |
8 | The land reserved for roads open spaces and public unities shall be made avalaible to concerned local body or any other goverment agency by way of deed of gift as and when required by them | 11-06-2020 | Permission awaited |
9 | Plantation in the open spaces and long the internal area is to be made before delivering the sub plot | 11-06-2020 | Not yet start |
: Yes | : View |
Point No. | Latitude | Longitude |
---|---|---|
1 | 85°50'49.3''E | 20°20'50.4''N |
2 | 85°50'50.1''E | 20°20'50.3''N |
3 | 85°50'50.0''E | 20°20'49.89'N |
4 | 85°50'50.3''E | 20°20'49.6''N |
5 | 85°50'50.3''E | 20°20'49.9''N |
6 | 85°50'51.8''E | 20°20'49.8''N |
7 | 85°50'48.8''E | 20°20'49.5''N |
8 | 85°50'51.2''E | 20°20'49.43''N |
9 | 85°50'50.7''E | 20°20'49.2''N |
10 | 85°50'51.3''E | 20°20'48.3''N |
11 | 85°50'48.5''E | 20°20'49.4''N |
12 | 85°50'49.1''E | 20°20'50.3''N |
Description* | Scheduled date of completion | Current Status | Site Images |
---|---|---|---|
Site Development | 09-05-2020 | Not yet start | |
Roof Casting | NA | NA | NA |
Ground Floor/Stilt Floor | 05-07-2020 | Not yet start | |
1 Floor | 15-10-2020 | Not yet start | |
Brick Work & Plastering | NA | NA | NA |
Ground Floor/Stilt Floor | 15-08-2020 | Not yet start | |
1 Floor | 30-10-2020 | Not yet start | |
Electrical Works | 01-04-2022 | Not yet start | |
Concealed Cabling including Plugs & switches | 25-04-2022 | Not yet start | |
Installation & Charging of Transformer | 12-05-2022 | Not yet start | |
Connection to Flats/Apartments | 27-05-2022 | Not yet start | |
PH works | 15-06-2022 | Not yet start | |
Laying of concealed Pipes | 26-06-2022 | Not yet start | |
PH Fittings | 28-06-2022 | Not yet start | |
Overhead Water Tanks | 28-062022 | Not yet start | |
Water Supply Connection to all units | 2-07-2022 | Not yet start | |
STP construction and completion | 3-07-2022 | Not yet start | |
Distempering & Colouring of all units and exteriors | 15-07-2022 | Not yet start | |
Fixation of doors and windows | 2-08-2022 | Not yet start | |
Scheduled Date of handing over possession | 20-08-2022 | Not yet start | |
Development of common areas, parks, gardens etc | 10-09-2022 | Not yet start | |
Site Development | 09-05-2020 | COMPLETE | NA |
NA | NA | NA | NA |
Ground Floor/Stilt Floor | 05-07-2020 | COMPLETE | NA |
1 Floor | 15-10-2020 | COMPLETE | NA |
NA | NA | NA | NA |
Ground Floor/Stilt Floor | 15-08-2020 | COMPLETE | NA |
1 Floor | 30-10-2020 | COMPLETE | NA |
Electrical Works | 01-04-2022 | COMPLETE | NA |
Concealed Cabling including Plugs & switches | 25-04-2022 | COMPLETE | NA |
Installation & Charging of Transformer | 12-05-2022 | COMPLETE | NA |
Connection to Flats/Apartments | 27-05-2022 | COMPLETE | NA |
PH works | 15-06-2022 | COMPLETE | NA |
Laying of concealed Pipes | 26-06-2022 | COMPLETE | NA |
PH Fittings | 28-06-2022 | COMPLETE | NA |
Overhead Water Tanks | 28-062022 | COMPLETE | NA |
Water Supply Connection to all units | 2-07-2022 | COMPLETE | NA |
STP construction and completion | 3-07-2022 | COMPLETE | NA |
Distempering & Colouring of all units and exteriors | 15-07-2022 | COMPLETE | NA |
Fixation of doors and windows | 2-08-2022 | COMPLETE | NA |
Scheduled Date of handing over possession | 20-08-2022 | COMPLETE | NA |
Development of common areas, parks, gardens etc | 10-09-2022 | COMPLETE | NA |
Site Development | 09-05-2020 | COMPLETE | NA |
NA | 05-07-2020 | COMPLETE | NA |
Ground Floor/Stilt Floor | 05-07-2020 | COMPLETE | NA |
1 Floor | 15-10-2020 | COMPLETE | NA |
NA | 15-08-2020 | COMPLETE | NA |
Ground Floor/Stilt Floor | 15-08-2020 | COMPLETE | NA |
1 Floor | 30-10-2020 | COMPLETE | NA |
Electrical Works | 01-04-2022 | COMPLETE | NA |
Concealed Cabling including Plugs & switches | 25-04-2022 | COMPLETE | NA |
Installation & Charging of Transformer | 12-05-2022 | COMPLETE | NA |
Connection to Flats/Apartments | 27-05-2022 | COMPLETE | NA |
PH works | 15-06-2022 | COMPLETE | NA |
Laying of concealed Pipes | 26-06-2022 | COMPLETE | NA |
PH Fittings | 28-06-2022 | COMPLETE | NA |
Overhead Water Tanks | 28-062022 | COMPLETE | NA |
Water Supply Connection to all units | 2-07-2022 | COMPLETE | NA |
STP construction and completion | 3-07-2022 | COMPLETE | NA |
Distempering & Colouring of all units and exteriors | 15-07-2022 | COMPLETE | NA |
Fixation of doors and windows | 2-08-2022 | COMPLETE | NA |
Scheduled Date of handing over possession | 20-08-2022 | COMPLETE | NA |
Development of common areas, parks, gardens etc | 10-09-2022 | COMPLETE | NA |
: Residential | |
: 12
|
|
Residential Flats/ House | |||||
---|---|---|---|---|---|
S. No. | Flat No./ House No. | ||||
Area in square metres |
Ownership | ||||
Carpet Area | Balcony Area | Exclusive Open Terrace Area | |||
1 | B1 | 139.4 | 3.34 | 00 | Promoter |
2 | B2 | 143.75 | 3.34 | 00 | Promoter |
3 | B3 | 171.6 | 3.55 | 00 | Promoter |
4 | B4 | 171.6 | 3.55 | 00 | Promoter |
5 | C1 | 140.12 | 2.74 | 00 | Promoter |
6 | C2 | 143.91 | 3.4 | 00 | Promoter |
7 | D18 | 143.75 | 3.34 | 00 | Promoter |
8 | D20 | 143.75 | 3.34 | 00 | Promoter |
9 | D21 | 143.75 | 3.34 | 00 | Promoter |
10 | D22 | 171.6 | 3.55 | 00 | Promoter |
11 | D23 | 171.6 | 3.55 | 00 | Promoter |
12 | D24 | 171.6 | 3.55 | 00 | Promoter |
Types of garages and parking | ||||||
---|---|---|---|---|---|---|
House No. | Type of Garage/ Parking allotted | Serial No., if any | Dimension (Length x Width) in Metres | Floor area in sq. metres | Garage/Parking area cost is included or additional | |
B1 | Covered Parking | 1 | 3.025*5.12 | 15.49 | Included | B2 | Covered Parking | 2 | 3.025*5.12 | 15.49 | Included | B3 | Covered Parking | 3 | 4.05*5.27 | 21.34 | Included | B4 | Covered Parking | 4 | 4.05*5.27 | 21.34 | Included | C1 | Covered Parking | 5 | 3.275*4.51 | 14.77 | Included | C2 | Covered Parking | 6 | 3.025*5.12 | 15.49 | Included | D18 | Covered Parking | 7 | 3.025*5.12 | 15.49 | Included | D20 | Covered Parking | 8 | 3.025*5.12 | 15.49 | Included | D21 | Covered Parking | 9 | 3.025*5.12 | 15.49 | Included | D22 | Covered Parking | 10 | 4.05*5.27 | 21.34 | Included | D23 | Covered Parking | 11 | 4.05*5.27 | 21.34 | Included | D24 | Covered Parking | 12 | 4.05*5.27 | 21.34 | Included |
Particulars of Facilities | Status of the facility | Brief description of facility |
---|---|---|
Drinking Water Facility | Ground Water | Copy of Consent Letter |
Fire Fighting Facility | No | All side fire fighting cylinder |
Emergency Evacuation Services | No | |
Use of Renewable Energy | No | DG backup |
Lift Facility | No | |
Market Complex | No | |
Community Hall | Yes | 88.114 sqm, community hall |
Gymnasium | No | |
Swimming Pool | No | |
Play Ground | No | |
Park/Garden | No | yes |
Plantation Area | Yes | 167.70 sqm |
Others(Please Specify) | No | DG back up with all area cc c |
Internal Road | Yes | as per BDA approval plan 30 ft width plantation ,concrete road and drain |
External Road | Yes | 30ft width black top connecting to patia square |
Elecricity Supply | Yes | Copy of Consent Letter |
Other Amenities | Yes | As per BDA norms |