: Omshree Infratech Pvt.Ltd | : Private Company |
: U45201OR2008PTC009749 | :View |
NA | : Om Shree Infratech Pvt. Ltd, QR No.L-1693,Hanspal, Naharakanta, Bhubaneswar-751010, Khurdha, Odisha. |
: Omshree Infratech Pvt. Ltd. QR No.- L-1693, Hanspal, Naharakanta, Bhubaneswar, Dist- Khordha, Odisha- 751010. | : ranjanswainjatni@gmail.com |
: 2364458 | : 9437129839 |
: AAACO9941K | :View |
: 12 Years Experiences | : NO |
: www.omshreeinfrratech.com |
: Keshab Chandra Pradhan |
: ![]() |
: Managing Director | : APDPP0562N |
:PAN Card | : omshreeinfratech@gmail.com |
: MA(LLB | : 8249893040 |
: 12 YEARS EXPERINCES IN BUILDING LINE | |
: Yes | : NA |
: Ahalya Pradhan |
: ![]() |
: Director | : CJQPP0347E |
:PAN Card | : omshreeinfratech@ymail.com |
: Matriculation | : 7008020157 |
: 12 YEARS EXPERINCES IN BUILDING LINE | |
: Yes | : NA |
: New | : OM SHREE PRIDE |
: Residential | : ( Residential Project, S+4, No. of Units- 32 ) |
: Khordha | : Bhubaneswar |
: 752101 | : Development Authority |
: BHUBANESWAR DEVELOPMENT AUTHORITY | |
: S+4 | : NA |
: 526/1996/2407 | : 704/809 |
: Mouza-Balianta,Tahsil Balianta, Bhubaneswar, Khordha, Odisha. | : 1121.38 |
: Yes | |
Yes | : View |
: View | |
: Other Person | |
: Mina Rani Jena, Bani Priya Jena, Radhakanta Jena,& Ramakanta Jena | : Mina Rani Jena, Bani Priya Jena, Radhakanta Jena,& Ramakanta Jena to Executed General Power of Attorney M/s. Omshree Infratech Pvt.Ltd.,Managing Directer Mr. Keshab Chandra Pradhan. |
: No | |
: Yes | |
: 11821703376 | : 29-12-2017 |
: DSR-BHUBANESWAR | : Attached |
: Yes |
Serial No. | Particulars of the Person | Land/Plot Details | Share of the Person | Document Attached |
---|---|---|---|---|
1 | Mina Rani Jena, Bani Priya Jena, Radhakanta Jena,& Ramakanta Jena | 526/1996 | 45% | Agreement Copy |
View | View |
Download site plan | 10-02-2025 |
Sl. No. | Description of Conditions | Schedule date of compliance | Present Status |
---|---|---|---|
1 | The building shall be used exclusively for residential apartment purpose and the use shall not be changed to any other use without prior approval of this Authority. | 22-12-2022 | UNDER PROGRESS |
2 | Parking space measuring 673.55 sqm as shown in the approved plans shall be left for parking of vehicles and no part of it will be used for any other purpose. | 18-02-2023 | UNDER PROGRESS |
3 | The land over which construction is proposed is accessible by an approved means of access of 9.14 mt(Nine Point one four meter)mt in width. | 18-05-2023 | UNDER PROGRESS |
4 | The permission granted under these regulation shall remain valid upto three years from the date of issue. However the permission shall have to be revalidated before the expiry of the above period on payment of such fee as may be prescribe under rules and such revalidation shall be valid for one year. | 20-07-2023 | UNDER PROGRESS |
5 | Storm water from the permises of roof top shall be conveyed and discharged to the rain water recharging pits as per BDA (Planning & Building Standards) Regulation,2018 | 26-05-2023 | UNDER PROGRESS |
6 | The space which is meant for parking shall not be changed to any other use and shall not be partitioned/closed in any manner. | 10-07-2023 | UNDER PROGRESS |
7 | 20% of the parking space in group housing/apartment building shall be exclusively earmarked for ambulances fire tender physically handicapped persons and outside visitors with signage as per norms of BDA (Planning & Building Standards) regulation2018. | 20-09-2023 | UNDER PROGRESS |
8 | Plantation @80 sqm per one tree of the plot area shall be made by the applicant as per provision of BDA (Planning & Building Standards) Regulation 2018. | 22-12-2023 | UNDER PROGRESS |
9 | The concerned Architect/Applicant/ Developer are fully responsible for any deviations addition & alternation beyomd approved plan/defective construction etc. shall be liable for action as per the provisions of the regulation. | 08-03-2024 | UNDER PROGRESS |
10 | The Authority shall in noway be held responsible for any structural failure and damage due to earthquake/cyclone/any other natural disaster. | 26-04-2024 | UNDER PROGRESS |
: Yes | : View |
Point No. | Latitude | Longitude |
---|---|---|
1 | 20°17'45.8''N | 85°53'48.0''E |
2 | 20°17.45.7'N | 85°53'47.5''E |
3 | 20°17'45.1''N | 85°53'47.6''E |
4 | 20°17'45.0''N | 85°53'46.3''E |
5 | 20°17'46.0''N | 85°53'46.3''E |
6 | 20°17'46.0''N | 85°53'46.9''E |
7 | 20°17'46.1''N | 85°53'47.9''E |
Description* | Scheduled date of completion | Current Status | Site Images |
---|---|---|---|
Site Development | 22-09-2022 | UNDER PROGRESSS | |
Roof Casting | NA | NA | NA |
Ground Floor/Stilt Floor | 12-10-2022 | UNDER PROGRESSS | NA |
1 Floor | 24-11-2022 | UNDER PROGRESSS | NA |
2 Floor | 22-12-2022 | UNDER PROGRESSS | NA |
3 Floor | 15-01-2023 | UNDER PROGRESSS | NA |
4 Floor | 30-01-2023 | UNDER PROGRESSS | NA |
Brick Work & Plastering | NA | NA | NA |
Ground Floor/Stilt Floor | 12-02-2023 | UNDER PROGRESSS | NA |
1 Floor | 28-02-2023 | UNDER PROGRESSS | NA |
2 Floor | 06-03-2023 | UNDER PROGRESSS | NA |
3 Floor | 30-03-2023 | UNDER PROGRESSS | NA |
4 Floor | 10-04-2023 | UNDER PROGRESSS | NA |
Electrical Works | 20-06-2023 | UNDER PROGRESSS | NA |
Concealed Cabling including Plugs & switches | 10-07-2023 | UNDER PROGRESSS | NA |
Installation & Charging of Transformer | 20-08-2023 | UNDER PROGRESSS | NA |
Connection to Flats/Apartments | 20-09-2023 | UNDER PROGRESSS | NA |
PH works | 10-10-2023 | UNDER PROGRESSS | NA |
Laying of concealed Pipes | 28-11-2023 | UNDER PROGRESSS | NA |
PH Fittings | 10-12-2023 | UNDER PROGRESSS | NA |
Overhead Water Tanks | 30-12-2023 | UNDER PROGRESSS | NA |
Water Supply Connection to all units | 11-02-2024 | UNDER PROGRESSS | NA |
STP construction and completion | 28-02-2024 | UNDER PROGRESSS | NA |
Distempering & Colouring of all units and exteriors | 20-03-2024 | UNDER PROGRESSS | NA |
Fixation of doors and windows | 16-04-2024 | UNDER PROGRESSS | NA |
Scheduled Date of handing over possession | 16-05-2024 | UNDER PROGRESSS | NA |
Development of common areas, parks, gardens etc | 26-07-2024 | UNDER PROGRESSS | NA |
Site Development | 22-09-2022 | UNDER PROGRESSS | NA |
NA | NA | NA | NA |
Ground Floor/Stilt Floor | 12-10-2022 | UNDER PROGRESSS | NA |
1 Floor | 24-11-2022 | UNDER PROGRESSS | NA |
2 Floor | 22-12-2022 | UNDER PROGRESSS | NA |
3 Floor | 15-01-2023 | UNDER PROGRESSS | NA |
4 Floor | 30-01-2023 | UNDER PROGRESSS | NA |
NA | NA | NA | NA |
Ground Floor/Stilt Floor | 12-02-2023 | UNDER PROGRESSS | NA |
1 Floor | 28-02-2023 | UNDER PROGRESSS | NA |
2 Floor | 06-03-2023 | UNDER PROGRESSS | NA |
3 Floor | 30-03-2023 | UNDER PROGRESSS | NA |
4 Floor | 10-04-2023 | UNDER PROGRESSS | NA |
Electrical Works | 20-06-2023 | UNDER PROGRESSS | NA |
Concealed Cabling including Plugs & switches | 10-07-2023 | UNDER PROGRESSS | NA |
Installation & Charging of Transformer | 20-08-2023 | UNDER PROGRESSS | NA |
Connection to Flats/Apartments | 20-09-2023 | UNDER PROGRESSS | NA |
PH works | 10-10-2023 | UNDER PROGRESSS | NA |
Laying of concealed Pipes | 28-11-2023 | UNDER PROGRESSS | NA |
PH Fittings | 10-12-2023 | UNDER PROGRESSS | NA |
Overhead Water Tanks | 30-12-2023 | UNDER PROGRESSS | NA |
Water Supply Connection to all units | 11-02-2024 | UNDER PROGRESSS | NA |
STP construction and completion | 28-02-2024 | UNDER PROGRESSS | NA |
Distempering & Colouring of all units and exteriors | 20-03-2024 | UNDER PROGRESSS | NA |
Fixation of doors and windows | 16-04-2024 | UNDER PROGRESSS | NA |
Scheduled Date of handing over possession | 16-05-2024 | UNDER PROGRESSS | NA |
Development of common areas, parks, gardens etc | 26-07-2024 | UNDER PROGRESSS | NA |
Site Development | 22-09-2022 | UNDER PROGRESSS | NA |
NA | 07-10-2022 | UNDER PROGRESSS | NA |
Ground Floor/Stilt Floor | 12-10-2022 | UNDER PROGRESSS | NA |
1 Floor | 24-11-2022 | UNDER PROGRESSS | NA |
2 Floor | 22-12-2022 | UNDER PROGRESSS | NA |
3 Floor | 15-01-2023 | UNDER PROGRESSS | NA |
4 Floor | 30-01-2023 | UNDER PROGRESSS | NA |
NA | 07-02-2023 | UNDER PROGRESSS | NA |
Ground Floor/Stilt Floor | 12-02-2023 | UNDER PROGRESSS | NA |
1 Floor | 28-02-2023 | UNDER PROGRESSS | NA |
2 Floor | 06-03-2023 | UNDER PROGRESSS | NA |
3 Floor | 30-03-2023 | UNDER PROGRESSS | NA |
4 Floor | 10-04-2023 | UNDER PROGRESSS | NA |
Electrical Works | 20-06-2023 | UNDER PROGRESSS | NA |
Concealed Cabling including Plugs & switches | 10-07-2023 | UNDER PROGRESSS | NA |
Installation & Charging of Transformer | 20-08-2023 | UNDER PROGRESSS | NA |
Connection to Flats/Apartments | 20-09-2023 | UNDER PROGRESSS | NA |
PH works | 10-10-2023 | UNDER PROGRESSS | NA |
Laying of concealed Pipes | 28-11-2023 | UNDER PROGRESSS | NA |
PH Fittings | 10-12-2023 | UNDER PROGRESSS | NA |
Overhead Water Tanks | 30-12-2023 | UNDER PROGRESSS | NA |
Water Supply Connection to all units | 11-02-2024 | UNDER PROGRESSS | NA |
STP construction and completion | 28-02-2024 | UNDER PROGRESSS | NA |
Distempering & Colouring of all units and exteriors | 20-03-2024 | UNDER PROGRESSS | NA |
Fixation of doors and windows | 16-04-2024 | UNDER PROGRESSS | NA |
Scheduled Date of handing over possession | 16-05-2024 | UNDER PROGRESSS | NA |
Development of common areas, parks, gardens etc | 26-07-2024 | UNDER PROGRESSS | NA |
: Residential | |
: 32
|
|
Residential Flats/ House | |||||
---|---|---|---|---|---|
S. No. | Flat No./ House No. | ||||
Area in square metres |
Ownership | ||||
Carpet Area | Balcony Area | Exclusive Open Terrace Area | |||
1 | 101 | 54.46 Sqmt | 4.69 Sqmt | 00 | Land Owner |
2 | 102 | 54.83 Sqmt | 4.69 Sqmt | 00 | Land Owner |
3 | 103 | 55.06 Sqmt | 4.69 Sqmt | 00 | Promoter |
4 | 104 | 24.13 Sqmt | 4.69 Sqmt | 00 | Land Owner |
5 | 105 | 26.64 Sqmt | 4.69 Sqmt | 00 | Promoter |
6 | 106 | 60.04 Sqmt | 4.69 Sqmt | 00 | Promoter |
7 | 107 | 54.81 Sqmt | 4.69 Sqmt | 00 | Promoter |
8 | 108 | 79.61 Sqmt | 4.69 Sqmt | 00 | Promoter |
9 | 201 | 54.46 Sqmt | 4.69 Sqmt | 00 | Promoter |
10 | 202 | 54.83 Sqmt | 4.69 Sqmt | 00 | Promoter |
11 | 203 | 55.06 Sqmt | 4.69 Sqmt | 00 | Promoter |
12 | 204 | 24.13 Sqmt | 4.69 Sqmt | 00 | Promoter |
13 | 205 | 26.64 Sqmt | 4.69 Sqmt | 00 | Promoter |
14 | 206 | 60.04 Sqmt | 4.69 Sqmt | 00 | Promoter |
15 | 207 | 54.81 Sqmt | 4.69 Sqmt | 00 | Land Owner |
16 | 208 | 79.61 Sqmt | 4.69 Sqmt | 00 | Land Owner |
17 | 301 | 54.46 Sqmt | 4.69 Sqmt | 00 | Land Owner |
18 | 302 | 54.83 Sqmt | 4.69 Sqmt | 00 | Land Owner |
19 | 303 | 55.06 Sqmt | 4.69 Sqmt | 00 | Promoter |
20 | 304 | 24.13 Sqmt | 4.69 Sqmt | 00 | Land Owner |
21 | 305 | 26.64 Sqmt | 4.69 Sqmt | 00 | Promoter |
22 | 306 | 60.04 Sqmt | 4.69 Sqmt | 00 | Promoter |
23 | 307 | 54.81 Sqmt | 4.69 Sqmt | 00 | Promoter |
24 | 308 | 79.61 Sqmt | 4.69 Sqmt | 00 | Promoter |
25 | 401 | 54.46 Sqmt | 4.69 Sqmt | 00 | Promoter |
26 | 402 | 54.83 Sqmt | 4.69 Sqmt | 00 | Promoter |
27 | 403 | 55.06 Sqmt | 4.69 Sqmt | 00 | Land Owner |
28 | 404 | 24.13 Sqmt | 4.69 Sqmt | 00 | Land Owner |
29 | 405 | 26.64 Sqmt | 4.69 Sqmt | 00 | Promoter |
30 | 406 | 60.04 Sqmt | 4.69 Sqmt | 00 | Promoter |
31 | 407 | 54.81 Sqmt | 4.69 Sqmt | 00 | Land Owner |
32 | 408 | 79.61 Sqmt | 4.69 Sqmt | 00 | Promoter |
Types of garages and parking | ||||||
---|---|---|---|---|---|---|
House No. | Type of Garage/ Parking allotted | Serial No., if any | Dimension (Length x Width) in Metres | Floor area in sq. metres | Garage/Parking area cost is included or additional | |
101 | Covered Parking | 1 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 102 | Covered Parking | 2 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 103 | Covered Parking | 3 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 104 | Covered Parking | 4 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 105 | Covered Parking | 5 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 106 | Covered Parking | 6 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 107 | Covered Parking | 7 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 108 | Covered Parking | 8 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 201 | Covered Parking | 9 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 202 | Covered Parking | 10 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 203 | Covered Parking | 11 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 204 | Covered Parking | 12 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 205 | Covered Parking | 13 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 206 | Covered Parking | 14 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 207 | Covered Parking | 15 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 208 | Covered Parking | 16 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 301 | Covered Parking | 17 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 302 | Covered Parking | 18 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 303 | Covered Parking | 19 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 304 | Covered Parking | 20 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 305 | Covered Parking | 21 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 306 | Covered Parking | 22 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 307 | Covered Parking | 23 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 308 | Covered Parking | 24 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 401 | Covered Parking | 25 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 402 | Covered Parking | 26 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 403 | Covered Parking | 27 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 404 | Covered Parking | 28 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 405 | Covered Parking | 29 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 406 | Covered Parking | 30 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 407 | Covered Parking | 31 | 6.67 Mx3.16M | 21.09 Sqmt | Included | 408 | Covered Parking | 32 | 6.67 Mx3.16M | 21.09 Sqmt | Included |
Particulars of Facilities | Status of the facility | Brief description of facility |
---|---|---|
Drinking Water Facility | Ground Water | Copy of Consent Letter |
Fire Fighting Facility | Yes | Affidavit/Under taking |
Emergency Evacuation Services | Yes | Stair Case |
Use of Renewable Energy | Yes | DG BACK UP |
Lift Facility | Yes | Jhonson Brand, 6 Person Capacity with ARD Facility |
Market Complex | No | |
Community Hall | Yes | 32.40 Sqmt Community hall with one door and two windows |
Gymnasium | No | |
Swimming Pool | No | |
Play Ground | No | |
Park/Garden | No | |
Plantation Area | Yes | Both side Plantation with 113.02 Sqmt (80 sqm per one tree) |
Others(Please Specify) | No | |
Internal Road | Yes | Black top Road 381.06 sqm with drive way |
External Road | Yes | Black top Road 30 ft wide BDA Road |
Elecricity Supply | Yes | Copy of Consent Letter |
Other Amenities | Yes | CC Camera all side |