Generated by pacms.orera.in on date: 2024-06-30
: SAINATH EARTH MOVERS PVT. LTD | : Private Company |
: U14200OR2012PTC015221 | :View |
NA | : PLOT NO-88/974,ROAD-8,JAGANNATH NAGAR,BHUBANESWAR |
: Plot No.- 88/974, Road-8, Jagannath Nagar, Bhubaneswar, Odisha. | : abhayapanda@hotmail.com |
: 236584 | : 9937058888 |
: AARCS6270J | :View |
: 1 YEAR EXPERIENCES IN BUILDING LINE | : NO |
NA |
: ABHAYA KUMAR PANDA |
: ![]() |
: Managing Director | : AHDPP5794N |
:PAN Card | : abhayapanda@hotmail.com |
: BA | : 9937058888 |
: 1 YEAR EXPERIENCES IN BUILDING LINE | |
: Yes | : NA |
: PRITI RANI PANDA |
: ![]() |
: Director | : AGVPP9463H |
:PAN Card | : abhayapanda@hotmail.com |
: BA | : 9937058888 |
: 1 YEAR EXPERIENCES IN BUILDING LINE | |
: Yes | : NA |
1. : PRITI HEIGHTS | : Residential | ||||
: Plot No-4/12038, Khata No-619/4284, Bhubaneswar Sahar Unit No-41,Chandrasekharpur, Bhubaneswar | : Ongoing | ||||
: RP/19/2023/00894 | NA | ||||
: Joint Venture | |||||
: B+S+5 | NA | NA | : B+S+5 | ||
: No |
: | : |
: | : |
: |
: No | : NA |
: No | : NA |
: New | : PRITI MANSION |
: Residential | : (Residential Project, Regularization of Basement of Block-1 and proposed addition to Block-1 (B+S+5) and proposed Block-2 (B+S+5) storied Residential Apartment Building, No. Of Units- 65) |
: Khordha | : Bhubaneswar MC |
: 751024 | : Urban Local Body |
: BHUBANESWAR MUNICIPAL CORPORATION | |
: BLOCK-1 (B+S+5), & BLOCK-2 (B+S+5) | : NA |
: Yes |
Serial No. | Particulars of the Person | Land/Plot Details | Share of the Person | Document Attached |
---|---|---|---|---|
1 | SURYAKANTA MISHRA | 550 | AS PER DEVELOPMENT AGREEMENT TO DISTRUBIT SHARE | Agreement Copy |
2 | MAMATA ROUT | 550/3604 | AS PER DEVELOPMENT AGREEMENT TO DISTRUBIT SHARE | Agreement Copy |
3 | JOGENDRA KUMAR DAS | 550/2323 | AS PER DEVELOPMENT AGREEMENT TO DISTRUBIT SHARE | Agreement Copy |
View | View |
Download site plan | 10-01-2026 |
11-01-2023 |
Sl. No. | Description of Conditions | Schedule date of compliance | Present Status |
---|---|---|---|
1 | The building shall be used exclusively for Residential Apartment use shall not be changed to any other use without prior appr 1 f Propose and | 14-07-2023 | UNDER PROGRESS |
2 | Parking space mea suring 2 180.737 Sqm. as shown in the app d left for parking of vehicles and no part of it shall be used for an/~;~ plan shall be shall not be partitioned/closed in any V er. | 20-10-2023 | UNDER PROGRESS |
3 | The land over which construction is proposed is accessible by an approved means of access of 9.14 mtr. (Nine Point One Four mtr.) in width | 12-11-2023 | UNDER PROGRESS |
4 | The permission granted under these regulat10ns shall remam valid up to three years from the date of issue .However the permission shall have to be revalidated before the expiry of the above period on payment of such fee as may be prescribed under rules and such revalidation shall be valid for one year. | 30-12-2023 | UNDER PROGRESS |
5 | The owner/ applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC from PHED vide Letter No- 14397 dt. 17.09.2022 , & NOC from CGWA vide letter No-CGWA/NOC/INF/ORIG/2022/16561/dt. 29/09/2022, FIRE SAFETY RECOMMENDATION vide letter NoRECOMM1204130052022000818/dt.29.09.2022 | 20-02-2024 | UNDER PROGRESS |
6 | Storm water from the premises of roof top rain water shall be conveyed and discharged to the rain water Harvesting structure in the premises as per Rule-4 7 of ODA (Planning & Building Standards) Rules-2020. | 28-03-2024 | UNDER PROGRESS |
7 | Provisions of green building norms are to be strictly followed as per Rule-51 of ODA (Planning & Building Standards) Rules, 2020. | 20-04-2024 | UNDER PROGRESS |
8 | Plantation as required under Rule 30 of ODA (Planning & Building Standards) Rules, 2020 shall be strictly adhered. | 08-08-2024 | UNDER PROGRESS |
9 | At least 10% of the parking shall be earmarked for visitors. | 11-10-2024 | UNDER PROGRESS |
10 | The Owner/ Applicant/ Architect/ Structural Engineer/ PMO are fully and jointly responsible for any structural failure of building due to any earthquake/ cyclone/any other natural disaster, structural/construction defects. Authority will be no way be held responsible for the same in what so ever manner. | 20-12-2024 | UNDER PROGRESS |
11 | The applicant shall get the EIDP approved towards development of External infrastructure, execute it and obtain clearance from E~neering Wing of BMC before Occupancy. Page 5 of 6 | 25-04-2025 | UNDER PROGRESS |
: Yes | : View |
Point No. | Latitude | Longitude |
---|---|---|
1 | 20°21'09.0''N | 85°49'48.3''E |
2 | 20°21'07.9''N | 85°49'48.5''E |
3 | 20°21'07.6''N | 85°49'48.1''E |
4 | 20°21'07.2''N | 85°49'47.7''E |
5 | 20°21'07.3''N | 85°49'47.6''E |
6 | 20°21'08.0''N | 85°49'47.6''E |
7 | 20°21'08.1''N | 85°49'46.0''E |
8 | 20°21'08.4''N | 85°49'46.2''E |
9 | 20°21'08.9''N | 85°49'46.2''E |
10 | 20°21'09.0''N | 85°49'47.4''E |
Description* | Scheduled date of completion | Current Status | Site Images |
---|---|---|---|
Site Development | 04-05-2023 | WORK NOT YET START | |
Roof Casting | NA | NA | NA |
Ground Floor/Stilt Floor | 06-07-2023 | WORK NOT YET START | NA |
1 Floor | 21-09-2023 | WORK NOT YET START | NA |
2 Floor | 22-11-2023 | WORK NOT YET START | NA |
3 Floor | 30-12-2023 | WORK NOT YET START | NA |
4 Floor | 12-01-2024 | WORK NOT YET START | NA |
5 Floor | 16-03-2024 | WORK NOT YET START | NA |
Brick Work & Plastering | NA | NA | NA |
Ground Floor/Stilt Floor | 17-05-2024 | WORK NOT YET START | NA |
1 Floor | 12-06-2024 | WORK NOT YET START | NA |
2 Floor | 16-08-2024 | WORK NOT YET START | NA |
3 Floor | 22-10-2024 | WORK NOT YET START | NA |
4 Floor | 26-12-2024 | WORK NOT YET START | NA |
5 Floor | 06-01-2025 | WORK NOT YET START | NA |
Electrical Works | 02-03-2025 | WORK NOT YET START | NA |
Concealed Cabling including Plugs & switches | 30-04-2025 | WORK NOT YET START | NA |
Installation & Charging of Transformer | 21-05-2025 | WORK NOT YET START | NA |
Connection to Flats/Apartments | 30-06-2025 | WORK NOT YET START | NA |
PH works | 12-07-2025 | WORK NOT YET START | NA |
Laying of concealed Pipes | 10-08-2025 | WORK NOT YET START | NA |
PH Fittings | 08-09-2025 | WORK NOT YET START | NA |
Overhead Water Tanks | 12-10-2025 | WORK NOT YET START | NA |
Water Supply Connection to all units | 02-11-2025 | WORK NOT YET START | NA |
STP construction and completion | 31-12-2025 | WORK NOT YET START | NA |
Distempering & Colouring of all units and exteriors | 20-01-2026 | WORK NOT YET START | NA |
Fixation of doors and windows | 26-02-2026 | WORK NOT YET START | NA |
Scheduled Date of handing over possession | 08-03-2026 | WORK NOT YET START | NA |
Development of common areas, parks, gardens etc | 15-04-2026 | WORK NOT YET START | NA |
Site Development | 04-05-2023 | WORK NOT YET START | NA |
NA | NA | NA | NA |
Ground Floor/Stilt Floor | 06-07-2023 | WORK NOT YET START | NA |
1 Floor | 21-09-2023 | WORK NOT YET START | NA |
2 Floor | 22-11-2023 | WORK NOT YET START | NA |
3 Floor | 30-12-2023 | WORK NOT YET START | NA |
4 Floor | 12-01-2024 | WORK NOT YET START | NA |
5 Floor | 16-03-2024 | WORK NOT YET START | NA |
NA | NA | NA | NA |
Ground Floor/Stilt Floor | 17-05-2024 | WORK NOT YET START | NA |
1 Floor | 12-06-2024 | WORK NOT YET START | NA |
2 Floor | 16-08-2024 | WORK NOT YET START | NA |
3 Floor | 22-10-2024 | WORK NOT YET START | NA |
4 Floor | 26-12-2024 | WORK NOT YET START | NA |
5 Floor | 06-01-2025 | WORK NOT YET START | NA |
Electrical Works | 02-03-2025 | WORK NOT YET START | NA |
Concealed Cabling including Plugs & switches | 30-04-2025 | WORK NOT YET START | NA |
Installation & Charging of Transformer | 21-05-2025 | WORK NOT YET START | NA |
Connection to Flats/Apartments | 30-06-2025 | WORK NOT YET START | NA |
PH works | 12-07-2025 | WORK NOT YET START | NA |
Laying of concealed Pipes | 10-08-2025 | WORK NOT YET START | NA |
PH Fittings | 08-09-2025 | WORK NOT YET START | NA |
Overhead Water Tanks | 12-10-2025 | WORK NOT YET START | NA |
Water Supply Connection to all units | 02-11-2025 | WORK NOT YET START | NA |
STP construction and completion | 31-12-2025 | WORK NOT YET START | NA |
Distempering & Colouring of all units and exteriors | 20-01-2026 | WORK NOT YET START | NA |
Fixation of doors and windows | 26-02-2026 | WORK NOT YET START | NA |
Scheduled Date of handing over possession | 08-03-2026 | WORK NOT YET START | NA |
Development of common areas, parks, gardens etc | 15-04-2026 | WORK NOT YET START | NA |
: Residential | |
: 65
|
|
Residential Flats/ House | |||||
---|---|---|---|---|---|
S. No. | Flat No./ House No. | ||||
Area in square metres |
Ownership | ||||
Carpet Area | Balcony Area | Exclusive Open Terrace Area | |||
1 | 101 (Block-1) | 69.28 | 8.595 | 00 | Promoter |
2 | 102 (Block-1) | 71.99 | 2.48 | 00 | Promoter |
3 | 103 (Block-1) | 54.87 | 3.66 | 00 | Land Owner |
4 | 104 (Block-1) | 59.28 | 3.66 | 00 | Promoter |
5 | 105 (Block-1) | 51.79 | 2.33 | 00 | Land Owner |
6 | 201 (Block-1) | 69.28 | 8.595 | 00 | Promoter |
7 | 202 (Block-1) | 71.99 | 2.48 | 00 | Land Owner |
8 | 203 (Block-1) | 54.87 | 3.66 | 00 | Promoter |
9 | 204 (Block-1) | 59.28 | 3.66 | 00 | Promoter |
10 | 205 (Block-1) | 51.79 | 2.33 | 00 | Promoter |
11 | 301(Block-1) | 69.28 | 8.595 | 00 | Promoter |
12 | 302 (Block-1) | 71.99 | 2.48 | 00 | Promoter |
13 | 303 (Block-1) | 54.87 | 3.66 | 00 | Promoter |
14 | 304 (Block-1) | 59.28 | 3.66 | 00 | Promoter |
15 | 305 (Block-1) | 51.79 | 2.33 | 00 | Promoter |
16 | 401 (Block-1) | 69.28 | 8.595 | 00 | Promoter |
17 | 402 (Block-1) | 71.99 | 2.48 | 00 | Promoter |
18 | 403 (Block-1) | 54.87 | 3.66 | 00 | Promoter |
19 | 404 (Block-1) | 59.28 | 3.66 | 00 | Promoter |
20 | 405 (Block-1) | 51.79 | 2.33 | 00 | Land Owner |
21 | 501 (Block-1) | 69.28 | 8.595 | 00 | Promoter |
22 | 502 (Block-1) | 71.99 | 2.48 | 00 | Promoter |
23 | 503 (Block-1) | 54.87 | 3.66 | 00 | Promoter |
24 | 504 (Block-1) | 59.28 | 3.66 | 00 | Land Owner |
25 | 505 (Block-1) | 51.79 | 2.33 | 00 | Promoter |
26 | 101 (Block-2) | 79.19 | 8.595 | 00 | Promoter |
27 | 102 (Block-2) | 77.47 | 2.48 | 00 | Promoter |
28 | 103 (Block-2) | 77.65 | 3.66 | 00 | Promoter |
29 | 104 (Block-2) | 72.6 | 3.66 | 00 | Promoter |
30 | 105 (Block-2) | 77.02 | 2.33 | 00 | Promoter |
31 | 106 (Block-2) | 73.93 | 8.595 | 00 | Promoter |
32 | 107 (Block-2) | 66.8 | 2.48 | 00 | Promoter |
33 | 108 (Block-2) | 73.34 | 3.66 | 00 | Promoter |
34 | 201 (Block-2) | 79.19 | 3.66 | 00 | Land Owner |
35 | 202 (Block-2) | 77.47 | 2.33 | 00 | Land Owner |
36 | 203 (Block-2) | 77.65 | 8.595 | 00 | Promoter |
37 | 204 (Block-2) | 72.6 | 2.48 | 00 | Promoter |
38 | 205 (Block-2) | 77.02 | 3.66 | 00 | Promoter |
39 | 206 (Block-2) | 73.93 | 3.66 | 00 | Promoter |
40 | 207 (Block-2) | 66.8 | 2.33 | 00 | Promoter |
41 | 208 (Block-2) | 73.34 | 8.595 | 00 | Promoter |
42 | 301 (Block-2) | 79.19 | 2.48 | 00 | Promoter |
43 | 302 (Block-2) | 77.47 | 3.66 | 00 | Promoter |
44 | 303 (Block-2) | 77.65 | 3.66 | 00 | Promoter |
45 | 304 (Block-2) | 72.6 | 2.33 | 00 | Promoter |
46 | 305 (Block-2) | 77.02 | 8.595 | 00 | Promoter |
47 | 306 (Block-2) | 73.93 | 2.48 | 00 | Promoter |
48 | 307 (Block-2) | 66.8 | 3.66 | 00 | Land Owner |
49 | 308 (Block-2) | 73.34 | 3.66 | 00 | Land Owner |
50 | 401 (Block-2) | 79.19 | 2.33 | 00 | Promoter |
51 | 402 (Block-2) | 77.47 | 8.595 | 00 | Land Owner |
52 | 403 (Block-2) | 77.65 | 2.48 | 00 | Promoter |
53 | 404 (Block-2) | 72.6 | 3.66 | 00 | Promoter |
54 | 405 (Block-2) | 77.02 | 3.66 | 00 | Promoter |
55 | 406 (Block-2) | 73.93 | 2.33 | 00 | Promoter |
56 | 407 (Block-2) | 66.8 | 8.595 | 00 | Promoter |
57 | 408 (Block-2) | 73.34 | 2.48 | 00 | Promoter |
58 | 501 (Block-2) | 79.19 | 3.66 | 00 | Promoter |
59 | 502 (Block-2) | 77.47 | 8.595 | 00 | Promoter |
60 | 503 (Block-2) | 77.65 | 2.48 | 00 | Promoter |
61 | 504 (Block-2) | 72.6 | 3.66 | 00 | Promoter |
62 | 505 (Block-2) | 77.02 | 3.66 | 00 | Promoter |
63 | 506 (Block-2) | 73.93 | 2.33 | 00 | Land Owner |
64 | 507 (Block-2) | 66.8 | 8.595 | 00 | Land Owner |
65 | 508 (Block-2) | 73.34 | 2.48 | 00 | Land Owner |
Types of garages and parking | ||||||
---|---|---|---|---|---|---|
House No. | Type of Garage/ Parking allotted | Serial No., if any | Dimension (Length x Width) in Metres | Floor area in sq. metres | Garage/Parking area cost is included or additional | |
101 (Block-1) | Covered Parking | 101 | 4.5 X2.4 | 10.8 | Included | 102 (Block-1) | Covered Parking | 102 | 4.5 X2.4 | 10.8 | Included | 103 (Block-1) | Covered Parking | 103 | 4.5 X2.4 | 10.8 | Included | 104 (Block-1) | Covered Parking | 104 | 4.5 X2.4 | 10.8 | Included | 105 (Block-1) | Covered Parking | 105 | 4.5 X2.4 | 10.8 | Included | 201 (Block-1) | Covered Parking | 201 | 4.5 X2.4 | 10.8 | Included | 202 (Block-1) | Covered Parking | 202 | 4.5 X2.4 | 10.8 | Included | 203 (Block-1) | Covered Parking | 203 | 4.5 X2.4 | 10.8 | Included | 204 (Block-1) | Covered Parking | 204 | 4.5 X2.4 | 10.8 | Included | 205 (Block-1) | Covered Parking | 205 | 4.5 X2.4 | 10.8 | Included | 301 (Block-1) | Covered Parking | 301 | 4.5 X2.4 | 10.8 | Included | 302 (Block-1) | Covered Parking | 302 | 4.5 X2.4 | 10.8 | Included | 303 (Block-1) | Covered Parking | 303 | 4.5 X2.4 | 10.8 | Included | 304 (Block-1) | Covered Parking | 304 | 4.5 X2.4 | 10.8 | Included | 305 (Block-1) | Covered Parking | 305 | 4.5 X2.4 | 10.8 | Included | 401 (Block-1) | Covered Parking | 401 | 4.5 X2.4 | 10.8 | Included | 402 (Block-1) | Covered Parking | 402 | 4.5 X2.4 | 10.8 | Included | 403 (Block-1) | Covered Parking | 403 | 4.5 X2.4 | 10.8 | Included | 404 (Block-1) | Covered Parking | 404 | 4.5 X2.4 | 10.8 | Included | 405 (Block-1) | Covered Parking | 405 | 4.5 X2.4 | 10.8 | Included | 501 (Block-1) | Covered Parking | 501 | 4.5 X2.4 | 10.8 | Included | 502 (Block-1) | Covered Parking | 502 | 4.5 X2.4 | 10.8 | Included | 503 (Block-1) | Covered Parking | 503 | 4.5 X2.4 | 10.8 | Included | 504(Block-1) | Covered Parking | 504 | 4.5 X2.4 | 10.8 | Included | 505 (Block-1) | Covered Parking | 505 | 4.5 X2.4 | 10.8 | Included | 101 (Block-2) | Covered Parking | 101 | 4.5 X2.4 | 10.8 | Included | 102 (Block-2) | Covered Parking | 102 | 4.5 X2.4 | 10.8 | Included | 103 (Block-2) | Covered Parking | 103 | 4.5 X2.4 | 10.8 | Included | 104 (Block-2) | Covered Parking | 104 | 4.5 X2.4 | 10.8 | Included | 105 (Block-2) | Covered Parking | 105 | 4.5 X2.4 | 10.8 | Included | 106 (Block-2) | Covered Parking | 106 | 4.5 X2.4 | 10.8 | Included | 107 (Block-2) | Covered Parking | 107 | 4.5 X2.4 | 10.8 | Included | 108 (Block-2) | Covered Parking | 108 | 4.5 X2.4 | 10.8 | Included | 201 (Block-2) | Covered Parking | 201 | 4.5 X2.4 | 10.8 | Included | 202 (Block-2) | Covered Parking | 202 | 4.5 X2.4 | 10.8 | Included | 203 (Block-2) | Covered Parking | 203 | 4.5 X2.4 | 10.8 | Included | 204 (Block-2) | Covered Parking | 204 | 4.5 X2.4 | 10.8 | Included | 205 (Block-2) | Covered Parking | 205 | 4.5 X2.4 | 10.8 | Included | 206 (Block-2) | Covered Parking | 206 | 4.5 X2.4 | 10.8 | Included | 207 (Block-2) | Covered Parking | 207 | 4.5 X2.4 | 10.8 | Included | 208 (Block-2) | Covered Parking | 208 | 4.5 X2.4 | 10.8 | Included | 301 (Block-2) | Covered Parking | 301 | 4.5 X2.4 | 10.8 | Included | 302 (Block-2) | Covered Parking | 302 | 4.5 X2.4 | 10.8 | Included | 303 (Block-2) | Covered Parking | 303 | 4.5 X2.4 | 10.8 | Included | 304 (Block-2) | Covered Parking | 304 | 4.5 X2.4 | 10.8 | Included | 305 (Block-2) | Covered Parking | 305 | 4.5 X2.4 | 10.8 | Included | 306 (Block-2) | Covered Parking | 306 | 4.5 X2.4 | 10.8 | Included | 307 (Block-2) | Covered Parking | 307 | 4.5 X2.4 | 10.8 | Included | 308 (Block-2) | Covered Parking | 308 | 4.5 X2.4 | 10.8 | Included | 401 (Block-2) | Covered Parking | 401 | 4.5 X2.4 | 10.8 | Included | 402 (Block-2) | Covered Parking | 402 | 4.5 X2.4 | 10.8 | Included | 403 (Block-2) | Covered Parking | 403 | 4.5 X2.4 | 10.8 | Included | 404 (Block-2) | Covered Parking | 404 | 4.5 X2.4 | 10.8 | Included | 405 (Block-2) | Covered Parking | 405 | 4.5 X2.4 | 10.8 | Included | 406 (Block-2) | Covered Parking | 406 | 4.5 X2.4 | 10.8 | Included | 407 (Block-2) | Covered Parking | 407 | 4.5 X2.4 | 10.8 | Included | 408 (Block-2) | Covered Parking | 408 | 4.5 X2.4 | 10.8 | Included | 501 (Block-2) | Covered Parking | 501 | 4.5 X2.4 | 10.8 | Included | 502 (Block-2) | Covered Parking | 502 | 4.5 X2.4 | 10.8 | Included | 503 (Block-2) | Covered Parking | 503 | 4.5 X2.4 | 10.8 | Included | 504 (Block-2) | Covered Parking | 504 | 4.5 X2.4 | 10.8 | Included | 505 (Block-2) | Covered Parking | 505 | 4.5 X2.4 | 10.8 | Included | 506 (Block-2) | Covered Parking | 506 | 4.5 X2.4 | 10.8 | Included | 507 (Block-2) | Covered Parking | 507 | 4.5 X2.4 | 10.8 | Included | 508 (Block-2) | Covered Parking | 508 | 4.5 X2.4 | 10.8 | Included |
Particulars of Facilities | Status of the facility | Brief description of facility |
---|---|---|
Drinking Water Facility | Ground Water | Copy of Consent Letter |
Fire Fighting Facility | Yes | UNDER TAKING |
Emergency Evacuation Services | Yes | STAIR CASE |
Use of Renewable Energy | Yes | DG BACKUP |
Lift Facility | Yes | 4 NOS OF LIFT KONE AND OTIS BRAND, 6 PERSON CAPACITY, WITH ARD FACILITY. |
Market Complex | No | |
Community Hall | Yes | 66.13 Community Hall |
Gymnasium | No | |
Swimming Pool | No | |
Play Ground | No | |
Park/Garden | No | |
Plantation Area | Yes | 208 SQMT PLANTATION AREA |
Others(Please Specify) | Yes | 24 HOUR SECURITY |
Internal Road | Yes | 509.724 SQMT INTERNAL ROAD PATH WAY/DRIVE WAY |
External Road | Yes | 9.14 MT WIDTH GOVT. ROAD |
Elecricity Supply | Yes | Copy of Consent Letter |
Other Amenities | Yes | CC CAMERA ALL BLOCKS |
Generated by pacms.orera.in on date: 2024-06-30