Promoter Details
Promoter Name :
KALINGA KESHARI RATH
Project Name :
BILASINI ENCLAVE
Project Location :
(S+4, 21 Units) Over Plot No. 350/429, Khata No. 180/17, Plot No. 350/427, Khata No. 180/136, Mouza-Tamando, Tahasil- Bhubaneswar, Bhubaneswar-752054, Dist- Khordha, Odisha

Form- I

A. Promoter's Details

:  Evos Buildcon Private Limited :  Private Company
:  U70101OR2010PTC012674 :View
NA :  PLOT NO-284/2485
:  Plot No.284/2485, Patrapada, Near Union Bank of India, Bhubaneswar-751019, Dist- Khordha, Odisha. :  kkrath@evos.co.in
:  9861930011 :  9040051152
:  AACCE5477G :View
:  10 YEARS :  Odisha
:  www.evos.co.in

B. Details of Board of Directors / Partners / MC Members

:  KALINGA KESHARI RATH :  
:  Managing Director :  ALWPR1547G
:PAN Card :  kkrath@evos.co.in
:  B-TECH(MECHANICAL) MBA :  9040051152
:  10 YEARS
:  Yes :  NA
:  RAJASHREE RATH :  
:  Director :  AWMPR6439C
:PAN Card :  support@evos.co.in
:  B.A :  9040051152
:  10 YEARS
:  Yes :  NA

Annexure-1

Details of last projects already implemented (Ongoing or Complete)

Annexure-2

Details of the project to be registered

:   New :  BILASINI ENCLAVE
:  Residential :  (S+4, 21 Units) Over Plot No. 350/429, Khata No. 180/17, Plot No. 350/427, Khata No. 180/136, Mouza-Tamando, Tahasil- Bhubaneswar, Bhubaneswar-752054, Dist- Khordha, Odisha
:  Khordha :  Bhubaneswar
:  752054 :  Development Authority
:  BHUBANESWAR DEVELOPMENT AUTHORITY
:  S+4 residential apartment :  NA

Land Details of the Project


:  350/429 :  180/17
:  TAMANDO :  6069
:  Yes
No :  View
:  View
:  Other Person
:  NITYANANDA BAL :  THROUGH REGISTERED POWER OF ATTORNEY .
: No
: Yes
:  11131906847 :  04-09-2019
:  SUB-REGISTRAR KHANDAGIRI,BHUBANESWAR :  Attached

:  350/427 :  180/136
:  TAMANDO :  6069
:  Yes
No :  View
:  View
:  Other Person
:  NITYANANDA BAL :  THROUGH REGISTERED POWER OF ATTORNEY.
: No
: Yes
:  11131906847 :  04-09-2019
:  SUB-REGISTRAR KHANDAGIRI,BHUBANESWAR :  Attached

Development Agreement

: Yes
Serial No. Particulars of the Person Land/Plot Details Share of the Person Document Attached
1 NITYANANDA BAL KHATA NO-180/17,PLOT NO-350/429,KHATA NO-180/136,PLOT NO-350/427 40%   Agreement Copy

Building Plan

  View   View
  Download site plan 27-03-2021

Conditions of building plan approval

Sl. No. Description of Conditions Schedule date of compliance Present Status
1 storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per regulation-44 of BDA (planning & building standards)regulation,2008 04-09-2022 NOT YET STARTED
2 the space which is meant for parking shall not be changed to any other use and shall not be partitioned/closed in any manner 04-09-2022 not yet started
3 20% of the parking space in group housing/apartment building shall be exclusively earnmarked for ambulance, fire tender,physically handicapped persons and outside visitors with signage as per norms under regulation -35(11)(12)of BDA (Planning & Building Standards)Regulations 2008 04-09-2022 not yet started
4 Plantaion over 20% of the plot area shall be made by the applicant as per provision under regulation -28 of BDA (Planning and Building Standards)Regulation2008 26-09-2022 not yet started
5 If the construction/Development are not as per the approved plan /deviated beyond permissible norms,The performance security shall forfeited and action shall be initiated against the applicant /builder /developer as per the provisions of the ODA act ,1982 rules and regulation made there under 04-09-2022 not yet started
6 The owner /applicant/architect/structural engineers are fully and jointly responsible for any structural failure of the building due to any structural/construction effects,authority will be no way be held responsible for the same in what so ever manner 04-09-2022 not yet started
7 The concerned Architect/Applicant/Developer are fully responsible for any deviations additions & alternations beyond approved plan/defective construction etc.shall be liable for action as per the provisions of the regulation. 04-09-2022 not yet started
8 The applicant shall obtain infrastructural specification and subsquent clearance with regard to development of infrastructure from BMC/BDA before commencement of construction 04-09-2022 not yet started
9 All the stipulated conditions of the NOG given by BMC,BDA shall be adhered to strictly.All the fire fighting installation etc are to be ensured and maintained by the applicant as per 04-09-2022 not yet started
10 No storm water shall be discharged to the public road/public premises and other adjoining plots 04-09-2022 not yet started
11 Adhere to the provisions of BDA (Planning & Building Standards) Regulation strictly and conditions thereto 04-09-2022 not yet started
12 The authority shall in no way be held responsible for any structural failure and damage due to earthquake/cyclone/any other natural disaster 04-09-2022 not yet started
13 The number of dwelling units so approved shall not be changed in any manner 04-09-2022 not yet started
14 the construction workers welfare Cess @ 1% i.e Rs. 5,41,850/-(Rupees Five Lakhs forty one thousand eight hundred fifty only) shall be adjusted from the security deposit before issue of Occupancy Certificate 04-09-2022 not yet started

Layout Plan

: Yes :  View

Location Map with geo-coordinates of bend points

Point No. Latitude Longitude
1 85°44'57.1" 20°14'31.8"
2 85°44'56.1" 20°14'29.6"
3 85°44'56.4" 20°14'30.2"
4 85°44'55.6" 20°14'30.6"
View

Milestone of Project Construction

Description* Scheduled date of completion Current Status Site Images
Site Development 30-01-2020 WORK IN PROGRESS
Roof Casting NA NA NA
Ground Floor/Stilt Floor 15-03-2020 Not started
1 Floor 30-04-2020 Not started
2 Floor 15-06-2020 Not started
3 Floor 31-07-2020 Not started
4 Floor 15-09-2020 Not started
Brick Work & Plastering NA NA NA
Ground Floor/Stilt Floor 30-11-2020 Not started
1 Floor 31-12-2020 Not started
2 Floor 15-02-2021 Not started
3 Floor 31-03-2021 Not started
4 Floor 15-05-2021 Not started
Electrical Works 15-05-2022 Not started
Concealed Cabling including Plugs & switches 15-11-2021 Not started
Installation & Charging of Transformer 01-05-2022 Not started
Connection to Flats/Apartments 10-05-2022 Not started
PH works 15-05-2022 Not started
Laying of concealed Pipes 15-11-2021 Not started
PH Fittings 15-03-2022 Not started
Overhead Water Tanks 15-04-2022 Not started
Water Supply Connection to all units 30-04-2022 Not started
STP construction and completion 10-05-2022 Not started
Distempering & Colouring of all units and exteriors 15-05-2022 Not started
Fixation of doors and windows 31-03-2021 Not started
Scheduled Date of handing over possession 04-09-2022 Not started
Development of common areas, parks, gardens etc 01-08-2022 Not started
Site Development 30-01-2020 WORK IN PROGRESS NA
NA NA NA NA
Ground Floor/Stilt Floor 15-03-2020 COMPLETED
1 Floor 30-04-2020 COMPLETED
2 Floor 15-06-2020 COMPLETED
3 Floor 31-07-2020 COMPLETED
4 Floor 15-09-2020 COMPLETED
NA NA NA NA
Ground Floor/Stilt Floor 30-11-2020 COMPLETED
1 Floor 31-12-2020 COMPLETED
2 Floor 15-02-2021 COMPLETED
3 Floor 31-03-2021 COMPLETED
4 Floor 15-05-2021 COMPLETED
Electrical Works 15-05-2022 WORK IN PROGRESS
Concealed Cabling including Plugs & switches 15-11-2021 WORK IN PROGRESS
Installation & Charging of Transformer 01-05-2022 NOT YET STARTED NA
Connection to Flats/Apartments 10-05-2022 NOT YET STARTED NA
PH works 15-05-2022 WORK IN PROGRESS
Laying of concealed Pipes 15-11-2021 COMPLETED
PH Fittings 15-03-2022 NOT YET STARTED NA
Overhead Water Tanks 15-04-2022 NOT YET STARTED NA
Water Supply Connection to all units 30-04-2022 NOT YET STARTED NA
STP construction and completion 10-05-2022 NOT YET STARTED NA
Distempering & Colouring of all units and exteriors 15-05-2022 WORK IN PROGRESS
Fixation of doors and windows 31-03-2021 WORK IN PROGRESS
Scheduled Date of handing over possession 04-09-2022 NOT YET STARTED NA
Development of common areas, parks, gardens etc 01-08-2022 NOT YET STARTED NA
Site Development 30-01-2020 WORK IN PROGRESS NA
NA 30-01-2020 WORK IN PROGRESS NA
Ground Floor/Stilt Floor 15-03-2020 COMPLETED NA
1 Floor 30-04-2020 COMPLETED NA
2 Floor 15-06-2020 COMPLETED NA
3 Floor 31-07-2020 COMPLETED NA
4 Floor 15-09-2020 COMPLETED NA
NA 15-09-2020 COMPLETED NA
Ground Floor/Stilt Floor 30-11-2020 COMPLETED NA
1 Floor 31-12-2020 COMPLETED NA
2 Floor 15-02-2021 COMPLETED NA
3 Floor 31-03-2021 COMPLETED NA
4 Floor 15-05-2021 COMPLETED NA
Electrical Works 15-05-2022 WORK IN PROGRESS NA
Concealed Cabling including Plugs & switches 15-11-2021 WORK IN PROGRESS NA
Installation & Charging of Transformer 01-05-2022 NOT YET STARTED NA
Connection to Flats/Apartments 10-05-2022 NOT YET STARTED NA
PH works 15-05-2022 WORK IN PROGRESS NA
Laying of concealed Pipes 15-11-2021 COMPLETED NA
PH Fittings 15-03-2022 NOT YET STARTED NA
Overhead Water Tanks 15-04-2022 NOT YET STARTED NA
Water Supply Connection to all units 30-04-2022 NOT YET STARTED NA
STP construction and completion 10-05-2022 NOT YET STARTED NA
Distempering & Colouring of all units and exteriors 15-05-2022 WORK IN PROGRESS NA
Fixation of doors and windows 31-03-2021 WORK IN PROGRESS NA
Scheduled Date of handing over possession 04-09-2022 NOT YET STARTED NA
Development of common areas, parks, gardens etc 01-08-2022 NOT YET STARTED NA
Site Development 30-01-2020 completed
NA 30-01-2020 completed
Ground Floor/Stilt Floor 15-03-2020 COMPLETED
1 Floor 30-04-2020 COMPLETED
2 Floor 15-06-2020 COMPLETED
3 Floor 31-07-2020 COMPLETED
4 Floor 15-09-2020 COMPLETED
NA 15-09-2020 COMPLETED
Ground Floor/Stilt Floor 30-11-2020 COMPLETED
1 Floor 31-12-2020 COMPLETED
2 Floor 15-02-2021 COMPLETED
3 Floor 31-03-2021 COMPLETED
4 Floor 15-05-2021 COMPLETED NA
Electrical Works 15-05-2022 COMPLETED
Concealed Cabling including Plugs & switches 15-11-2021 WORK IN PROGRESS NA
Installation & Charging of Transformer 01-05-2022 COMPLETED
Connection to Flats/Apartments 10-05-2022 NOT YET STARTED NA
PH works 15-05-2022 WORK IN PROGRESS NA
Laying of concealed Pipes 15-11-2021 COMPLETED NA
PH Fittings 15-03-2022 WORK IN PROGRESS NA
Overhead Water Tanks 15-04-2022 WORK IN PROGRESS NA
Water Supply Connection to all units 30-04-2022 WORK IN PROGRESS NA
STP construction and completion 10-05-2022 COMPLETED
Distempering & Colouring of all units and exteriors 15-05-2022 WORK IN PROGRESS NA
Fixation of doors and windows 31-03-2021 WORK IN PROGRESS NA
Scheduled Date of handing over possession 04-09-2022 NOT YET STARTED NA
Development of common areas, parks, gardens etc 01-08-2022 NOT YET STARTED NA
Site Development 30-01-2020 completed NA
NA 30-01-2020 completed NA
Ground Floor/Stilt Floor 15-03-2020 COMPLETED NA
1 Floor 30-04-2020 COMPLETED NA
2 Floor 15-06-2020 COMPLETED NA
3 Floor 31-07-2020 COMPLETED NA
4 Floor 15-09-2020 COMPLETED NA
NA 15-09-2020 COMPLETED NA
Ground Floor/Stilt Floor 30-11-2020 COMPLETED NA
1 Floor 31-12-2020 COMPLETED NA
2 Floor 15-02-2021 COMPLETED NA
3 Floor 31-03-2021 COMPLETED NA
4 Floor 15-05-2021 COMPLETED NA
Electrical Works 15-05-2022 COMPLETED NA
Concealed Cabling including Plugs & switches 15-11-2021 COMPLETED
Installation & Charging of Transformer 01-05-2022 COMPLETED NA
Connection to Flats/Apartments 10-05-2022 COMPLETED NA
PH works 15-05-2022 COMPLETED NA
Laying of concealed Pipes 15-11-2021 COMPLETED NA
PH Fittings 15-03-2022 COMPLETED NA
Overhead Water Tanks 15-04-2022 COMPLETED NA
Water Supply Connection to all units 30-04-2022 COMPLETED NA
STP construction and completion 10-05-2022 COMPLETED NA
Distempering & Colouring of all units and exteriors 15-05-2022 COMPLETED
Fixation of doors and windows 31-03-2021 COMPLETED NA
Scheduled Date of handing over possession 04-09-2022 NOT YET STARTED NA
Development of common areas, parks, gardens etc 01-08-2022 COMPLETED
Site Development 30-01-2020 completed
NA 30-01-2020 completed
Ground Floor/Stilt Floor 15-03-2020 COMPLETED
1 Floor 30-04-2020 COMPLETED
2 Floor 15-06-2020 COMPLETED NA
3 Floor 31-07-2020 COMPLETED NA
4 Floor 15-09-2020 COMPLETED NA
NA 15-09-2020 COMPLETED NA
Ground Floor/Stilt Floor 30-11-2020 COMPLETED NA
1 Floor 31-12-2020 COMPLETED NA
2 Floor 15-02-2021 COMPLETED NA
3 Floor 31-03-2021 COMPLETED NA
4 Floor 15-05-2021 COMPLETED NA
Electrical Works 15-05-2022 COMPLETED
Concealed Cabling including Plugs & switches 15-11-2021 COMPLETED NA
Installation & Charging of Transformer 01-05-2022 COMPLETED NA
Connection to Flats/Apartments 10-05-2022 COMPLETED NA
PH works 15-05-2022 COMPLETED
Laying of concealed Pipes 15-11-2021 COMPLETED NA
PH Fittings 15-03-2022 COMPLETED NA
Overhead Water Tanks 15-04-2022 COMPLETED NA
Water Supply Connection to all units 30-04-2022 COMPLETED NA
STP construction and completion 10-05-2022 COMPLETED NA
Distempering & Colouring of all units and exteriors 15-05-2022 COMPLETED NA
Fixation of doors and windows 31-03-2021 COMPLETED NA
Scheduled Date of handing over possession 04-09-2022 NOT YET STARTED NA
Development of common areas, parks, gardens etc 01-08-2022 COMPLETED NA
Site Development 30-01-2020 completed NA
NA 30-01-2020 completed NA
Ground Floor/Stilt Floor 15-03-2020 COMPLETED NA
1 Floor 30-04-2020 COMPLETED NA
2 Floor 15-06-2020 COMPLETED NA
3 Floor 31-07-2020 COMPLETED NA
4 Floor 15-09-2020 COMPLETED NA
NA 15-09-2020 COMPLETED NA
Ground Floor/Stilt Floor 30-11-2020 COMPLETED NA
1 Floor 31-12-2020 COMPLETED NA
2 Floor 15-02-2021 COMPLETED NA
3 Floor 31-03-2021 COMPLETED NA
4 Floor 15-05-2021 COMPLETED NA
Electrical Works 15-05-2022 COMPLETED NA
Concealed Cabling including Plugs & switches 15-11-2021 COMPLETED NA
Installation & Charging of Transformer 01-05-2022 COMPLETED NA
Connection to Flats/Apartments 10-05-2022 COMPLETED NA
PH works 15-05-2022 COMPLETED NA
Laying of concealed Pipes 15-11-2021 COMPLETED NA
PH Fittings 15-03-2022 COMPLETED NA
Overhead Water Tanks 15-04-2022 COMPLETED NA
Water Supply Connection to all units 30-04-2022 COMPLETED NA
STP construction and completion 10-05-2022 COMPLETED NA
Distempering & Colouring of all units and exteriors 15-05-2022 COMPLETED NA
Fixation of doors and windows 31-03-2021 COMPLETED NA
Scheduled Date of handing over possession 04-09-2022 NOT YET STARTED NA
Development of common areas, parks, gardens etc 01-08-2022 COMPLETED NA
Site Development 30-01-2020 completed
NA 30-01-2020 completed NA
Ground Floor/Stilt Floor 15-03-2020 COMPLETED NA
1 Floor 30-04-2020 COMPLETED NA
2 Floor 15-06-2020 COMPLETED NA
3 Floor 31-07-2020 COMPLETED NA
4 Floor 15-09-2020 COMPLETED NA
NA 15-09-2020 COMPLETED NA
Ground Floor/Stilt Floor 30-11-2020 COMPLETED NA
1 Floor 31-12-2020 COMPLETED NA
2 Floor 15-02-2021 COMPLETED NA
3 Floor 31-03-2021 COMPLETED NA
4 Floor 15-05-2021 COMPLETED NA
Electrical Works 15-05-2022 COMPLETED NA
Concealed Cabling including Plugs & switches 15-11-2021 COMPLETED NA
Installation & Charging of Transformer 01-05-2022 COMPLETED NA
Connection to Flats/Apartments 10-05-2022 COMPLETED NA
PH works 15-05-2022 COMPLETED NA
Laying of concealed Pipes 15-11-2021 COMPLETED NA
PH Fittings 15-03-2022 COMPLETED NA
Overhead Water Tanks 15-04-2022 COMPLETED NA
Water Supply Connection to all units 30-04-2022 COMPLETED NA
STP construction and completion 10-05-2022 COMPLETED NA
Distempering & Colouring of all units and exteriors 15-05-2022 COMPLETED NA
Fixation of doors and windows 31-03-2021 COMPLETED NA
Scheduled Date of handing over possession 04-09-2022 NOT YET STARTED NA
Development of common areas, parks, gardens etc 01-08-2022 COMPLETED NA

Category and no. of units to be developed

:  Residential
:  
:  21
:  
:  
:  
Residential Flats/ House
S. No. Flat No./ House No.

Area in square metres

Ownership
Carpet Area Balcony Area Exclusive Open Terrace Area
1 101 65 7.4 N/A Promoter
2 102 65 7.4 N/A Land Owner
3 103 67.5 8 N/A Land Owner
4 104 67.5 8 N/A Land Owner
5 105 82.5 8.8 N/A Promoter
6 106 82.5 8.8 N/A Promoter
7 201 65 7.4 N/A Promoter
8 202 65 7.4 N/A Promoter
9 203 67.5 8 N/A Land Owner
10 204 67.5 8 N/A Land Owner
11 205 82.5 8.8 N/A Promoter
12 206 82.5 8.8 N/A Promoter
13 301 65 7.4 N/A Promoter
14 302 65 7.4 N/A Land Owner
15 303 67.5 8 N/A Promoter
16 304 67.5 8 N/A Promoter
17 305 82.5 8.8 N/A Promoter
18 306 82.5 8.8 N/A Promoter
19 401 65 7.4 N/A Promoter
20 402 65 7.4 N/A Land Owner
21 404 67.5 8 N/A Land Owner
Types of garages and parking
House No. Type of Garage/ Parking allotted Serial No., if any Dimension (Length x Width) in Metres Floor area in sq. metres Garage/Parking area cost is included or additional
101 Covered Parking 1 4X3 12 Included
102 Covered Parking 2 4X3 12 Included
103 Covered Parking 3 4X3 12 Included
104 Covered Parking 4 4X3 12 Included
105 Covered Parking 5 4X3 12 Included
106 Covered Parking 6 4X3 12 Included
201 Covered Parking 7 4X3 12 Included
202 Covered Parking 8 4X3 12 Included
203 Covered Parking 9 4X3 12 Included
204 Covered Parking 10 4X3 12 Included
205 Covered Parking 11 4X3 12 Included
206 Covered Parking 12 4X3 12 Included
301 Covered Parking 13 4X3 12 Included
302 Covered Parking 14 4X3 12 Included
303 Covered Parking 15 4X3 12 Included
304 Covered Parking 16 4X3 12 Included
305 Covered Parking 17 4X3 12 Included
306 Covered Parking 18 4X3 12 Included
401 Covered Parking 19 4X3 12 Included
402 Covered Parking 20 4X3 12 Included
404 Covered Parking 21 4X3 12 Included
Yes

Facilities to be provided

Particulars of Facilities Status of the facility Brief description of facility
Drinking Water Facility PHED Copy of NOC Letter
Fire Fighting Facility No
Emergency Evacuation Services No
Use of Renewable Energy No
Lift Facility Yes 2 Nos. of KONE,OTIS brand lift of 6 person capacity with ARD facility
Market Complex No
Community Hall Yes 20.32 sqm community hall with tiles flooring
Gymnasium No
Swimming Pool No
Play Ground No
Park/Garden No
Plantation Area Yes 242.70SQMTR
Others(Please Specify) No
Internal Road Yes 58.3M X 3.6M internal road with flooring tiles specification
External Road No
Elecricity Supply Yes Copy of Consent Letter
Other Amenities No

Bank Particulars of the Project

  STATE BANK OF INDIA
  RCE CAMPUS BRANCH
  38748057401
  SBIN0005302
   View
  2567648
  9437488712

Particulars of Architect/Construction Engineer/Contractor/Chartered Accountant

Name position Address with mobile number and email address Registration number Key real estate projects Is active Effective date
GOURAV CHOUDHURY Chartered Accountant 19-A,BAPUJI NAGAR,BHUBANESWAR-751009,MOB-9776022240,EMAIL-gourav.choudhurt1988@gmail.com 309583 TAMANDO,BHUBANESWAR
KESHARI NANDAN PRAKALPA PVT LTD Contractor PLOT NO-284/2485,PATRAPADA,BHUBANESWAR-751019,mob-9861930011,email-kesharin579@gmail.com U70101OR2015PTC019206 TAMANDO BHUBANESWAR
LAGNAJIT MOHAPATRA Architect GHATIKIA,BHUBANESWAR,MOB-9861194401,EMAIL-thresholdarchitects2@gmail.com CA/11/51306 TAMANDO BHUBANESWAR
ER.SIDDHARTH DAS Construction Engineer PATRAPADA,BHUBANESWAR,,MOB-7809653552,EMAIL-adwitya.lenka@gmail.com M 1247462 TAMANDO,BHUBANESWAR

Financial Details

:  494 :   View
  04-09-2022 :  70
:  424 :  0

Documents Attached

Description of Document Option Documents
Fire Safety Certificate Undertaking Attached
Affidavit in Form-A as per clause-l of sub-section-2 of section-4 of the Act Yes Attached
Allotment letter format Yes Attached
Conveyance Deed Format Yes Attached
Affidavit to adopt agreement for sale format as per Rule-8(1) of ORE (R and D) Rules, 2017 Yes Attached
Annual Report 2019-20 Attached
Annual Report 2017-18 Attached
IT Return 2019-20 Attached
IT Return 2017-18 Attached
Audit Report 2019-20 Attached
Audit Report 2017-18 Attached

Additional Documents Attached

Sl. No. Title of the document Upload Document
1 CANCEL POWER OF ATTORNEY
2 CANCEL OF SALE AGREEMENT
3 PARTITION DEED
4 EC PLOT NO-180/136 2007 T0 31/12/2018
5 EC PLOT NO-180/17 2007 T0 31/12/2018
6 FY-2017-18 ANNUAL REPORT
7 FY 2017-18 AUDIT REPORT
8 FY 2017-18 IT RETURN
9 FY 2018-19 ANNUAL REPORT
10 FY 2018-19 AUDIT REPORT
11 FY 2018-19 IT RETURN

Other documents

“I undertake that the information submitted by me in this application are correct and true to best my knowledge. I also understand that providing false or wrong information is punishable under the Section-60 of the Real Estate (Regulation & Development) Act, 2016. I also further understand that furnishing wrong or false information will lead to rejection of my application registration of the project with forfeiture of registration fee and other charges deposited by me.”
  DOCUMENT ATTACH FOR CANCELLATION OF POA & AGREEMENT. Khata No.-180/17, Plot No.- 350/429, ROR in the name of Udayanath Bala (1)We are processing the matter with the concerned government authorities and trying our best to get it at the earliest. Further shall upload the same as soon as any document related to it is received from the concerned government authority. (2)Registered Partition Deed Uploaded (3) We have already uploaded E.C from 01/01/1995 to 18/09/2019, So, the required period is well covered. Khata No.-180/136 Plot No.- 350/427, ROR in the name of Nityananda Bala 1. We are processing the matter with the concerned government authorities and trying our best to get it at the earliest. Further shall upload the same as soon as any document related to it is received from the concerned government authority. 2.The Building Plan was approved by the BDA vide it's letter No.-8659 28/03/2018 in favor of the Land Owner (the copy of the approval letter has already been uploaded). Whereas in the drawing the name of the then GPA Holder, Mr. Shasank Pradhan, Director M/S. Green field Manor Pvt. Ltd. is reflected. It is a fact that on the date of plan approval as mentioned above Mr. Shasank Pradhan, Director M/S. Green field Manor Pvt. Ltd. was the GPA Holder of the recorded Land owner. Subsequently on 05/09/2019, the recorded owner vide registered document no.- 11131906824 has cancelled the same & on the same date a new GPA has been registered vide document no.- 11131906847 in favor of Evos Buildcon Pvt. Ltd. M.D Kalinga Keshari Rath (both the documents have already been uploaded). Since, the title/Ownership of the land has not been changed in any manner whatsoever & moreover we shall undertake construction in accordance with the above refereed plan approval given by the BDA.

Construction Progress

Updated Construction Progress

SL NO. Description Scheduled date of completion Current Status Remarks
1 Site Development 30-01-2020 WORK IN PROGRESS
2 Roof Casting NA NA NA
3 Ground Floor/Stilt Floor 15-03-2020 Not started
4 1 Floor 30-04-2020 Not started
5 2 Floor 15-06-2020 Not started
6 3 Floor 31-07-2020 Not started
7 4 Floor 15-09-2020 Not started
8 Brick Work & Plastering NA NA NA
9 Ground Floor/Stilt Floor 30-11-2020 Not started
10 1 Floor 31-12-2020 Not started
11 2 Floor 15-02-2021 Not started
12 3 Floor 31-03-2021 Not started
13 4 Floor 15-05-2021 Not started
14 Electrical Works 15-05-2022 Not started
15 Concealed Cabling including Plugs & switches 15-11-2021 Not started
16 Installation & Charging of Transformer 01-05-2022 Not started
17 Connection to Flats/Apartments 10-05-2022 Not started
18 PH works 15-05-2022 Not started
19 Laying of concealed Pipes 15-11-2021 Not started
20 PH Fittings 15-03-2022 Not started
21 Overhead Water Tanks 15-04-2022 Not started
22 Water Supply Connection to all units 30-04-2022 Not started
23 STP construction and completion 10-05-2022 Not started
24 Distempering & Colouring of all units and exteriors 15-05-2022 Not started
25 Fixation of doors and windows 31-03-2021 Not started
26 Scheduled Date of handing over possession 04-09-2022 Not started
27 Development of common areas, parks, gardens etc 01-08-2022 Not started
Updated Changes on 01-12-2021
28 Site Development 30-01-2020 WORK IN PROGRESS NA
29 NA NA NA NA
30 Ground Floor/Stilt Floor 15-03-2020 COMPLETED
31 1 Floor 30-04-2020 COMPLETED
32 2 Floor 15-06-2020 COMPLETED
33 3 Floor 31-07-2020 COMPLETED
34 4 Floor 15-09-2020 COMPLETED
35 NA NA NA NA
36 Ground Floor/Stilt Floor 30-11-2020 COMPLETED
37 1 Floor 31-12-2020 COMPLETED
38 2 Floor 15-02-2021 COMPLETED
39 3 Floor 31-03-2021 COMPLETED
40 4 Floor 15-05-2021 COMPLETED
41 Electrical Works 15-05-2022 WORK IN PROGRESS
42 Concealed Cabling including Plugs & switches 15-11-2021 WORK IN PROGRESS
43 Installation & Charging of Transformer 01-05-2022 NOT YET STARTED NA
44 Connection to Flats/Apartments 10-05-2022 NOT YET STARTED NA
45 PH works 15-05-2022 WORK IN PROGRESS
46 Laying of concealed Pipes 15-11-2021 COMPLETED
47 PH Fittings 15-03-2022 NOT YET STARTED NA
48 Overhead Water Tanks 15-04-2022 NOT YET STARTED NA
49 Water Supply Connection to all units 30-04-2022 NOT YET STARTED NA
50 STP construction and completion 10-05-2022 NOT YET STARTED NA
51 Distempering & Colouring of all units and exteriors 15-05-2022 WORK IN PROGRESS
52 Fixation of doors and windows 31-03-2021 WORK IN PROGRESS
53 Scheduled Date of handing over possession 04-09-2022 NOT YET STARTED NA
54 Development of common areas, parks, gardens etc 01-08-2022 NOT YET STARTED NA
Updated Changes on 26-07-2022
55 Site Development 30-01-2020 WORK IN PROGRESS NA
56 NA 30-01-2020 WORK IN PROGRESS NA
57 Ground Floor/Stilt Floor 15-03-2020 COMPLETED NA
58 1 Floor 30-04-2020 COMPLETED NA
59 2 Floor 15-06-2020 COMPLETED NA
60 3 Floor 31-07-2020 COMPLETED NA
61 4 Floor 15-09-2020 COMPLETED NA
62 NA 15-09-2020 COMPLETED NA
63 Ground Floor/Stilt Floor 30-11-2020 COMPLETED NA
64 1 Floor 31-12-2020 COMPLETED NA
65 2 Floor 15-02-2021 COMPLETED NA
66 3 Floor 31-03-2021 COMPLETED NA
67 4 Floor 15-05-2021 COMPLETED NA
68 Electrical Works 15-05-2022 WORK IN PROGRESS NA
69 Concealed Cabling including Plugs & switches 15-11-2021 WORK IN PROGRESS NA
70 Installation & Charging of Transformer 01-05-2022 NOT YET STARTED NA
71 Connection to Flats/Apartments 10-05-2022 NOT YET STARTED NA
72 PH works 15-05-2022 WORK IN PROGRESS NA
73 Laying of concealed Pipes 15-11-2021 COMPLETED NA
74 PH Fittings 15-03-2022 NOT YET STARTED NA
75 Overhead Water Tanks 15-04-2022 NOT YET STARTED NA
76 Water Supply Connection to all units 30-04-2022 NOT YET STARTED NA
77 STP construction and completion 10-05-2022 NOT YET STARTED NA
78 Distempering & Colouring of all units and exteriors 15-05-2022 WORK IN PROGRESS NA
79 Fixation of doors and windows 31-03-2021 WORK IN PROGRESS NA
80 Scheduled Date of handing over possession 04-09-2022 NOT YET STARTED NA
81 Development of common areas, parks, gardens etc 01-08-2022 NOT YET STARTED NA
Updated Changes on 11-10-2022
82 Site Development 30-01-2020 completed
83 NA 30-01-2020 completed
84 Ground Floor/Stilt Floor 15-03-2020 COMPLETED
85 1 Floor 30-04-2020 COMPLETED
86 2 Floor 15-06-2020 COMPLETED
87 3 Floor 31-07-2020 COMPLETED
88 4 Floor 15-09-2020 COMPLETED
89 NA 15-09-2020 COMPLETED
90 Ground Floor/Stilt Floor 30-11-2020 COMPLETED
91 1 Floor 31-12-2020 COMPLETED
92 2 Floor 15-02-2021 COMPLETED
93 3 Floor 31-03-2021 COMPLETED
94 4 Floor 15-05-2021 COMPLETED NA
95 Electrical Works 15-05-2022 COMPLETED
96 Concealed Cabling including Plugs & switches 15-11-2021 WORK IN PROGRESS NA
97 Installation & Charging of Transformer 01-05-2022 COMPLETED
98 Connection to Flats/Apartments 10-05-2022 NOT YET STARTED NA
99 PH works 15-05-2022 WORK IN PROGRESS NA
100 Laying of concealed Pipes 15-11-2021 COMPLETED NA
101 PH Fittings 15-03-2022 WORK IN PROGRESS NA
102 Overhead Water Tanks 15-04-2022 WORK IN PROGRESS NA
103 Water Supply Connection to all units 30-04-2022 WORK IN PROGRESS NA
104 STP construction and completion 10-05-2022 COMPLETED
105 Distempering & Colouring of all units and exteriors 15-05-2022 WORK IN PROGRESS NA
106 Fixation of doors and windows 31-03-2021 WORK IN PROGRESS NA
107 Scheduled Date of handing over possession 04-09-2022 NOT YET STARTED NA
108 Development of common areas, parks, gardens etc 01-08-2022 NOT YET STARTED NA
Updated Changes on 13-07-2023
109 Site Development 30-01-2020 completed NA
110 NA 30-01-2020 completed NA
111 Ground Floor/Stilt Floor 15-03-2020 COMPLETED NA
112 1 Floor 30-04-2020 COMPLETED NA
113 2 Floor 15-06-2020 COMPLETED NA
114 3 Floor 31-07-2020 COMPLETED NA
115 4 Floor 15-09-2020 COMPLETED NA
116 NA 15-09-2020 COMPLETED NA
117 Ground Floor/Stilt Floor 30-11-2020 COMPLETED NA
118 1 Floor 31-12-2020 COMPLETED NA
119 2 Floor 15-02-2021 COMPLETED NA
120 3 Floor 31-03-2021 COMPLETED NA
121 4 Floor 15-05-2021 COMPLETED NA
122 Electrical Works 15-05-2022 COMPLETED NA
123 Concealed Cabling including Plugs & switches 15-11-2021 COMPLETED
124 Installation & Charging of Transformer 01-05-2022 COMPLETED NA
125 Connection to Flats/Apartments 10-05-2022 COMPLETED NA
126 PH works 15-05-2022 COMPLETED NA
127 Laying of concealed Pipes 15-11-2021 COMPLETED NA
128 PH Fittings 15-03-2022 COMPLETED NA
129 Overhead Water Tanks 15-04-2022 COMPLETED NA
130 Water Supply Connection to all units 30-04-2022 COMPLETED NA
131 STP construction and completion 10-05-2022 COMPLETED NA
132 Distempering & Colouring of all units and exteriors 15-05-2022 COMPLETED
133 Fixation of doors and windows 31-03-2021 COMPLETED NA
134 Scheduled Date of handing over possession 04-09-2022 NOT YET STARTED NA
135 Development of common areas, parks, gardens etc 01-08-2022 COMPLETED
Updated Changes on 31-10-2023
136 Site Development 30-01-2020 completed
137 NA 30-01-2020 completed
138 Ground Floor/Stilt Floor 15-03-2020 COMPLETED
139 1 Floor 30-04-2020 COMPLETED
140 2 Floor 15-06-2020 COMPLETED NA
141 3 Floor 31-07-2020 COMPLETED NA
142 4 Floor 15-09-2020 COMPLETED NA
143 NA 15-09-2020 COMPLETED NA
144 Ground Floor/Stilt Floor 30-11-2020 COMPLETED NA
145 1 Floor 31-12-2020 COMPLETED NA
146 2 Floor 15-02-2021 COMPLETED NA
147 3 Floor 31-03-2021 COMPLETED NA
148 4 Floor 15-05-2021 COMPLETED NA
149 Electrical Works 15-05-2022 COMPLETED
150 Concealed Cabling including Plugs & switches 15-11-2021 COMPLETED NA
151 Installation & Charging of Transformer 01-05-2022 COMPLETED NA
152 Connection to Flats/Apartments 10-05-2022 COMPLETED NA
153 PH works 15-05-2022 COMPLETED
154 Laying of concealed Pipes 15-11-2021 COMPLETED NA
155 PH Fittings 15-03-2022 COMPLETED NA
156 Overhead Water Tanks 15-04-2022 COMPLETED NA
157 Water Supply Connection to all units 30-04-2022 COMPLETED NA
158 STP construction and completion 10-05-2022 COMPLETED NA
159 Distempering & Colouring of all units and exteriors 15-05-2022 COMPLETED NA
160 Fixation of doors and windows 31-03-2021 COMPLETED NA
161 Scheduled Date of handing over possession 04-09-2022 NOT YET STARTED NA
162 Development of common areas, parks, gardens etc 01-08-2022 COMPLETED NA
Updated Changes on 02-04-2024
163 Site Development 30-01-2020 completed NA
164 NA 30-01-2020 completed NA
165 Ground Floor/Stilt Floor 15-03-2020 COMPLETED NA
166 1 Floor 30-04-2020 COMPLETED NA
167 2 Floor 15-06-2020 COMPLETED NA
168 3 Floor 31-07-2020 COMPLETED NA
169 4 Floor 15-09-2020 COMPLETED NA
170 NA 15-09-2020 COMPLETED NA
171 Ground Floor/Stilt Floor 30-11-2020 COMPLETED NA
172 1 Floor 31-12-2020 COMPLETED NA
173 2 Floor 15-02-2021 COMPLETED NA
174 3 Floor 31-03-2021 COMPLETED NA
175 4 Floor 15-05-2021 COMPLETED NA
176 Electrical Works 15-05-2022 COMPLETED NA
177 Concealed Cabling including Plugs & switches 15-11-2021 COMPLETED NA
178 Installation & Charging of Transformer 01-05-2022 COMPLETED NA
179 Connection to Flats/Apartments 10-05-2022 COMPLETED NA
180 PH works 15-05-2022 COMPLETED NA
181 Laying of concealed Pipes 15-11-2021 COMPLETED NA
182 PH Fittings 15-03-2022 COMPLETED NA
183 Overhead Water Tanks 15-04-2022 COMPLETED NA
184 Water Supply Connection to all units 30-04-2022 COMPLETED NA
185 STP construction and completion 10-05-2022 COMPLETED NA
186 Distempering & Colouring of all units and exteriors 15-05-2022 COMPLETED NA
187 Fixation of doors and windows 31-03-2021 COMPLETED NA
188 Scheduled Date of handing over possession 04-09-2022 NOT YET STARTED NA
189 Development of common areas, parks, gardens etc 01-08-2022 COMPLETED NA
Updated Changes on 30-04-2024
190 Site Development 30-01-2020 completed
191 NA 30-01-2020 completed NA
192 Ground Floor/Stilt Floor 15-03-2020 COMPLETED NA
193 1 Floor 30-04-2020 COMPLETED NA
194 2 Floor 15-06-2020 COMPLETED NA
195 3 Floor 31-07-2020 COMPLETED NA
196 4 Floor 15-09-2020 COMPLETED NA
197 NA 15-09-2020 COMPLETED NA
198 Ground Floor/Stilt Floor 30-11-2020 COMPLETED NA
199 1 Floor 31-12-2020 COMPLETED NA
200 2 Floor 15-02-2021 COMPLETED NA
201 3 Floor 31-03-2021 COMPLETED NA
202 4 Floor 15-05-2021 COMPLETED NA
203 Electrical Works 15-05-2022 COMPLETED NA
204 Concealed Cabling including Plugs & switches 15-11-2021 COMPLETED NA
205 Installation & Charging of Transformer 01-05-2022 COMPLETED NA
206 Connection to Flats/Apartments 10-05-2022 COMPLETED NA
207 PH works 15-05-2022 COMPLETED NA
208 Laying of concealed Pipes 15-11-2021 COMPLETED NA
209 PH Fittings 15-03-2022 COMPLETED NA
210 Overhead Water Tanks 15-04-2022 COMPLETED NA
211 Water Supply Connection to all units 30-04-2022 COMPLETED NA
212 STP construction and completion 10-05-2022 COMPLETED NA
213 Distempering & Colouring of all units and exteriors 15-05-2022 COMPLETED NA
214 Fixation of doors and windows 31-03-2021 COMPLETED NA
215 Scheduled Date of handing over possession 04-09-2022 NOT YET STARTED NA
216 Development of common areas, parks, gardens etc 01-08-2022 COMPLETED NA

Booking Status

Residential Flats/ House
S. No. Flat No./ House No.

Area in square metres

Ownership Status
Carpet Area Balcony Area Exclusive Open Terrace Area
1 101 65 7.4 N/A Promoter
2 102 65 7.4 N/A Land Owner
3 103 67.5 8 N/A Land Owner
4 104 67.5 8 N/A Land Owner
5 105 82.5 8.8 N/A Promoter
6 106 82.5 8.8 N/A Promoter
7 201 65 7.4 N/A Promoter
8 202 65 7.4 N/A Promoter
9 203 67.5 8 N/A Land Owner
10 204 67.5 8 N/A Land Owner
11 205 82.5 8.8 N/A Promoter
12 206 82.5 8.8 N/A Promoter
13 301 65 7.4 N/A Promoter
14 302 65 7.4 N/A Land Owner
15 303 67.5 8 N/A Promoter
16 304 67.5 8 N/A Promoter
17 305 82.5 8.8 N/A Promoter
18 306 82.5 8.8 N/A Promoter
19 401 65 7.4 N/A Promoter
20 402 65 7.4 N/A Land Owner
21 404 67.5 8 N/A Land Owner

Financial Status

SL No. Funds Collected from the Allottees Funds Borrowed from Financial Institutions Funds Employed from Own Sources Expenditure As On Date Status
1 80928567 0 70000000 106090771 30-11-2021 110858
2 87039834 0 70000000 119559943 30-09-2022 819510.93
3 92077063 0 70000000 119559943 30-06-2023 13076.77
4 92184475 0 0 119559943 21-10-2023 1577
5 92184475 0 0 119559943 02-03-2024 As on 31-12-2023
6 92760124 0 0 78352514 31-03-2024 31.3.2024

Updated Conditions of building plan approval

Sl. No. Description of Conditions Schedule date of compliance Present Status
1 storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per regulation-44 of BDA (planning & building standards)regulation,2008 04-09-2022 NOT YET STARTED
2 the space which is meant for parking shall not be changed to any other use and shall not be partitioned/closed in any manner 04-09-2022 not yet started
3 20% of the parking space in group housing/apartment building shall be exclusively earnmarked for ambulance, fire tender,physically handicapped persons and outside visitors with signage as per norms under regulation -35(11)(12)of BDA (Planning & Building Standards)Regulations 2008 04-09-2022 not yet started
4 Plantaion over 20% of the plot area shall be made by the applicant as per provision under regulation -28 of BDA (Planning and Building Standards)Regulation2008 26-09-2022 not yet started
5 If the construction/Development are not as per the approved plan /deviated beyond permissible norms,The performance security shall forfeited and action shall be initiated against the applicant /builder /developer as per the provisions of the ODA act ,1982 rules and regulation made there under 04-09-2022 not yet started
6 The owner /applicant/architect/structural engineers are fully and jointly responsible for any structural failure of the building due to any structural/construction effects,authority will be no way be held responsible for the same in what so ever manner 04-09-2022 not yet started
7 The concerned Architect/Applicant/Developer are fully responsible for any deviations additions & alternations beyond approved plan/defective construction etc.shall be liable for action as per the provisions of the regulation. 04-09-2022 not yet started
8 The applicant shall obtain infrastructural specification and subsquent clearance with regard to development of infrastructure from BMC/BDA before commencement of construction 04-09-2022 not yet started
9 All the stipulated conditions of the NOG given by BMC,BDA shall be adhered to strictly.All the fire fighting installation etc are to be ensured and maintained by the applicant as per 04-09-2022 not yet started
10 No storm water shall be discharged to the public road/public premises and other adjoining plots 04-09-2022 not yet started
11 Adhere to the provisions of BDA (Planning & Building Standards) Regulation strictly and conditions thereto 04-09-2022 not yet started
12 The authority shall in no way be held responsible for any structural failure and damage due to earthquake/cyclone/any other natural disaster 04-09-2022 not yet started
13 The number of dwelling units so approved shall not be changed in any manner 04-09-2022 not yet started
14 the construction workers welfare Cess @ 1% i.e Rs. 5,41,850/-(Rupees Five Lakhs forty one thousand eight hundred fifty only) shall be adjusted from the security deposit before issue of Occupancy Certificate 04-09-2022 not yet started
Updated Changes on 01-12-2021
15 storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per regulation-44 of BDA (planning & building standards)regulation,2008 04-09-2022 NOT YET STARTED
16 the space which is meant for parking shall not be changed to any other use and shall not be partitioned/closed in any manner 04-09-2022 not yet started
17 20% of the parking space in group housing/apartment building shall be exclusively earnmarked for ambulance, fire tender,physically handicapped persons and outside visitors with signage as per norms under regulation -35(11)(12)of BDA (Planning & Building Standards)Regulations 2008 04-09-2022 not yet started
18 Plantaion over 20% of the plot area shall be made by the applicant as per provision under regulation -28 of BDA (Planning and Building Standards)Regulation2008 26-09-2022 YES,IT SHOULD FOLLOWED
19 If the construction/Development are not as per the approved plan /deviated beyond permissible norms,The performance security shall forfeited and action shall be initiated against the applicant /builder /developer as per the provisions of the ODA act ,1982 rules and regulation made there under 04-09-2022 YES,IT SHOULD FOLLOWED
20 The owner /applicant/architect/structural engineers are fully and jointly responsible for any structural failure of the building due to any structural/construction effects,authority will be no way be held responsible for the same in what so ever manner 04-09-2022 YES,IT SHOULD FOLLOWED
21 The concerned Architect/Applicant/Developer are fully responsible for any deviations additions & alternations beyond approved plan/defective construction etc.shall be liable for action as per the provisions of the regulation. 04-09-2022 not yet started
22 The applicant shall obtain infrastructural specification and subsquent clearance with regard to development of infrastructure from BMC/BDA before commencement of construction 04-09-2022 not yet started
23 All the stipulated conditions of the NOG given by BMC,BDA shall be adhered to strictly.All the fire fighting installation etc are to be ensured and maintained by the applicant as per 04-09-2022 not yet started
24 No storm water shall be discharged to the public road/public premises and other adjoining plots 04-09-2022 not yet started
25 Adhere to the provisions of BDA (Planning & Building Standards) Regulation strictly and conditions thereto 04-09-2022 not yet started
26 The authority shall in no way be held responsible for any structural failure and damage due to earthquake/cyclone/any other natural disaster 04-09-2022 not yet started
27 The number of dwelling units so approved shall not be changed in any manner 04-09-2022 not yet started
28 the construction workers welfare Cess @ 1% i.e Rs. 5,41,850/-(Rupees Five Lakhs forty one thousand eight hundred fifty only) shall be adjusted from the security deposit before issue of Occupancy Certificate 04-09-2022 not yet started
Updated Changes on 26-07-2022
29 storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per regulation-44 of BDA (planning & building standards)regulation,2008 04-09-2022 NOT YET STARTED
30 the space which is meant for parking shall not be changed to any other use and shall not be partitioned/closed in any manner 04-09-2022 not yet started
31 20% of the parking space in group housing/apartment building shall be exclusively earnmarked for ambulance, fire tender,physically handicapped persons and outside visitors with signage as per norms under regulation -35(11)(12)of BDA (Planning & Building Standards)Regulations 2008 04-09-2022 not yet started
32 Plantaion over 20% of the plot area shall be made by the applicant as per provision under regulation -28 of BDA (Planning and Building Standards)Regulation2008 26-09-2022 YES,IT SHOULD FOLLOWED
33 If the construction/Development are not as per the approved plan /deviated beyond permissible norms,The performance security shall forfeited and action shall be initiated against the applicant /builder /developer as per the provisions of the ODA act ,1982 rules and regulation made there under 04-09-2022 YES,IT SHOULD FOLLOWED
34 The owner /applicant/architect/structural engineers are fully and jointly responsible for any structural failure of the building due to any structural/construction effects,authority will be no way be held responsible for the same in what so ever manner 04-09-2022 YES,IT SHOULD FOLLOWED
35 The concerned Architect/Applicant/Developer are fully responsible for any deviations additions & alternations beyond approved plan/defective construction etc.shall be liable for action as per the provisions of the regulation. 04-09-2022 not yet started
36 The applicant shall obtain infrastructural specification and subsquent clearance with regard to development of infrastructure from BMC/BDA before commencement of construction 04-09-2022 not yet started
37 All the stipulated conditions of the NOG given by BMC,BDA shall be adhered to strictly.All the fire fighting installation etc are to be ensured and maintained by the applicant as per 04-09-2022 not yet started
38 No storm water shall be discharged to the public road/public premises and other adjoining plots 04-09-2022 not yet started
39 Adhere to the provisions of BDA (Planning & Building Standards) Regulation strictly and conditions thereto 04-09-2022 not yet started
40 The authority shall in no way be held responsible for any structural failure and damage due to earthquake/cyclone/any other natural disaster 04-09-2022 not yet started
41 The number of dwelling units so approved shall not be changed in any manner 04-09-2022 not yet started
42 the construction workers welfare Cess @ 1% i.e Rs. 5,41,850/-(Rupees Five Lakhs forty one thousand eight hundred fifty only) shall be adjusted from the security deposit before issue of Occupancy Certificate 04-09-2022 not yet started
Updated Changes on 11-10-2022
43 storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per regulation-44 of BDA (planning & building standards)regulation,2008 04-09-2022 NOT YET STARTED
44 the space which is meant for parking shall not be changed to any other use and shall not be partitioned/closed in any manner 04-09-2022 not yet started
45 20% of the parking space in group housing/apartment building shall be exclusively earnmarked for ambulance, fire tender,physically handicapped persons and outside visitors with signage as per norms under regulation -35(11)(12)of BDA (Planning & Building Standards)Regulations 2008 04-09-2022 not yet started
46 Plantaion over 20% of the plot area shall be made by the applicant as per provision under regulation -28 of BDA (Planning and Building Standards)Regulation2008 26-09-2022 YES,IT SHOULD FOLLOWED
47 If the construction/Development are not as per the approved plan /deviated beyond permissible norms,The performance security shall forfeited and action shall be initiated against the applicant /builder /developer as per the provisions of the ODA act ,1982 rules and regulation made there under 04-09-2022 YES,IT SHOULD FOLLOWED
48 The owner /applicant/architect/structural engineers are fully and jointly responsible for any structural failure of the building due to any structural/construction effects,authority will be no way be held responsible for the same in what so ever manner 04-09-2022 YES,IT SHOULD FOLLOWED
49 The concerned Architect/Applicant/Developer are fully responsible for any deviations additions & alternations beyond approved plan/defective construction etc.shall be liable for action as per the provisions of the regulation. 04-09-2022 not yet started
50 The applicant shall obtain infrastructural specification and subsquent clearance with regard to development of infrastructure from BMC/BDA before commencement of construction 04-09-2022 not yet started
51 All the stipulated conditions of the NOG given by BMC,BDA shall be adhered to strictly.All the fire fighting installation etc are to be ensured and maintained by the applicant as per 04-09-2022 not yet started
52 No storm water shall be discharged to the public road/public premises and other adjoining plots 04-09-2022 not yet started
53 Adhere to the provisions of BDA (Planning & Building Standards) Regulation strictly and conditions thereto 04-09-2022 not yet started
54 The authority shall in no way be held responsible for any structural failure and damage due to earthquake/cyclone/any other natural disaster 04-09-2022 not yet started
55 The number of dwelling units so approved shall not be changed in any manner 04-09-2022 not yet started
56 the construction workers welfare Cess @ 1% i.e Rs. 5,41,850/-(Rupees Five Lakhs forty one thousand eight hundred fifty only) shall be adjusted from the security deposit before issue of Occupancy Certificate 04-09-2022 not yet started
Updated Changes on 13-07-2023
57 storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per regulation-44 of BDA (planning & building standards)regulation,2008 04-09-2022 YES,IT SHOULD FOLLOWED
58 the space which is meant for parking shall not be changed to any other use and shall not be partitioned/closed in any manner 04-09-2022 YES,IT SHOULD FOLLOWED
59 20% of the parking space in group housing/apartment building shall be exclusively earnmarked for ambulance, fire tender,physically handicapped persons and outside visitors with signage as per norms under regulation -35(11)(12)of BDA (Planning & Building Standards)Regulations 2008 04-09-2022 YES,IT SHOULD FOLLOWED
60 Plantaion over 20% of the plot area shall be made by the applicant as per provision under regulation -28 of BDA (Planning and Building Standards)Regulation2008 26-09-2022 YES,IT SHOULD FOLLOWED
61 If the construction/Development are not as per the approved plan /deviated beyond permissible norms,The performance security shall forfeited and action shall be initiated against the applicant /builder /developer as per the provisions of the ODA act ,1982 rules and regulation made there under 04-09-2022 YES,IT SHOULD FOLLOWED
62 The owner /applicant/architect/structural engineers are fully and jointly responsible for any structural failure of the building due to any structural/construction effects,authority will be no way be held responsible for the same in what so ever manner 04-09-2022 YES,IT SHOULD FOLLOWED
63 The concerned Architect/Applicant/Developer are fully responsible for any deviations additions & alternations beyond approved plan/defective construction etc.shall be liable for action as per the provisions of the regulation. 04-09-2022 YES,IT SHOULD FOLLOWED
64 The applicant shall obtain infrastructural specification and subsquent clearance with regard to development of infrastructure from BMC/BDA before commencement of construction 04-09-2022 YES,IT SHOULD FOLLOWED
65 All the stipulated conditions of the NOG given by BMC,BDA shall be adhered to strictly.All the fire fighting installation etc are to be ensured and maintained by the applicant as per 04-09-2022 YES,IT SHOULD FOLLOWED
66 No storm water shall be discharged to the public road/public premises and other adjoining plots 04-09-2022 YES,IT SHOULD FOLLOWED
67 Adhere to the provisions of BDA (Planning & Building Standards) Regulation strictly and conditions thereto 04-09-2022 YES,IT SHOULD FOLLOWED
68 The authority shall in no way be held responsible for any structural failure and damage due to earthquake/cyclone/any other natural disaster 04-09-2022 YES,IT SHOULD FOLLOWED
69 The number of dwelling units so approved shall not be changed in any manner 04-09-2022 YES,IT SHOULD FOLLOWED
70 the construction workers welfare Cess @ 1% i.e Rs. 5,41,850/-(Rupees Five Lakhs forty one thousand eight hundred fifty only) shall be adjusted from the security deposit before issue of Occupancy Certificate 04-09-2022 YES,IT SHOULD FOLLOWED
Updated Changes on 31-10-2023
71 storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per regulation-44 of BDA (planning & building standards)regulation,2008 04-09-2022 YES,IT SHOULD FOLLOWED
72 the space which is meant for parking shall not be changed to any other use and shall not be partitioned/closed in any manner 04-09-2022 YES,IT SHOULD FOLLOWED
73 20% of the parking space in group housing/apartment building shall be exclusively earnmarked for ambulance, fire tender,physically handicapped persons and outside visitors with signage as per norms under regulation -35(11)(12)of BDA (Planning & Building Standards)Regulations 2008 04-09-2022 YES,IT SHOULD FOLLOWED
74 Plantaion over 20% of the plot area shall be made by the applicant as per provision under regulation -28 of BDA (Planning and Building Standards)Regulation2008 26-09-2022 YES,IT SHOULD FOLLOWED
75 If the construction/Development are not as per the approved plan /deviated beyond permissible norms,The performance security shall forfeited and action shall be initiated against the applicant /builder /developer as per the provisions of the ODA act ,1982 rules and regulation made there under 04-09-2022 YES,IT SHOULD FOLLOWED
76 The owner /applicant/architect/structural engineers are fully and jointly responsible for any structural failure of the building due to any structural/construction effects,authority will be no way be held responsible for the same in what so ever manner 04-09-2022 YES,IT SHOULD FOLLOWED
77 The concerned Architect/Applicant/Developer are fully responsible for any deviations additions & alternations beyond approved plan/defective construction etc.shall be liable for action as per the provisions of the regulation. 04-09-2022 YES,IT SHOULD FOLLOWED
78 The applicant shall obtain infrastructural specification and subsquent clearance with regard to development of infrastructure from BMC/BDA before commencement of construction 04-09-2022 YES,IT SHOULD FOLLOWED
79 All the stipulated conditions of the NOG given by BMC,BDA shall be adhered to strictly.All the fire fighting installation etc are to be ensured and maintained by the applicant as per 04-09-2022 YES,IT SHOULD FOLLOWED
80 No storm water shall be discharged to the public road/public premises and other adjoining plots 04-09-2022 YES,IT SHOULD FOLLOWED
81 Adhere to the provisions of BDA (Planning & Building Standards) Regulation strictly and conditions thereto 04-09-2022 YES,IT SHOULD FOLLOWED
82 The authority shall in no way be held responsible for any structural failure and damage due to earthquake/cyclone/any other natural disaster 04-09-2022 YES,IT SHOULD FOLLOWED
83 The number of dwelling units so approved shall not be changed in any manner 04-09-2022 YES,IT SHOULD FOLLOWED
84 the construction workers welfare Cess @ 1% i.e Rs. 5,41,850/-(Rupees Five Lakhs forty one thousand eight hundred fifty only) shall be adjusted from the security deposit before issue of Occupancy Certificate 04-09-2022 YES,IT SHOULD FOLLOWED
Updated Changes on 02-04-2024
85 storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per regulation-44 of BDA (planning & building standards)regulation,2008 04-09-2022 YES,IT SHOULD FOLLOWED
86 the space which is meant for parking shall not be changed to any other use and shall not be partitioned/closed in any manner 04-09-2022 YES,IT SHOULD FOLLOWED
87 20% of the parking space in group housing/apartment building shall be exclusively earnmarked for ambulance, fire tender,physically handicapped persons and outside visitors with signage as per norms under regulation -35(11)(12)of BDA (Planning & Building Standards)Regulations 2008 04-09-2022 YES,IT SHOULD FOLLOWED
88 Plantaion over 20% of the plot area shall be made by the applicant as per provision under regulation -28 of BDA (Planning and Building Standards)Regulation2008 26-09-2022 YES,IT SHOULD FOLLOWED
89 If the construction/Development are not as per the approved plan /deviated beyond permissible norms,The performance security shall forfeited and action shall be initiated against the applicant /builder /developer as per the provisions of the ODA act ,1982 rules and regulation made there under 04-09-2022 YES,IT SHOULD FOLLOWED
90 The owner /applicant/architect/structural engineers are fully and jointly responsible for any structural failure of the building due to any structural/construction effects,authority will be no way be held responsible for the same in what so ever manner 04-09-2022 YES,IT SHOULD FOLLOWED
91 The concerned Architect/Applicant/Developer are fully responsible for any deviations additions & alternations beyond approved plan/defective construction etc.shall be liable for action as per the provisions of the regulation. 04-09-2022 YES,IT SHOULD FOLLOWED
92 The applicant shall obtain infrastructural specification and subsquent clearance with regard to development of infrastructure from BMC/BDA before commencement of construction 04-09-2022 YES,IT SHOULD FOLLOWED
93 All the stipulated conditions of the NOG given by BMC,BDA shall be adhered to strictly.All the fire fighting installation etc are to be ensured and maintained by the applicant as per 04-09-2022 YES,IT SHOULD FOLLOWED
94 No storm water shall be discharged to the public road/public premises and other adjoining plots 04-09-2022 YES,IT SHOULD FOLLOWED
95 Adhere to the provisions of BDA (Planning & Building Standards) Regulation strictly and conditions thereto 04-09-2022 YES,IT SHOULD FOLLOWED
96 The authority shall in no way be held responsible for any structural failure and damage due to earthquake/cyclone/any other natural disaster 04-09-2022 YES,IT SHOULD FOLLOWED
97 The number of dwelling units so approved shall not be changed in any manner 04-09-2022 YES,IT SHOULD FOLLOWED
98 the construction workers welfare Cess @ 1% i.e Rs. 5,41,850/-(Rupees Five Lakhs forty one thousand eight hundred fifty only) shall be adjusted from the security deposit before issue of Occupancy Certificate 04-09-2022 YES,IT SHOULD FOLLOWED
Updated Changes on 30-04-2024
99 storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per regulation-44 of BDA (planning & building standards)regulation,2008 04-09-2022 YES,IT SHOULD FOLLOWED
100 the space which is meant for parking shall not be changed to any other use and shall not be partitioned/closed in any manner 04-09-2022 YES,IT SHOULD FOLLOWED
101 20% of the parking space in group housing/apartment building shall be exclusively earnmarked for ambulance, fire tender,physically handicapped persons and outside visitors with signage as per norms under regulation -35(11)(12)of BDA (Planning & Building Standards)Regulations 2008 04-09-2022 YES,IT SHOULD FOLLOWED
102 Plantaion over 20% of the plot area shall be made by the applicant as per provision under regulation -28 of BDA (Planning and Building Standards)Regulation2008 26-09-2022 YES,IT SHOULD FOLLOWED
103 If the construction/Development are not as per the approved plan /deviated beyond permissible norms,The performance security shall forfeited and action shall be initiated against the applicant /builder /developer as per the provisions of the ODA act ,1982 rules and regulation made there under 04-09-2022 YES,IT SHOULD FOLLOWED
104 The owner /applicant/architect/structural engineers are fully and jointly responsible for any structural failure of the building due to any structural/construction effects,authority will be no way be held responsible for the same in what so ever manner 04-09-2022 YES,IT SHOULD FOLLOWED
105 The concerned Architect/Applicant/Developer are fully responsible for any deviations additions & alternations beyond approved plan/defective construction etc.shall be liable for action as per the provisions of the regulation. 04-09-2022 YES,IT SHOULD FOLLOWED
106 The applicant shall obtain infrastructural specification and subsquent clearance with regard to development of infrastructure from BMC/BDA before commencement of construction 04-09-2022 YES,IT SHOULD FOLLOWED
107 All the stipulated conditions of the NOG given by BMC,BDA shall be adhered to strictly.All the fire fighting installation etc are to be ensured and maintained by the applicant as per 04-09-2022 YES,IT SHOULD FOLLOWED
108 No storm water shall be discharged to the public road/public premises and other adjoining plots 04-09-2022 YES,IT SHOULD FOLLOWED
109 Adhere to the provisions of BDA (Planning & Building Standards) Regulation strictly and conditions thereto 04-09-2022 YES,IT SHOULD FOLLOWED
110 The authority shall in no way be held responsible for any structural failure and damage due to earthquake/cyclone/any other natural disaster 04-09-2022 YES,IT SHOULD FOLLOWED
111 The number of dwelling units so approved shall not be changed in any manner 04-09-2022 YES,IT SHOULD FOLLOWED
112 the construction workers welfare Cess @ 1% i.e Rs. 5,41,850/-(Rupees Five Lakhs forty one thousand eight hundred fifty only) shall be adjusted from the security deposit before issue of Occupancy Certificate 04-09-2022 YES,IT SHOULD FOLLOWED

Updated Project Documents

Sl. No. Title of the document Upload Document
1 RERA CERTIFICATE
2 BDA APPROVAL LETTER
3 RERA
4 BDA
5 rera
6 bmc
7 Proforma 1
8 Proforma 2
9 Proforma 3
10 Completion Certificate
11 Proforma-III
12 Proforma-I & II
13 Proforma I & II
14 Proforma III
15 Proforma-i & ii
16 Proforma-III
:  KALINGA KESHARI RATH :  
NA :  ALWPR1547G
:PAN Card :  kkrath@evos.co.in
:  B-TECH(MECHANICAL) MBA :  9040051152
:  10 YEARS
:  Yes :  NA
:  RAJASHREE RATH :  
NA :  AWMPR6439C
:PAN Card :  support@evos.co.in
:  B.A :  9040051152
:  10 YEARS
:  Yes :  NA

Particulars of Architect/Construction Engineer/Contractor/Chartered Accountant

Name position Address with mobile number and email address Registration number Key real estate projects Is active Effective date
GOURAV CHOUDHURY Chartered Accountant 19-A,BAPUJI NAGAR,BHUBANESWAR-751009,MOB-9776022240,EMAIL-gourav.choudhurt1988@gmail.com 309583 TAMANDO,BHUBANESWAR
KESHARI NANDAN PRAKALPA PVT LTD Contractor PLOT NO-284/2485,PATRAPADA,BHUBANESWAR-751019,mob-9861930011,email-kesharin579@gmail.com U70101OR2015PTC019206 TAMANDO BHUBANESWAR
LAGNAJIT MOHAPATRA Architect GHATIKIA,BHUBANESWAR,MOB-9861194401,EMAIL-thresholdarchitects2@gmail.com CA/11/51306 TAMANDO BHUBANESWAR
ER.SIDDHARTH DAS Construction Engineer PATRAPADA,BHUBANESWAR,,MOB-7809653552,EMAIL-adwitya.lenka@gmail.com M 1247462 TAMANDO,BHUBANESWAR

Updated Units

House No. Type of Garage/ Parking allotted Serial No., if any Dimension (Length x Width) in Metres Floor area in sq. metres Garage/Parking area cost is included or additional
101 Covered Parking 1 4X3 12 Included
102 Covered Parking 2 4X3 12 Included
103 Covered Parking 3 4X3 12 Included
104 Covered Parking 4 4X3 12 Included
105 Covered Parking 5 4X3 12 Included
106 Covered Parking 6 4X3 12 Included
201 Covered Parking 7 4X3 12 Included
202 Covered Parking 8 4X3 12 Included
203 Covered Parking 9 4X3 12 Included
204 Covered Parking 10 4X3 12 Included
205 Covered Parking 11 4X3 12 Included
206 Covered Parking 12 4X3 12 Included
301 Covered Parking 13 4X3 12 Included
302 Covered Parking 14 4X3 12 Included
303 Covered Parking 15 4X3 12 Included
304 Covered Parking 16 4X3 12 Included
305 Covered Parking 17 4X3 12 Included
306 Covered Parking 18 4X3 12 Included
401 Covered Parking 19 4X3 12 Included
402 Covered Parking 20 4X3 12 Included
404 Covered Parking 21 4X3 12 Included