Promoter Details
Promoter Name :
Anshuman Patnaik
Project Name :
Archid Sailabala
Project Location :
(Residential Project, Revised S+5 storey Residential Building, No. of Units- 40)

Form- I

A. Promoter's Details

:  M/s. Archid Builders Pvt. Ltd :  Private Company
:   U45201OR2009PTC011159 :View
NA :   4th Floor, Archid Central, Plot No.315, District Centre, Chandrasekharpur, Bhubaneswar-751021, Dist. Khordha, Odisha
:  4th Floor, Archid Central, Plot No.- 315, District Centre, Chandrasekharpur, Bhubaneswar, Dist- Khordha, Odisha- 751021. :  archidhomes@gmail.com
:  2747940 :  9437076631
:  AAHCA9933C :View
:  WE HAVE AN EXPERIENCE OF 14 YEARS IN REAL ESTATE & HAVE COMPLETED APPROX 250000 SQFT OF CONSTRUCTION :   NO EXPERIENCE OUTSIDE STATE
:   www.archidhomes.in

B. Details of Board of Directors / Partners / MC Members

:  Anshuman Patnaik :  
:  Director :  AWLPP2012N
:PAN Card :  archidhomes@gmail.com
:  MBA :  9437076631
:  Has an experience of 14 years in the real-estate sector
:  Yes :  NA
:  SIMANTIKA MOHANTY :  
:  Director :  AMDPM3225G
:PAN Card :  archidhomes@gmail.com
:  B.A :  7537000001
:  Has an experience of 14 years in the real-estate sector
:  Yes :  NA
:  BANDAN MOHANTY :  
:  Managing Director :  AFMPM7898D
:PAN Card :  archidhomes@gmail.com
:  MBA :  9437094412
:  Has an experience of 14 years in the real-estate sector
:  Yes :  NA

Annexure-1

Details of last projects already implemented (Ongoing or Complete)

Annexure-2

Details of the project to be registered

:   New :  Archid Sailabala
:  Residential :  (Residential Project, Revised S+5 storey Residential Building, No. of Units- 40)
:  Khordha :  Bhubaneswar
:  751025 :  Urban Local Body
:   Bhubaneswar Municipal Corporation
:  Revised S+5 Storied Residential Building :  NA

Land Details of the Project


:  2405/4170 :  640
:  Sunderpada :  1801.48
:  Yes
No :  View
:  View
:  Other Person
:  Binoy Kumar Nanda & Others :   It is their Ancestral Property. After the death of their father (Late Lingaraj Nanda) the land has been transferred to the name of the legal heirs.
: No
: Yes
:  11081711964 :  12-12-2017
:  Bhubaneswar :  Attached

Development Agreement

: Yes
Serial No. Particulars of the Person Land/Plot Details Share of the Person Document Attached
1 Sri Binoy Kumar Nanda & Others Plot No:2405, Khata No:640, Mouza: Bhubaneswar Sahar Unit No-24, Sundarpada 40%   Agreement Copy

Building Plan

  View   View
  Download site plan 28-04-2025

Conditions of building plan approval

Sl. No. Description of Conditions Schedule date of compliance Present Status
1 The building shall be used exclusively for residential purpose and the use shall not be changed to any other use without prior of this Authority. 30-11-2021 work in progress
2 The development shall be undertaken strictly according to plans enclosed with necessary permission endorsement. 16-03-2022 work in progress
3 Parking space measuring 982.11 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 15-06-2022 work in progress
4 The land over which construction is proposed is accessible by an approved means of access of 9.14 Mt (Nine point one four) in width. 17-11-2022 work in progress
5 The land in question must be in lawful ownership and peaceful possession of the applicant. 30-12-2022 work in progress
6 The permission granted under these regulations shall remain valid up to three years from the date of issue. However the permission shall have to be revalidated before the expiry of the above period on payment of such fee as may be prescribed under rules and such revalidation shall be valid for one year. 03-05-2023 work in progress
7 In Case of any dispute arising out of land record or in respect of right,title,intrest after this permission is granted, the permission so granted shall be treated as automatically cancelled during the period of dispute. 10-11-2023 work in progress
8 Neither granting of the permit nor the approval of the drawing and specifications, nor inspections made by the Authority during erection of the building shall in any way relieve the owner of such building from full responsibility for carrying out the work in accordance with the requirements of NBC 2016 and these regulations. 05-10-2023 work in progress
9 Wherever tests of any material are made to ensure conformity of the requirements of the regulations in force, records of the test data shall be kept available for inspection during the construction of building and for such period thereafter as required by the Authority. 23-03-2023 work in progress
10 If the Authority finds at any stage that the construction is not being carried in accordance to the sanctioned plan or is in violation of any of the provisions of these regulations, it shall notify the owner and no further construction shall be allowed until necessary corrections in the plan are made and the corrected plan is approved. 07-07-2023 work in progress

Layout Plan

: Yes :  View

Location Map with geo-coordinates of bend points

Point No. Latitude Longitude
1 85°49'19.0"E 20°13'46.1"N
2 85°49'19.1"E 20°13'47.1"N
3 85°49'20.7"E 20°13'47.6"N
4 85°49'20.9"E 20°13'46.8"N
5 85°49'21.0"E 20°13'46.1"N
6 85°49'19.6"E 20°13'45.8"N
7 85°49'19.4"°E 20°13'46.3"°N
View

Milestone of Project Construction

Description* Scheduled date of completion Current Status Site Images
Site Development 11-01-2021 Tie-Beam work in Progress
Roof Casting NA NA NA
Ground Floor/Stilt Floor 06-05-2021 Work in Progress
1 Floor 10-07-2021 Work in Progress
2 Floor 05-09-2021 Work in Progress
3 Floor 10-12-2021 Work in Progress
4 Floor 25-02-2022 Work in Progress
5 Floor 31-08-2022 Work in Progress
Brick Work & Plastering NA NA NA
Ground Floor/Stilt Floor 16-06-2021 Not started
1 Floor 25-10-2021 Work in Progress
2 Floor 31-01-2022 Not started NA
3 Floor 14-04-2022 Not started NA
4 Floor 22-08-2022 Not started NA
5 Floor 26-05-2022 Not started NA
Electrical Works 30-04-2023 Not started NA
Concealed Cabling including Plugs & switches 31-12-2023 Not started NA
Installation & Charging of Transformer 31-03-2024 Not started NA
Connection to Flats/Apartments 30-04-2025 Not started NA
PH works 31-12-2024 Not started NA
Laying of concealed Pipes 31-01-2025 Not started NA
PH Fittings 31-08-2025 Not started NA
Overhead Water Tanks 31-03-2023 Not started NA
Water Supply Connection to all units 31-08-2025 Not started NA
STP construction and completion 30-09-2025 Not started NA
Distempering & Colouring of all units and exteriors 30-04-2025 Not started NA
Fixation of doors and windows 31-05-2025 Not started NA
Scheduled Date of handing over possession 31-12-2025 Not handed over NA
Development of common areas, parks, gardens etc 30-06-2025 Not started NA
Site Development 11-01-2021 Completed NA
NA NA NA NA
Ground Floor/Stilt Floor 06-05-2021 Completed NA
1 Floor 10-07-2021 Completed NA
2 Floor 05-09-2021 Completed NA
3 Floor 10-12-2021 Completed NA
4 Floor 25-02-2022 Completed NA
5 Floor 31-08-2022 Completed
NA NA NA NA
Ground Floor/Stilt Floor 16-06-2021 Completed NA
1 Floor 25-10-2021 Completed
2 Floor 31-01-2022 Completed
3 Floor 14-04-2022 Completed
4 Floor 22-08-2022 Completed
5 Floor 26-05-2022 Completed
Electrical Works 31-12-2023 Under Progress NA
Concealed Cabling including Plugs & switches 31-12-2023 Not started NA
Installation & Charging of Transformer 31-03-2024 Not started NA
Connection to Flats/Apartments 30-04-2025 Not started NA
PH works 31-12-2024 under progress NA
Laying of concealed Pipes 31-01-2024 Not started NA
PH Fittings 29-02-2024 Not started NA
Overhead Water Tanks 31-12-2023 Not started NA
Water Supply Connection to all units 01-02-2024 Not started NA
STP construction and completion 30-09-2025 Not started NA
Distempering & Colouring of all units and exteriors 31-01-2024 under progress
Fixation of doors and windows 31-10-2023 Not started NA
Scheduled Date of handing over possession 31-12-2025 Not handed over NA
Development of common areas, parks, gardens etc 30-06-2025 Not started NA
Site Development 11-01-2021 Completed NA
NA 31-01-2024 Under Progress NA
Ground Floor/Stilt Floor 06-05-2021 Completed NA
1 Floor 10-07-2021 Completed NA
2 Floor 05-09-2021 Completed NA
3 Floor 10-12-2021 Completed NA
4 Floor 25-02-2022 Completed NA
5 Floor 31-08-2022 Completed NA
NA 31-01-2024 Under Progress NA
Ground Floor/Stilt Floor 16-06-2021 Completed NA
1 Floor 25-10-2021 Completed NA
2 Floor 31-01-2022 Completed NA
3 Floor 14-04-2022 Completed NA
4 Floor 22-08-2022 Completed NA
5 Floor 26-05-2022 Completed NA
Electrical Works 31-12-2023 Under Progress NA
Concealed Cabling including Plugs & switches 31-12-2023 Under Progress
Installation & Charging of Transformer 31-03-2024 Not started NA
Connection to Flats/Apartments 30-04-2025 Not started NA
PH works 31-12-2024 under progress NA
Laying of concealed Pipes 31-01-2024 Under Progress
PH Fittings 29-02-2024 Not started NA
Overhead Water Tanks 31-12-2023 Not started NA
Water Supply Connection to all units 01-02-2024 Not started NA
STP construction and completion 30-09-2025 Not started NA
Distempering & Colouring of all units and exteriors 31-01-2024 under progress NA
Fixation of doors and windows 31-12-2023 Under Progress
Scheduled Date of handing over possession 31-12-2025 Not handed over NA
Development of common areas, parks, gardens etc 30-06-2025 Not started NA
Site Development 11-01-2021 Completed NA
NA 31-01-2024 Under Progress NA
Ground Floor/Stilt Floor 06-05-2021 Completed NA
1 Floor 10-07-2021 Completed
2 Floor 05-09-2021 Completed
3 Floor 10-12-2021 Completed
4 Floor 25-02-2022 Completed
5 Floor 31-08-2022 Completed
NA 31-01-2024 Under Progress NA
Ground Floor/Stilt Floor 16-06-2021 Completed NA
1 Floor 25-10-2021 Completed
2 Floor 31-01-2022 Completed
3 Floor 14-04-2022 Completed
4 Floor 22-08-2022 Completed
5 Floor 26-05-2022 Completed
Electrical Works 31-12-2023 Under Progress NA
Concealed Cabling including Plugs & switches 31-12-2023 Under Progress NA
Installation & Charging of Transformer 31-03-2024 Under Progress NA
Connection to Flats/Apartments 30-04-2025 Not Started NA
PH works 31-12-2024 under progress NA
Laying of concealed Pipes 31-01-2024 Under Progress NA
PH Fittings 29-02-2024 Under Progress NA
Overhead Water Tanks 31-12-2023 Under Progress NA
Water Supply Connection to all units 01-02-2024 Under Progress NA
STP construction and completion 01-06-2024 Work Under Progress NA
Distempering & Colouring of all units and exteriors 01-04-2024 Work Under Progress NA
Fixation of doors and windows 01-04-2024 Work Under Progress NA
Scheduled Date of handing over possession 31-12-2025 Not started NA
Development of common areas, parks, gardens etc 30-06-2025 Not started NA
Site Development 11-01-2021 Completed NA
NA 31-01-2024 Under Progress NA
Ground Floor/Stilt Floor 06-05-2021 Completed NA
1 Floor 10-07-2021 Completed NA
2 Floor 05-09-2021 Completed NA
3 Floor 10-12-2021 Completed NA
4 Floor 25-02-2022 Completed NA
5 Floor 31-08-2022 Completed NA
NA 31-01-2024 Under Progress NA
Ground Floor/Stilt Floor 16-06-2021 Completed NA
1 Floor 25-10-2021 Completed NA
2 Floor 31-01-2022 Completed NA
3 Floor 14-04-2022 Completed NA
4 Floor 22-08-2022 Completed NA
5 Floor 26-05-2022 Completed NA
Electrical Works 31-03-2024 90% WORK COMPLETE NA
Concealed Cabling including Plugs & switches 31-03-2024 Under Progress NA
Installation & Charging of Transformer 01-07-2024 Under Progress NA
Connection to Flats/Apartments 30-04-2025 Not Started NA
PH works 31-12-2024 COMPLETE NA
Laying of concealed Pipes 31-01-2024 COMPLETE NA
PH Fittings 29-02-2024 COMPLETE NA
Overhead Water Tanks 01-02-2024 COMPLETE
Water Supply Connection to all units 01-06-2024 Under Progress NA
STP construction and completion 01-06-2024 80% WORK COMPLETE NA
Distempering & Colouring of all units and exteriors 01-04-2024 COMPLETE
Fixation of doors and windows 01-04-2024 COMPLETE
Scheduled Date of handing over possession 31-12-2025 Not started NA
Development of common areas, parks, gardens etc 30-06-2025 Not started NA

Category and no. of units to be developed

:  Residential
:  
:  40
:  
:  
:  
Residential Flats/ House
S. No. Flat No./ House No.

Area in square metres

Ownership
Carpet Area Balcony Area Exclusive Open Terrace Area
1 101 62.79 8.30 NA Land Owner
2 102 62.77 8.32 NA Land Owner
3 103 62.70 8.39 NA Promoter
4 104 62.47 8.62 NA Promoter
5 105 79.37 9.38 NA Promoter
6 106 79.57 9.19 NA Land Owner
7 107 79.27 9.48 NA Promoter
8 108 80.49 8.26 NA Promoter
9 201 62.79 8.30 NA Promoter
10 202 62.77 8.32 NA Promoter
11 203 62.70 8.39 NA Land Owner
12 204 62.47 8.62 NA Land Owner
13 205 79.37 9.38 NA Promoter
14 206 79.57 9.19 NA Promoter
15 207 79.27 9.48 NA Land Owner
16 208 80.49 8.26 NA Promoter
17 301 62.79 8.30 NA Promoter
18 302 62.77 8.32 NA Promoter
19 303 62.70 8.39 NA Land Owner
20 304 62.47 8.62 NA Promoter
21 305 79.37 9.38 NA Land Owner
22 306 79.57 9.19 NA Land Owner
23 307 79.27 9.48 NA Promoter
24 308 80.49 8.26 NA Promoter
25 401 62.79 8.30 NA Promoter
26 402 62.77 8.32 NA Land Owner
27 403 62.70 8.39 NA Promoter
28 404 62.47 8.62 NA Land Owner
29 405 79.37 9.38 NA Promoter
30 406 79.57 9.19 NA Promoter
31 407 79.27 9.48 NA Land Owner
32 408 80.49 8.26 NA Land Owner
33 501 62.79 8.30 NA Promoter
34 502 62.77 8.32 NA Land Owner
35 503 62.70 8.39 NA Land Owner
36 504 62.47 8.62 NA Land Owner
37 505 79.37 9.38 NA Promoter
38 506 79.57 9.19 NA Promoter
39 507 79.27 9.48 NA Promoter
40 508 80.49 8.26 NA Promoter
Types of garages and parking
House No. Type of Garage/ Parking allotted Serial No., if any Dimension (Length x Width) in Metres Floor area in sq. metres Garage/Parking area cost is included or additional
101 Covered Parking 101 4.57 X 2.51 11.47 Included
102 Covered Parking 102 4.57 X 2.51 11.47 Included
103 Covered Parking 103 4.57 X 2.51 11.47 Included
104 Covered Parking 104 4.57 X 2.51 11.47 Included
105 Covered Parking 105 4.57 X 2.51 11.47 Included
106 Covered Parking 106 4.57 X 2.51 11.47 Included
107 Covered Parking 107 4.57 X 2.51 11.47 Included
108 Covered Parking 108 4.57 X 2.51 11.47 Included
201 Covered Parking 201 4.57 X 2.51 11.47 Included
202 Covered Parking 202 4.57 X 2.51 11.47 Included
203 Covered Parking 203 4.57 X 2.51 11.47 Included
204 Covered Parking 204 4.57 X 2.51 11.47 Included
205 Covered Parking 205 4.57 X 2.51 11.47 Included
206 Covered Parking 206 4.57 X 2.51 11.47 Included
207 Covered Parking 207 4.57 X 2.51 11.47 Included
208 Covered Parking 208 4.57 X 2.51 11.47 Included
301 Covered Parking 301 4.57 X 2.51 11.47 Included
302 Covered Parking 302 4.57 X 2.51 11.47 Included
303 Covered Parking 303 4.57 X 2.51 11.47 Included
304 Covered Parking 304 4.57 X 2.51 11.47 Included
305 Covered Parking 305 4.57 X 2.51 11.47 Included
306 Covered Parking 306 4.57 X 2.51 11.47 Included
307 Covered Parking 307 4.57 X 2.51 11.47 Included
308 Covered Parking 308 4.57 X 2.51 11.47 Included
401 Covered Parking 401 4.57 X 2.51 11.47 Included
402 Covered Parking 402 4.57 X 2.51 11.47 Included
403 Covered Parking 403 4.57 X 2.51 11.47 Included
404 Covered Parking 404 4.57 X 2.51 11.47 Included
405 Covered Parking 405 4.57 X 2.51 11.47 Included
406 Covered Parking 406 4.57 X 2.51 11.47 Included
407 Covered Parking 407 4.57 X 2.51 11.47 Included
408 Covered Parking 408 4.57 X 2.51 11.47 Included
501 Covered Parking 501 4.57 X 2.51 11.47 Included
502 Covered Parking 502 4.57 X 2.51 11.47 Included
503 Covered Parking 503 4.57 X 2.51 11.47 Included
504 Covered Parking 504 4.57 X 2.51 11.47 Included
505 Covered Parking 505 4.57 X 2.51 11.47 Included
506 Covered Parking 506 4.57 X 2.51 11.47 Included
507 Covered Parking 507 4.57 X 2.51 11.47 Included
508 Covered Parking 508 4.57 X 2.51 11.47 Included
Yes

Facilities to be provided

Particulars of Facilities Status of the facility Brief description of facility
Drinking Water Facility Ground Water Copy of Consent Letter
Fire Fighting Facility No
Emergency Evacuation Services No
Use of Renewable Energy Yes Rain Water Harvesting
Lift Facility Yes 2 Nos of lifts, 6 Passenger Lift, Johnson Brand with ARD Facility
Market Complex No
Community Hall Yes 40.16 Sqmtr
Gymnasium No
Swimming Pool No
Play Ground No
Park/Garden No
Plantation Area Yes 23 Nos. Trees (1 No. Tree per 80 sqmtr)
Others(Please Specify) No
Internal Road No
External Road Yes 9.14 mtr wide road black top road
Elecricity Supply Yes Copy of Consent Letter
Other Amenities No

Bank Particulars of the Project

  DCB Bank Ltd.
  Chandrasekharpur
  42122000000019
  DCBL0000421
   View
  6812024
  9776019999

Particulars of Architect/Construction Engineer/Contractor/Chartered Accountant

Name position Address with mobile number and email address Registration number Key real estate projects Is active Effective date
Samir Kumar Patel Architect Plot no- 272, 1st floor, Cenal Road, Near Chandimata Lane-1, GGp Road, Rasulgarh,Bhubaneswar-751010, Mobile no- 9437090714, Email id- samir8229@gmail.com CA/2006/38244
Er. Bibbhudendu Keshari Bhola Construction Engineer A/48, Nilakantha Nagar, Debray College Road, Unit-08, Bhubaneswar, Mobile no- 9437141179, Email id- nirmanengs@gmail.com RTP/DTP(ST.ER)-019/2017
S.S Tekriwal Chartered Accountant Kathagarh Road, Cuttack, Odisha, Mobile no- 9437017625, Email id- sst_ca@rediffmail.com 319218E

Financial Details

:  1031.81 :   View
  31-12-2026 :  300
:  731.81 :  0

Documents Attached

Description of Document Option Documents
Fire Safety Certificate Undertaking Attached
Affidavit in Form-A as per clause-l of sub-section-2 of section-4 of the Act Yes Attached
Allotment letter format Yes Attached
Conveyance Deed Format Yes Attached
Affidavit to adopt agreement for sale format as per Rule-8(1) of ORE (R and D) Rules, 2017 Yes Attached
Annual Report 2022-23 Attached
Annual Report 2020-21 Attached
Annual Report 2021-22 Attached
IT Return 2022-23 Attached
IT Return 2020-21 Attached
IT Return 2021-22 Attached
Audit Report 2022-23 Attached
Audit Report 2020-21 Attached
Audit Report 2021-22 Attached

Additional Documents Attached

Sl. No. Title of the document Upload Document
1 Authorization Letter
2 Clarification Regarding A 0.445 dec.
3 Regarding Annual Report & Audit Report

Other documents

“I undertake that the information submitted by me in this application are correct and true to best my knowledge. I also understand that providing false or wrong information is punishable under the Section-60 of the Real Estate (Regulation & Development) Act, 2016. I also further understand that furnishing wrong or false information will lead to rejection of my application registration of the project with forfeiture of registration fee and other charges deposited by me.”
  

Construction Progress

Updated Construction Progress

SL NO. Description Scheduled date of completion Current Status Remarks
1 Site Development 11-01-2021 Tie-Beam work in Progress
2 Roof Casting NA NA NA
3 Ground Floor/Stilt Floor 06-05-2021 Work in Progress
4 1 Floor 10-07-2021 Work in Progress
5 2 Floor 05-09-2021 Work in Progress
6 3 Floor 10-12-2021 Work in Progress
7 4 Floor 25-02-2022 Work in Progress
8 5 Floor 31-08-2022 Work in Progress
9 Brick Work & Plastering NA NA NA
10 Ground Floor/Stilt Floor 16-06-2021 Not started
11 1 Floor 25-10-2021 Work in Progress
12 2 Floor 31-01-2022 Not started NA
13 3 Floor 14-04-2022 Not started NA
14 4 Floor 22-08-2022 Not started NA
15 5 Floor 26-05-2022 Not started NA
16 Electrical Works 30-04-2023 Not started NA
17 Concealed Cabling including Plugs & switches 31-12-2023 Not started NA
18 Installation & Charging of Transformer 31-03-2024 Not started NA
19 Connection to Flats/Apartments 30-04-2025 Not started NA
20 PH works 31-12-2024 Not started NA
21 Laying of concealed Pipes 31-01-2025 Not started NA
22 PH Fittings 31-08-2025 Not started NA
23 Overhead Water Tanks 31-03-2023 Not started NA
24 Water Supply Connection to all units 31-08-2025 Not started NA
25 STP construction and completion 30-09-2025 Not started NA
26 Distempering & Colouring of all units and exteriors 30-04-2025 Not started NA
27 Fixation of doors and windows 31-05-2025 Not started NA
28 Scheduled Date of handing over possession 31-12-2025 Not handed over NA
29 Development of common areas, parks, gardens etc 30-06-2025 Not started NA
Updated Changes on 13-07-2023
30 Site Development 11-01-2021 Completed NA
31 NA NA NA NA
32 Ground Floor/Stilt Floor 06-05-2021 Completed NA
33 1 Floor 10-07-2021 Completed NA
34 2 Floor 05-09-2021 Completed NA
35 3 Floor 10-12-2021 Completed NA
36 4 Floor 25-02-2022 Completed NA
37 5 Floor 31-08-2022 Completed
38 NA NA NA NA
39 Ground Floor/Stilt Floor 16-06-2021 Completed NA
40 1 Floor 25-10-2021 Completed
41 2 Floor 31-01-2022 Completed
42 3 Floor 14-04-2022 Completed
43 4 Floor 22-08-2022 Completed
44 5 Floor 26-05-2022 Completed
45 Electrical Works 31-12-2023 Under Progress NA
46 Concealed Cabling including Plugs & switches 31-12-2023 Not started NA
47 Installation & Charging of Transformer 31-03-2024 Not started NA
48 Connection to Flats/Apartments 30-04-2025 Not started NA
49 PH works 31-12-2024 under progress NA
50 Laying of concealed Pipes 31-01-2024 Not started NA
51 PH Fittings 29-02-2024 Not started NA
52 Overhead Water Tanks 31-12-2023 Not started NA
53 Water Supply Connection to all units 01-02-2024 Not started NA
54 STP construction and completion 30-09-2025 Not started NA
55 Distempering & Colouring of all units and exteriors 31-01-2024 under progress
56 Fixation of doors and windows 31-10-2023 Not started NA
57 Scheduled Date of handing over possession 31-12-2025 Not handed over NA
58 Development of common areas, parks, gardens etc 30-06-2025 Not started NA
Updated Changes on 14-10-2023
59 Site Development 11-01-2021 Completed NA
60 NA 31-01-2024 Under Progress NA
61 Ground Floor/Stilt Floor 06-05-2021 Completed NA
62 1 Floor 10-07-2021 Completed NA
63 2 Floor 05-09-2021 Completed NA
64 3 Floor 10-12-2021 Completed NA
65 4 Floor 25-02-2022 Completed NA
66 5 Floor 31-08-2022 Completed NA
67 NA 31-01-2024 Under Progress NA
68 Ground Floor/Stilt Floor 16-06-2021 Completed NA
69 1 Floor 25-10-2021 Completed NA
70 2 Floor 31-01-2022 Completed NA
71 3 Floor 14-04-2022 Completed NA
72 4 Floor 22-08-2022 Completed NA
73 5 Floor 26-05-2022 Completed NA
74 Electrical Works 31-12-2023 Under Progress NA
75 Concealed Cabling including Plugs & switches 31-12-2023 Under Progress
76 Installation & Charging of Transformer 31-03-2024 Not started NA
77 Connection to Flats/Apartments 30-04-2025 Not started NA
78 PH works 31-12-2024 under progress NA
79 Laying of concealed Pipes 31-01-2024 Under Progress
80 PH Fittings 29-02-2024 Not started NA
81 Overhead Water Tanks 31-12-2023 Not started NA
82 Water Supply Connection to all units 01-02-2024 Not started NA
83 STP construction and completion 30-09-2025 Not started NA
84 Distempering & Colouring of all units and exteriors 31-01-2024 under progress NA
85 Fixation of doors and windows 31-12-2023 Under Progress
86 Scheduled Date of handing over possession 31-12-2025 Not handed over NA
87 Development of common areas, parks, gardens etc 30-06-2025 Not started NA
Updated Changes on 12-01-2024
88 Site Development 11-01-2021 Completed NA
89 NA 31-01-2024 Under Progress NA
90 Ground Floor/Stilt Floor 06-05-2021 Completed NA
91 1 Floor 10-07-2021 Completed
92 2 Floor 05-09-2021 Completed
93 3 Floor 10-12-2021 Completed
94 4 Floor 25-02-2022 Completed
95 5 Floor 31-08-2022 Completed
96 NA 31-01-2024 Under Progress NA
97 Ground Floor/Stilt Floor 16-06-2021 Completed NA
98 1 Floor 25-10-2021 Completed
99 2 Floor 31-01-2022 Completed
100 3 Floor 14-04-2022 Completed
101 4 Floor 22-08-2022 Completed
102 5 Floor 26-05-2022 Completed
103 Electrical Works 31-12-2023 Under Progress NA
104 Concealed Cabling including Plugs & switches 31-12-2023 Under Progress NA
105 Installation & Charging of Transformer 31-03-2024 Under Progress NA
106 Connection to Flats/Apartments 30-04-2025 Not Started NA
107 PH works 31-12-2024 under progress NA
108 Laying of concealed Pipes 31-01-2024 Under Progress NA
109 PH Fittings 29-02-2024 Under Progress NA
110 Overhead Water Tanks 31-12-2023 Under Progress NA
111 Water Supply Connection to all units 01-02-2024 Under Progress NA
112 STP construction and completion 01-06-2024 Work Under Progress NA
113 Distempering & Colouring of all units and exteriors 01-04-2024 Work Under Progress NA
114 Fixation of doors and windows 01-04-2024 Work Under Progress NA
115 Scheduled Date of handing over possession 31-12-2025 Not started NA
116 Development of common areas, parks, gardens etc 30-06-2025 Not started NA
Updated Changes on 11-04-2024
117 Site Development 11-01-2021 Completed NA
118 NA 31-01-2024 Under Progress NA
119 Ground Floor/Stilt Floor 06-05-2021 Completed NA
120 1 Floor 10-07-2021 Completed NA
121 2 Floor 05-09-2021 Completed NA
122 3 Floor 10-12-2021 Completed NA
123 4 Floor 25-02-2022 Completed NA
124 5 Floor 31-08-2022 Completed NA
125 NA 31-01-2024 Under Progress NA
126 Ground Floor/Stilt Floor 16-06-2021 Completed NA
127 1 Floor 25-10-2021 Completed NA
128 2 Floor 31-01-2022 Completed NA
129 3 Floor 14-04-2022 Completed NA
130 4 Floor 22-08-2022 Completed NA
131 5 Floor 26-05-2022 Completed NA
132 Electrical Works 31-03-2024 90% WORK COMPLETE NA
133 Concealed Cabling including Plugs & switches 31-03-2024 Under Progress NA
134 Installation & Charging of Transformer 01-07-2024 Under Progress NA
135 Connection to Flats/Apartments 30-04-2025 Not Started NA
136 PH works 31-12-2024 COMPLETE NA
137 Laying of concealed Pipes 31-01-2024 COMPLETE NA
138 PH Fittings 29-02-2024 COMPLETE NA
139 Overhead Water Tanks 01-02-2024 COMPLETE
140 Water Supply Connection to all units 01-06-2024 Under Progress NA
141 STP construction and completion 01-06-2024 80% WORK COMPLETE NA
142 Distempering & Colouring of all units and exteriors 01-04-2024 COMPLETE
143 Fixation of doors and windows 01-04-2024 COMPLETE
144 Scheduled Date of handing over possession 31-12-2025 Not started NA
145 Development of common areas, parks, gardens etc 30-06-2025 Not started NA

Booking Status

Residential Flats/ House
S. No. Flat No./ House No.

Area in square metres

Ownership Status
Carpet Area Balcony Area Exclusive Open Terrace Area
1 101 62.79 8.30 NA Land Owner
2 102 62.77 8.32 NA Land Owner
3 103 62.70 8.39 NA Promoter
4 104 62.47 8.62 NA Promoter
5 105 79.37 9.38 NA Promoter
6 106 79.57 9.19 NA Land Owner
7 107 79.27 9.48 NA Promoter
8 108 80.49 8.26 NA Promoter
9 201 62.79 8.30 NA Promoter
10 202 62.77 8.32 NA Promoter
11 203 62.70 8.39 NA Land Owner
12 204 62.47 8.62 NA Land Owner
13 205 79.37 9.38 NA Promoter
14 206 79.57 9.19 NA Promoter
15 207 79.27 9.48 NA Land Owner
16 208 80.49 8.26 NA Promoter
17 301 62.79 8.30 NA Promoter
18 302 62.77 8.32 NA Promoter
19 303 62.70 8.39 NA Land Owner
20 304 62.47 8.62 NA Promoter
21 305 79.37 9.38 NA Land Owner
22 306 79.57 9.19 NA Land Owner
23 307 79.27 9.48 NA Promoter
24 308 80.49 8.26 NA Promoter
25 401 62.79 8.30 NA Promoter
26 402 62.77 8.32 NA Land Owner
27 403 62.70 8.39 NA Promoter
28 404 62.47 8.62 NA Land Owner
29 405 79.37 9.38 NA Promoter
30 406 79.57 9.19 NA Promoter
31 407 79.27 9.48 NA Land Owner
32 408 80.49 8.26 NA Land Owner
33 501 62.79 8.30 NA Promoter
34 502 62.77 8.32 NA Land Owner
35 503 62.70 8.39 NA Land Owner
36 504 62.47 8.62 NA Land Owner
37 505 79.37 9.38 NA Promoter
38 506 79.57 9.19 NA Promoter
39 507 79.27 9.48 NA Promoter
40 508 80.49 8.26 NA Promoter

Financial Status

SL No. Funds Collected from the Allottees Funds Borrowed from Financial Institutions Funds Employed from Own Sources Expenditure As On Date Status
1 100339679 8917284 0 72054385 13-07-2023 All the slabs have been completed, Brick work Completed, Flooring & Color work is on progress
2 118210730 0 556554 109500000 14-10-2023 75% of the work has been completed
3 120830254 0 0 113086956 31-12-2023 All the slabs have been completed, Brick work Completed, Tile, PH & Color work is on progress
4 120830254 0 55000 120885254 31-03-2024 ONGOING

Updated Conditions of building plan approval

Sl. No. Description of Conditions Schedule date of compliance Present Status
1 The building shall be used exclusively for residential purpose and the use shall not be changed to any other use without prior of this Authority. 30-11-2021 work in progress
2 The development shall be undertaken strictly according to plans enclosed with necessary permission endorsement. 16-03-2022 work in progress
3 Parking space measuring 982.11 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 15-06-2022 work in progress
4 The land over which construction is proposed is accessible by an approved means of access of 9.14 Mt (Nine point one four) in width. 17-11-2022 work in progress
5 The land in question must be in lawful ownership and peaceful possession of the applicant. 30-12-2022 work in progress
6 The permission granted under these regulations shall remain valid up to three years from the date of issue. However the permission shall have to be revalidated before the expiry of the above period on payment of such fee as may be prescribed under rules and such revalidation shall be valid for one year. 03-05-2023 work in progress
7 In Case of any dispute arising out of land record or in respect of right,title,intrest after this permission is granted, the permission so granted shall be treated as automatically cancelled during the period of dispute. 10-11-2023 work in progress
8 Neither granting of the permit nor the approval of the drawing and specifications, nor inspections made by the Authority during erection of the building shall in any way relieve the owner of such building from full responsibility for carrying out the work in accordance with the requirements of NBC 2016 and these regulations. 05-10-2023 work in progress
9 Wherever tests of any material are made to ensure conformity of the requirements of the regulations in force, records of the test data shall be kept available for inspection during the construction of building and for such period thereafter as required by the Authority. 23-03-2023 work in progress
10 If the Authority finds at any stage that the construction is not being carried in accordance to the sanctioned plan or is in violation of any of the provisions of these regulations, it shall notify the owner and no further construction shall be allowed until necessary corrections in the plan are made and the corrected plan is approved. 07-07-2023 work in progress
Updated Changes on 13-07-2023
11 The building shall be used exclusively for residential purpose and the use shall not be changed to any other use without prior of this Authority. 30-11-2021 work in progress
12 The development shall be undertaken strictly according to plans enclosed with necessary permission endorsement. 16-03-2022 work in progress
13 Parking space measuring 982.11 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 15-06-2022 work in progress
14 The land over which construction is proposed is accessible by an approved means of access of 9.14 Mt (Nine point one four) in width. 17-11-2022 work in progress
15 The land in question must be in lawful ownership and peaceful possession of the applicant. 30-12-2022 work in progress
16 The permission granted under these regulations shall remain valid up to three years from the date of issue. However the permission shall have to be revalidated before the expiry of the above period on payment of such fee as may be prescribed under rules and such revalidation shall be valid for one year. 03-05-2023 work in progress
17 In Case of any dispute arising out of land record or in respect of right,title,intrest after this permission is granted, the permission so granted shall be treated as automatically cancelled during the period of dispute. 10-11-2023 work in progress
18 Neither granting of the permit nor the approval of the drawing and specifications, nor inspections made by the Authority during erection of the building shall in any way relieve the owner of such building from full responsibility for carrying out the work in accordance with the requirements of NBC 2016 and these regulations. 05-10-2023 work in progress
19 Wherever tests of any material are made to ensure conformity of the requirements of the regulations in force, records of the test data shall be kept available for inspection during the construction of building and for such period thereafter as required by the Authority. 23-03-2023 work in progress
20 If the Authority finds at any stage that the construction is not being carried in accordance to the sanctioned plan or is in violation of any of the provisions of these regulations, it shall notify the owner and no further construction shall be allowed until necessary corrections in the plan are made and the corrected plan is approved. 07-07-2023 work in progress
Updated Changes on 09-10-2023
21 The building shall be used exclusively for residential purpose and the use shall not be changed to any other use without prior of this Authority. 30-11-2021 work in progress
22 The development shall be undertaken strictly according to plans enclosed with necessary permission endorsement. 16-03-2022 work in progress
23 Parking space measuring 982.11 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 15-06-2022 work in progress
24 The land over which construction is proposed is accessible by an approved means of access of 9.14 Mt (Nine point one four) in width. 17-11-2022 work in progress
25 The land in question must be in lawful ownership and peaceful possession of the applicant. 30-12-2022 work in progress
26 The permission granted under these regulations shall remain valid up to three years from the date of issue. However the permission shall have to be revalidated before the expiry of the above period on payment of such fee as may be prescribed under rules and such revalidation shall be valid for one year. 03-05-2023 work in progress
27 In Case of any dispute arising out of land record or in respect of right,title,intrest after this permission is granted, the permission so granted shall be treated as automatically cancelled during the period of dispute. 10-11-2023 work in progress
28 Neither granting of the permit nor the approval of the drawing and specifications, nor inspections made by the Authority during erection of the building shall in any way relieve the owner of such building from full responsibility for carrying out the work in accordance with the requirements of NBC 2016 and these regulations. 05-10-2023 work in progress
29 Wherever tests of any material are made to ensure conformity of the requirements of the regulations in force, records of the test data shall be kept available for inspection during the construction of building and for such period thereafter as required by the Authority. 23-03-2023 work in progress
30 If the Authority finds at any stage that the construction is not being carried in accordance to the sanctioned plan or is in violation of any of the provisions of these regulations, it shall notify the owner and no further construction shall be allowed until necessary corrections in the plan are made and the corrected plan is approved. 07-07-2023 work in progress
Updated Changes on 12-01-2024
31 The building shall be used exclusively for residential purpose and the use shall not be changed to any other use without prior of this Authority. 30-11-2021 work in progress
32 The development shall be undertaken strictly according to plans enclosed with necessary permission endorsement. 16-03-2022 work in progress
33 Parking space measuring 982.11 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 15-06-2022 work in progress
34 The land over which construction is proposed is accessible by an approved means of access of 9.14 Mt (Nine point one four) in width. 17-11-2022 work in progress
35 The land in question must be in lawful ownership and peaceful possession of the applicant. 30-12-2022 work in progress
36 The permission granted under these regulations shall remain valid up to three years from the date of issue. However the permission shall have to be revalidated before the expiry of the above period on payment of such fee as may be prescribed under rules and such revalidation shall be valid for one year. 03-05-2023 work in progress
37 In Case of any dispute arising out of land record or in respect of right,title,intrest after this permission is granted, the permission so granted shall be treated as automatically cancelled during the period of dispute. 10-11-2023 work in progress
38 Neither granting of the permit nor the approval of the drawing and specifications, nor inspections made by the Authority during erection of the building shall in any way relieve the owner of such building from full responsibility for carrying out the work in accordance with the requirements of NBC 2016 and these regulations. 05-10-2023 work in progress
39 Wherever tests of any material are made to ensure conformity of the requirements of the regulations in force, records of the test data shall be kept available for inspection during the construction of building and for such period thereafter as required by the Authority. 23-03-2023 work in progress
40 If the Authority finds at any stage that the construction is not being carried in accordance to the sanctioned plan or is in violation of any of the provisions of these regulations, it shall notify the owner and no further construction shall be allowed until necessary corrections in the plan are made and the corrected plan is approved. 07-07-2023 work in progress
Updated Changes on 11-04-2024
41 The building shall be used exclusively for residential purpose and the use shall not be changed to any other use without prior of this Authority. 30-11-2021 work in progress
42 The development shall be undertaken strictly according to plans enclosed with necessary permission endorsement. 16-03-2022 work in progress
43 Parking space measuring 982.11 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 15-06-2022 work in progress
44 The land over which construction is proposed is accessible by an approved means of access of 9.14 Mt (Nine point one four) in width. 17-11-2022 work in progress
45 The land in question must be in lawful ownership and peaceful possession of the applicant. 30-12-2022 work in progress
46 The permission granted under these regulations shall remain valid up to three years from the date of issue. However the permission shall have to be revalidated before the expiry of the above period on payment of such fee as may be prescribed under rules and such revalidation shall be valid for one year. 03-05-2023 work in progress
47 In Case of any dispute arising out of land record or in respect of right,title,intrest after this permission is granted, the permission so granted shall be treated as automatically cancelled during the period of dispute. 10-11-2023 work in progress
48 Neither granting of the permit nor the approval of the drawing and specifications, nor inspections made by the Authority during erection of the building shall in any way relieve the owner of such building from full responsibility for carrying out the work in accordance with the requirements of NBC 2016 and these regulations. 05-10-2023 work in progress
49 Wherever tests of any material are made to ensure conformity of the requirements of the regulations in force, records of the test data shall be kept available for inspection during the construction of building and for such period thereafter as required by the Authority. 23-03-2023 work in progress
50 If the Authority finds at any stage that the construction is not being carried in accordance to the sanctioned plan or is in violation of any of the provisions of these regulations, it shall notify the owner and no further construction shall be allowed until necessary corrections in the plan are made and the corrected plan is approved. 07-07-2023 work in progress

Updated Project Documents

Sl. No. Title of the document Upload Document
1 Agreement To Sale
2 PERFORMA I-II
3 PERFORMA III
4 PERFORMA-I
5 PERFORMA-II
6 PERFORMA-III
7 PERFORMA-I 01.10.2023 TO 31.12.2023
8 PERFORMA-II 01.10.2023 TO 31.12.2023
9 PERFORMA-III 01.10.2023 TO 31.12.2023
10 BANK STATEMENT OCTOBER 2023
11 BANK STATEMENT NOVEMBER 2023
12 BANK STATEMENT DECEMBER 2023
13 PERFORMA-I JAN-MAR 2024
14 PERFORMA-II JAN-MAR 2024
15 PERFORMA-III JAN-MAR 2024
:  Anshuman Patnaik :  
NA :  AWLPP2012N
:PAN Card :  archidhomes@gmail.com
:  MBA :  9437076631
:  Has an experience of 14 years in the real-estate sector
:  Yes :  NA
:  SIMANTIKA MOHANTY :  
NA :  AMDPM3225G
:PAN Card :  archidhomes@gmail.com
:  B.A :  7537000001
:  Has an experience of 14 years in the real-estate sector
:  Yes :  NA
:  BANDAN MOHANTY :  
NA :  AFMPM7898D
:PAN Card :  archidhomes@gmail.com
:  MBA :  9437094412
:  Has an experience of 14 years in the real-estate sector
:  Yes :  NA

Particulars of Architect/Construction Engineer/Contractor/Chartered Accountant

Name position Address with mobile number and email address Registration number Key real estate projects Is active Effective date
Samir Kumar Patel Architect Plot no- 272, 1st floor, Cenal Road, Near Chandimata Lane-1, GGp Road, Rasulgarh,Bhubaneswar-751010, Mobile no- 9437090714, Email id- samir8229@gmail.com CA/2006/38244
Er. Bibbhudendu Keshari Bhola Construction Engineer A/48, Nilakantha Nagar, Debray College Road, Unit-08, Bhubaneswar, Mobile no- 9437141179, Email id- nirmanengs@gmail.com RTP/DTP(ST.ER)-019/2017
S.S Tekriwal Chartered Accountant Kathagarh Road, Cuttack, Odisha, Mobile no- 9437017625, Email id- sst_ca@rediffmail.com 319218E

Updated Units

House No. Type of Garage/ Parking allotted Serial No., if any Dimension (Length x Width) in Metres Floor area in sq. metres Garage/Parking area cost is included or additional
Updated Changes
101 Covered Parking 101 4.57 X 2.51 11.47 Included
102 Covered Parking 102 4.57 X 2.51 11.47 Included
103 Covered Parking 103 4.57 X 2.51 11.47 Included
104 Covered Parking 104 4.57 X 2.51 11.47 Included
105 Covered Parking 105 4.57 X 2.51 11.47 Included
106 Covered Parking 106 4.57 X 2.51 11.47 Included
107 Covered Parking 107 4.57 X 2.51 11.47 Included
108 Covered Parking 108 4.57 X 2.51 11.47 Included
201 Covered Parking 201 4.57 X 2.51 11.47 Included
202 Covered Parking 202 4.57 X 2.51 11.47 Included
203 Covered Parking 203 4.57 X 2.51 11.47 Included
204 Covered Parking 204 4.57 X 2.51 11.47 Included
205 Covered Parking 205 4.57 X 2.51 11.47 Included
206 Covered Parking 206 4.57 X 2.51 11.47 Included
207 Covered Parking 207 4.57 X 2.51 11.47 Included
208 Covered Parking 208 4.57 X 2.51 11.47 Included
301 Covered Parking 301 4.57 X 2.51 11.47 Included
302 Covered Parking 302 4.57 X 2.51 11.47 Included
303 Covered Parking 303 4.57 X 2.51 11.47 Included
304 Covered Parking 304 4.57 X 2.51 11.47 Included
305 Covered Parking 305 4.57 X 2.51 11.47 Included
306 Covered Parking 306 4.57 X 2.51 11.47 Included
307 Covered Parking 307 4.57 X 2.51 11.47 Included
308 Covered Parking 308 4.57 X 2.51 11.47 Included
401 Covered Parking 401 4.57 X 2.51 11.47 Included
402 Covered Parking 402 4.57 X 2.51 11.47 Included
403 Covered Parking 403 4.57 X 2.51 11.47 Included
404 Covered Parking 404 4.57 X 2.51 11.47 Included
405 Covered Parking 405 4.57 X 2.51 11.47 Included
406 Covered Parking 406 4.57 X 2.51 11.47 Included
407 Covered Parking 407 4.57 X 2.51 11.47 Included
408 Covered Parking 408 4.57 X 2.51 11.47 Included
501 Covered Parking 501 4.57 X 2.51 11.47 Included
502 Covered Parking 502 4.57 X 2.51 11.47 Included
503 Covered Parking 503 4.57 X 2.51 11.47 Included
504 Covered Parking 504 4.57 X 2.51 11.47 Included
505 Covered Parking 505 4.57 X 2.51 11.47 Included
506 Covered Parking 506 4.57 X 2.51 11.47 Included
507 Covered Parking 507 4.57 X 2.51 11.47 Included
508 Covered Parking 508 4.57 X 2.51 11.47 Included
Updated Changes
101 Covered Parking 101 4.57 X 2.51 11.47 Included
102 Covered Parking 102 4.57 X 2.51 11.47 Included
103 Covered Parking 103 4.57 X 2.51 11.47 Included
104 Covered Parking 104 4.57 X 2.51 11.47 Included
105 Covered Parking 105 4.57 X 2.51 11.47 Included
106 Covered Parking 106 4.57 X 2.51 11.47 Included
107 Covered Parking 107 4.57 X 2.51 11.47 Included
108 Covered Parking 108 4.57 X 2.51 11.47 Included
201 Covered Parking 201 4.57 X 2.51 11.47 Included
202 Covered Parking 202 4.57 X 2.51 11.47 Included
203 Covered Parking 203 4.57 X 2.51 11.47 Included
204 Covered Parking 204 4.57 X 2.51 11.47 Included
205 Covered Parking 205 4.57 X 2.51 11.47 Included
206 Covered Parking 206 4.57 X 2.51 11.47 Included
207 Covered Parking 207 4.57 X 2.51 11.47 Included
208 Covered Parking 208 4.57 X 2.51 11.47 Included
301 Covered Parking 301 4.57 X 2.51 11.47 Included
302 Covered Parking 302 4.57 X 2.51 11.47 Included
303 Covered Parking 303 4.57 X 2.51 11.47 Included
304 Covered Parking 304 4.57 X 2.51 11.47 Included
305 Covered Parking 305 4.57 X 2.51 11.47 Included
306 Covered Parking 306 4.57 X 2.51 11.47 Included
307 Covered Parking 307 4.57 X 2.51 11.47 Included
308 Covered Parking 308 4.57 X 2.51 11.47 Included
401 Covered Parking 401 4.57 X 2.51 11.47 Included
402 Covered Parking 402 4.57 X 2.51 11.47 Included
403 Covered Parking 403 4.57 X 2.51 11.47 Included
404 Covered Parking 404 4.57 X 2.51 11.47 Included
405 Covered Parking 405 4.57 X 2.51 11.47 Included
406 Covered Parking 406 4.57 X 2.51 11.47 Included
407 Covered Parking 407 4.57 X 2.51 11.47 Included
408 Covered Parking 408 4.57 X 2.51 11.47 Included
501 Covered Parking 501 4.57 X 2.51 11.47 Included
502 Covered Parking 502 4.57 X 2.51 11.47 Included
503 Covered Parking 503 4.57 X 2.51 11.47 Included
504 Covered Parking 504 4.57 X 2.51 11.47 Included
505 Covered Parking 505 4.57 X 2.51 11.47 Included
506 Covered Parking 506 4.57 X 2.51 11.47 Included
507 Covered Parking 507 4.57 X 2.51 11.47 Included
508 Covered Parking 508 4.57 X 2.51 11.47 Included