Promoter Details
Promoter Name :
AMARESH PARIDA
Project Name :
AYUSHPREM ENCLAVE
Project Location :
( Residential Project, B+G+4, No. of Units- 19 )

Form- I

A. Promoter's Details

:  GK GLOBAL CONTECH :  Partnership
:  18202000060 of 2020 :View
NA :  Flat No.-102, Sai Prasad Enclave, Canal Road, Rasulgarh, Bhubaneswar, Dist- Khordha, Odisha- 751010.
:  Flat No.- 102, Sai Prasad Enclave, Canal Road, Rasulgarh, Bhubaneswar, Dist- Khordha, Odisha- 751010. :  gkodisha@gmail.com
:  9938212981
:  AATFG5890P :View
:  2 YEARS OF EXPERIENCE AS REAL ESTATE PROMOTER IN ODISHA :  NA
NA

B. Details of Board of Directors / Partners / MC Members

:  AMARESH PARIDA :  
:  Partner :  AWNPP5239R
:PAN Card :  amareshnsui.odisha@gmail.com
:  B.TECH :  9938212981
:  10 YEARS OF EXPERIENCE
:  Yes :  NA
:  MANAS KUMAR PAL :  
:  Partner :  BCLPP4414K
:PAN Card :  manasindus@gmail.com
:  B.TECH :  9438840739
:  2 YEARS OF EXPERIENCE
:  Yes :  NA

Annexure-1

Details of last projects already implemented (Ongoing or Complete)

1. :  GOPINATH VILLA :  Residential
:  PLOT NO.353, 356 KHATA NO.529/140-A, PLOT NO.351 KHATA NO.529/149, MOUZA-MATIAPADA-2, BHUBANESWAR, ODISHA :  Ongoing
:  RP/26/2022/00683 NA
:  Joint Venture
:  SUB-DIVISIONAL LAYOUT PLAN WITH (G+2) GROUP HOUSING PLAN & (S+4) MIG RESIDENTIAL NA NA :  SUB-DIVISIONAL LAYOUT PLAN WITH (G+2) GROUP HOUSING PLAN & (S+4) MIG RESIDENTIAL
:  No

:   :  
:   :  
:  
: No :  NA
: No :  NA

Annexure-2

Details of the project to be registered

:   New :  AYUSHPREM ENCLAVE
:  Residential :  ( Residential Project, B+G+4, No. of Units- 19 )
:  Khordha :  Bhubaneswar
:  751012 :  Urban Local Body
:  BHUBANESWAR MUNICIPAL CORPORATION
:  B+G+4 (MIG) storied Residential Apartment :  NA

Land Details of the Project


:  1678 :  766
:  NAYAPALLI :  822
:  Yes
No :  View
:  View :  View
:  Other Person
:  JITENDRA KUMAR PATTANAIK :  THE LAND OWNER JITENDRA KUMAR PATTANAIK HAS EXECUTED DEVELOPMENT AGREEMENT WITH THE PROMOTER GK GLOBAL CONTECH. THE PROMOTER IS ALSO REGISTERED GPA HOLDER OVER THE LAND BEARING PLOT NO.1678 KHATA NO.766.
: No
: Yes
:  11082010332 :  09-12-2020
:  SUB-REGISTRAR, KHURDA :  Attached

Development Agreement

: Yes
Serial No. Particulars of the Person Land/Plot Details Share of the Person Document Attached
1 JITENDRA KUMAR PATTANAIK PLOT NO.1678 KHATA NO.766 55%   Agreement Copy

Building Plan

  View   View
  Download site plan 08-04-2025

Conditions of building plan approval

Sl. No. Description of Conditions Schedule date of compliance Present Status
1 Parking space measuring 430.77 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 11-06-2022 NOT STARTED
2 The land over which construction is proposed is accessible by an approved means of access of 9.14 M (Nine point One Four) in width. 11-06-2022 NOT STARTED
3 Obtain, wherever applicable, from the competent Authority permissions/clearance required in connection with the proposed work; 11-06-2022 NOT STARTED
4 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 11-06-2022 NOT STARTED
5 Register the said Apartment project over scheduled property under the Real Estate(Regulation & Development)-Act-2016. 11-06-2022 IN PROGRESS
6 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC from PHED vide Letter No- 14412 dt. 17.11.2021 & AAI NOC Vide Letter No-BHUB/EAST/B/072321/564459, dt. 12/08/2021. 11-06-2022 WILL COMPLY AS PER THE PERMISSION
7 The applicant shall obtain NOC from the Central Ground Water Board towards extraction of ground water before start of construction. 11-06-2022 NOT STARTED
8 Storm water from the premises of roof top shall be conveyed and discharged to the rainwater recharging pits as per ODA (Planning & Building Standards) Rules, 2020. 11-06-2022 NOT STARTED
9 Plantation as required under the provision under Rule 30 of ODA (Planning & Building Standards) Rules, 2020 shall be strictly adhered. 11-06-2022 NOT STARTED
10 The applicant shall obtain EIDP towards development of Infrastructure & clearance from Engineering Wing of BMC before obtaining Occupancy Certificate. 11-06-2022 NOT STARTED

Layout Plan

: Yes :  View

Location Map with geo-coordinates of bend points

Point No. Latitude Longitude
1 20°16'49.0"N 85°49'13.2"E
2 20°16'48.1"N 85°49'12.9"E
3 20°16'48.3"N 85°49'12.4"E
4 20°16'48.6"N 85°49'11.7"E
5 20°16'48.8"N 85°49'11.8"E
6 20°16'48.7"N 85°49'12.1"E
7 20°16'49.5"N 85°49'12.4"E
View

Milestone of Project Construction

Description* Scheduled date of completion Current Status Site Images
Site Development 30-06-2022 IN PROGRESS
Roof Casting NA NA NA
Ground Floor/Stilt Floor 30-11-2022 NOT STARTED NA
1 Floor 31-01-2023 NOT STARTED NA
2 Floor 31-03-2023 NOT STARTED NA
3 Floor 31-05-2023 NOT STARTED NA
4 Floor 31-07-2023 NOT STARTED NA
Brick Work & Plastering NA NA NA
Ground Floor/Stilt Floor 31-05-2023 NOT STARTED NA
1 Floor 31-07-2023 NOT STARTED NA
2 Floor 30-09-2023 NOT STARTED NA
3 Floor 30-11-2023 NOT STARTED NA
4 Floor 31-01-2024 NOT STARTED NA
Electrical Works 30-06-2024 NOT STARTED NA
Concealed Cabling including Plugs & switches 30-06-2024 NOT STARTED NA
Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
PH works 30-11-2024 NOT STARTED NA
Laying of concealed Pipes 30-11-2024 NOT STARTED NA
PH Fittings 30-11-2024 NOT STARTED NA
Overhead Water Tanks 30-11-2024 NOT STARTED NA
Water Supply Connection to all units 30-11-2024 NOT STARTED NA
STP construction and completion 31-01-2025 NOT STARTED NA
Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
Fixation of doors and windows 31-03-2025 NOT STARTED NA
Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA
Site Development 30-06-2022 IN PROGRESS NA
NA NA NA NA
Ground Floor/Stilt Floor 30-11-2022 NOT STARTED NA
1 Floor 31-01-2023 NOT STARTED NA
2 Floor 31-03-2023 NOT STARTED NA
3 Floor 31-05-2023 NOT STARTED NA
4 Floor 31-07-2023 NOT STARTED NA
NA NA NA NA
Ground Floor/Stilt Floor 31-05-2023 NOT STARTED NA
1 Floor 31-07-2023 NOT STARTED NA
2 Floor 30-09-2023 NOT STARTED NA
3 Floor 30-11-2023 NOT STARTED NA
4 Floor 31-01-2024 NOT STARTED NA
Electrical Works 30-06-2024 NOT STARTED NA
Concealed Cabling including Plugs & switches 30-06-2024 NOT STARTED NA
Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
PH works 30-11-2024 NOT STARTED NA
Laying of concealed Pipes 30-11-2024 NOT STARTED NA
PH Fittings 30-11-2024 NOT STARTED NA
Overhead Water Tanks 30-11-2024 NOT STARTED NA
Water Supply Connection to all units 30-11-2024 NOT STARTED NA
STP construction and completion 31-01-2025 NOT STARTED NA
Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
Fixation of doors and windows 31-03-2025 NOT STARTED NA
Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA
Site Development 30-06-2022 IN PROGRESS NA
NA NA NA NA
Ground Floor/Stilt Floor 30-11-2022 NOT STARTED NA
1 Floor 31-01-2023 NOT STARTED NA
2 Floor 31-03-2023 NOT STARTED NA
3 Floor 31-05-2023 NOT STARTED NA
4 Floor 31-07-2023 NOT STARTED NA
NA NA NA NA
Ground Floor/Stilt Floor 31-05-2023 NOT STARTED NA
1 Floor 31-07-2023 NOT STARTED NA
2 Floor 30-09-2023 NOT STARTED NA
3 Floor 30-11-2023 NOT STARTED NA
4 Floor 31-01-2024 NOT STARTED NA
Electrical Works 30-06-2024 NOT STARTED NA
Concealed Cabling including Plugs & switches 30-06-2024 NOT STARTED NA
Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
PH works 30-11-2024 NOT STARTED NA
Laying of concealed Pipes 30-11-2024 NOT STARTED NA
PH Fittings 30-11-2024 NOT STARTED NA
Overhead Water Tanks 30-11-2024 NOT STARTED NA
Water Supply Connection to all units 30-11-2024 NOT STARTED NA
STP construction and completion 31-01-2025 NOT STARTED NA
Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
Fixation of doors and windows 31-03-2025 NOT STARTED NA
Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA
Site Development 30-06-2022 IN PROGRESS NA
NA NA NA NA
Ground Floor/Stilt Floor 30-11-2022 NOT STARTED NA
1 Floor 31-01-2023 NOT STARTED NA
2 Floor 31-03-2023 NOT STARTED NA
3 Floor 31-05-2023 NOT STARTED NA
4 Floor 31-07-2023 NOT STARTED NA
NA NA NA NA
Ground Floor/Stilt Floor 31-05-2023 NOT STARTED NA
1 Floor 31-07-2023 NOT STARTED NA
2 Floor 30-09-2023 NOT STARTED NA
3 Floor 30-11-2023 NOT STARTED NA
4 Floor 31-01-2024 NOT STARTED NA
Electrical Works 30-06-2024 NOT STARTED NA
Concealed Cabling including Plugs & switches 30-06-2024 NOT STARTED NA
Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
PH works 30-11-2024 NOT STARTED NA
Laying of concealed Pipes 30-11-2024 NOT STARTED NA
PH Fittings 30-11-2024 NOT STARTED NA
Overhead Water Tanks 30-11-2024 NOT STARTED NA
Water Supply Connection to all units 30-11-2024 NOT STARTED NA
STP construction and completion 31-01-2025 NOT STARTED NA
Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
Fixation of doors and windows 31-03-2025 NOT STARTED NA
Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA
Site Development 30-06-2022 IN PROGRESS NA
NA NA NA NA
Ground Floor/Stilt Floor 30-11-2022 IN PROGRESS NA
1 Floor 31-01-2023 NOT STARTED NA
2 Floor 31-03-2023 NOT STARTED NA
3 Floor 31-05-2023 NOT STARTED NA
4 Floor 31-07-2023 NOT STARTED NA
NA NA NA NA
Ground Floor/Stilt Floor 31-05-2023 NOT STARTED NA
1 Floor 31-07-2023 NOT STARTED NA
2 Floor 30-09-2023 NOT STARTED NA
3 Floor 30-11-2023 NOT STARTED NA
4 Floor 31-01-2024 NOT STARTED NA
Electrical Works 30-06-2024 NOT STARTED NA
Concealed Cabling including Plugs & switches 30-06-2024 NOT STARTED NA
Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
PH works 30-11-2024 NOT STARTED NA
Laying of concealed Pipes 30-11-2024 NOT STARTED NA
PH Fittings 30-11-2024 NOT STARTED NA
Overhead Water Tanks 30-11-2024 NOT STARTED NA
Water Supply Connection to all units 30-11-2024 NOT STARTED NA
STP construction and completion 31-01-2025 NOT STARTED NA
Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
Fixation of doors and windows 31-03-2025 NOT STARTED NA
Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA
Site Development 30-06-2022 IN PROGRESS NA
NA NA NA NA
Ground Floor/Stilt Floor 30-11-2022 COMPLETED NA
1 Floor 31-01-2023 COMPLETED NA
2 Floor 31-03-2023 COMPLETED NA
3 Floor 31-05-2023 NOT STARTED NA
4 Floor 31-07-2023 NOT STARTED NA
NA NA NA NA
Ground Floor/Stilt Floor 31-05-2023 NOT STARTED NA
1 Floor 31-07-2023 NOT STARTED NA
2 Floor 30-09-2023 NOT STARTED NA
3 Floor 30-11-2023 NOT STARTED NA
4 Floor 31-01-2024 NOT STARTED NA
Electrical Works 30-06-2024 NOT STARTED NA
Concealed Cabling including Plugs & switches 30-06-2024 NOT STARTED NA
Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
PH works 30-11-2024 NOT STARTED NA
Laying of concealed Pipes 30-11-2024 NOT STARTED NA
PH Fittings 30-11-2024 NOT STARTED NA
Overhead Water Tanks 30-11-2024 NOT STARTED NA
Water Supply Connection to all units 30-11-2024 NOT STARTED NA
STP construction and completion 31-01-2025 NOT STARTED NA
Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
Fixation of doors and windows 31-03-2025 NOT STARTED NA
Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA
Site Development 30-06-2022 IN PROGRESS NA
NA NA NA NA
Ground Floor/Stilt Floor 30-11-2022 COMPLETED NA
1 Floor 31-01-2023 COMPLETED NA
2 Floor 31-03-2023 COMPLETED NA
3 Floor 31-05-2023 IN PROGRESS NA
4 Floor 31-07-2023 NOT STARTED NA
NA NA NA NA
Ground Floor/Stilt Floor 31-05-2023 COMPLETED NA
1 Floor 31-07-2023 IN PROGRESS NA
2 Floor 30-09-2023 NOT STARTED NA
3 Floor 30-11-2023 NOT STARTED NA
4 Floor 31-01-2024 NOT STARTED NA
Electrical Works 30-06-2024 NOT STARTED NA
Concealed Cabling including Plugs & switches 30-06-2024 NOT STARTED NA
Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
PH works 30-11-2024 NOT STARTED NA
Laying of concealed Pipes 30-11-2024 NOT STARTED NA
PH Fittings 30-11-2024 NOT STARTED NA
Overhead Water Tanks 30-11-2024 NOT STARTED NA
Water Supply Connection to all units 30-11-2024 NOT STARTED NA
STP construction and completion 31-01-2025 NOT STARTED NA
Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
Fixation of doors and windows 31-03-2025 NOT STARTED NA
Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA
Site Development 30-06-2022 IN PROGRESS NA
NA 15-04-2024 NA NA
Ground Floor/Stilt Floor 30-11-2022 COMPLETED NA
1 Floor 31-01-2023 COMPLETED NA
2 Floor 31-03-2023 COMPLETED NA
3 Floor 31-05-2023 COMPLETED NA
4 Floor 31-07-2023 COMPLETED NA
NA 15-04-2024 NA NA
Ground Floor/Stilt Floor 31-05-2023 COMPLETED NA
1 Floor 31-07-2023 COMPLETED NA
2 Floor 30-09-2023 IN PROGRESS NA
3 Floor 30-11-2023 NOT STARTED NA
4 Floor 31-01-2024 NOT STARTED NA
Electrical Works 30-06-2024 NOT STARTED NA
Concealed Cabling including Plugs & switches 30-06-2024 NOT STARTED NA
Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
PH works 30-11-2024 NOT STARTED NA
Laying of concealed Pipes 30-11-2024 NOT STARTED NA
PH Fittings 30-11-2024 NOT STARTED NA
Overhead Water Tanks 30-11-2024 NOT STARTED NA
Water Supply Connection to all units 30-11-2024 NOT STARTED NA
STP construction and completion 31-01-2025 NOT STARTED NA
Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
Fixation of doors and windows 31-03-2025 NOT STARTED NA
Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA
Site Development 30-06-2022 IN PROGRESS NA
NA 15-04-2024 NA NA
Ground Floor/Stilt Floor 30-11-2022 COMPLETED NA
1 Floor 31-01-2023 COMPLETED NA
2 Floor 31-03-2023 COMPLETED NA
3 Floor 31-05-2023 COMPLETED NA
4 Floor 31-07-2023 COMPLETED NA
NA 15-04-2024 NA NA
Ground Floor/Stilt Floor 31-05-2023 COMPLETED NA
1 Floor 31-07-2023 COMPLETED NA
2 Floor 30-09-2023 COMPLETED NA
3 Floor 30-11-2023 COMPLETED NA
4 Floor 31-01-2024 IN PROGRESS NA
Electrical Works 30-06-2024 IN PROGRESS NA
Concealed Cabling including Plugs & switches 30-06-2024 IN PROGRESS NA
Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
PH works 30-11-2024 IN PROGRESS NA
Laying of concealed Pipes 30-11-2024 COMPLETED NA
PH Fittings 30-11-2024 NOT STARTED NA
Overhead Water Tanks 30-11-2024 NOT STARTED NA
Water Supply Connection to all units 30-11-2024 NOT STARTED NA
STP construction and completion 31-01-2025 NOT STARTED NA
Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
Fixation of doors and windows 31-03-2025 NOT STARTED NA
Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA

Category and no. of units to be developed

:  Residential
:  
:  19
:  
:  
:  
Residential Flats/ House
S. No. Flat No./ House No.

Area in square metres

Ownership
Carpet Area Balcony Area Exclusive Open Terrace Area
1 001 112.08 4.44 0 Promoter
2 002 91.35 3.87 0 Land Owner
3 003 82.80 4.05 0 Land Owner
4 004 68.58 4.03 0 Land Owner
5 101 112.08 4.44 0 Promoter
6 102 91.35 3.87 0 Land Owner
7 103 82.80 4.05 0 Land Owner
8 104 68.58 4.03 0 Land Owner
9 201 112.08 4.44 0 Promoter
10 202 91.35 3.87 0 Land Owner
11 203 82.80 4.05 0 Land Owner
12 204 68.58 4.03 0 Promoter
13 301 112.08 4.44 0 Promoter
14 302 91.35 3.87 0 Promoter
15 303 82.80 4.05 0 Land Owner
16 304 68.58 4.03 0 Promoter
17 401 112.08 4.44 0 Promoter
18 402 91.35 3.87 0 Land Owner
19 403 82.80 4.05 0 Land Owner
Types of garages and parking
House No. Type of Garage/ Parking allotted Serial No., if any Dimension (Length x Width) in Metres Floor area in sq. metres Garage/Parking area cost is included or additional
001 Covered Parking 001 4.26Mx3.04M 12.95 SQM Included
002 Covered Parking 002 4.26Mx3.04M 12.95 SQM Included
003 Covered Parking 003 4.26Mx3.04M 12.95 SQM Included
004 Covered Parking 004 4.26Mx3.04M 12.95 SQM Included
101 Covered Parking 101 4.26Mx3.04M 12.95 SQM Included
102 Covered Parking 102 4.26Mx3.04M 12.95 SQM Included
103 Covered Parking 103 4.26Mx3.04M 12.95 SQM Included
104 Covered Parking 104 4.26Mx3.04M 12.95 SQM Included
201 Covered Parking 201 4.26Mx3.04M 12.95 SQM Included
202 Covered Parking 202 4.26Mx3.04M 12.95 SQM Included
203 Covered Parking 203 4.26Mx3.04M 12.95 SQM Included
204 Covered Parking 204 4.26Mx3.04M 12.95 SQM Included
301 Covered Parking 301 4.26Mx3.04M 12.95 SQM Included
302 Covered Parking 302 4.26Mx3.04M 12.95 SQM Included
303 Covered Parking 303 4.26Mx3.04M 12.95 SQM Included
304 Covered Parking 304 4.26Mx3.04M 12.95 SQM Included
401 Open Parking 401 4.26Mx3.04M 12.95 SQM Included
402 Open Parking 402 4.26Mx3.04M 12.95 SQM Included
403 Open Parking 403 4.26Mx3.04M 12.95 SQM Included
Yes

Facilities to be provided

Particulars of Facilities Status of the facility Brief description of facility
Drinking Water Facility Ground Water Copy of Consent Letter
Fire Fighting Facility Yes STAIRCASE, FIRE EXTINGUISHER, FIRST-AID HOSE REEL, SPRINKLER
Emergency Evacuation Services Yes STAIRCASE
Use of Renewable Energy No
Lift Facility Yes 1 NO. OF LIFT OF OTIS/JHONSON/KONE/ETC. BRAND OF 6 PASSENGER CAPACITY WITH ARD FACILITY
Market Complex No
Community Hall Yes 4.67Mx4.07M i.e. 19 SQM COMMUNITY HALL WITH TILE FLOORING
Gymnasium No
Swimming Pool No
Play Ground No
Park/Garden No
Plantation Area Yes 88.00 SQM
Others(Please Specify) No
Internal Road Yes 124.5 MTR LENGTH & 3.32 MTR WIDE INTERNAL ROAD WITH PAVER BLOCK FLOORING
External Road Yes 9.14 MTR WIDE GOVT. PUBLIC ROAD WITH BLACKTOP FLOORING IS ADJACENT TO THE PROJECT PLOT
Elecricity Supply Yes Copy of Consent Letter
Other Amenities No

Bank Particulars of the Project

  ICICI BANK
  RASULGARH
  731105000550
  ICIC0007311
   View
  1207777
  7752006019

Particulars of Architect/Construction Engineer/Contractor/Chartered Accountant

Name position Address with mobile number and email address Registration number Key real estate projects Is active Effective date
RUPAK PANDA Architect PLOT NO.491/2, SAHID NAGAR, BHUBANESWAR-751007, MOB-9437017543, EMAIL-OFFICE@RPASSOCIATES.IN Reg.No.AR/013/BDA NA
PITABASH PANDA Construction Engineer PLOT NO.491/2, SAHID NAGAR, BHUBANESWAR-751007, MOB-9437017543, EMAIL-OFFICE@RPASSOCIATES.IN Reg.No.105369/4 NA
AMITABH SAHU Chartered Accountant 409/410, Forum Mart, 89, Kharabela Nagar, Bhubaneswar - 751001, MOB-9937006491, EMAIL-bsa.amit@gmail.com M.No.064676 NA

Financial Details

:  436.44996 :   View
  24-04-2025 :  150
:  286.44996 :  0

Documents Attached

Description of Document Option Documents
Fire Safety Certificate Undertaking Attached
Affidavit in Form-A as per clause-l of sub-section-2 of section-4 of the Act Yes Attached
Allotment letter format Yes Attached
Conveyance Deed Format Yes Attached
Affidavit to adopt agreement for sale format as per Rule-8(1) of ORE (R and D) Rules, 2017 Yes Attached
Annual Report 2019-20 Attached
Annual Report 2020-21 Attached
Annual Report 2021-22 Attached
IT Return 2019-20 Attached
IT Return 2020-21 Attached
IT Return 2021-22 Attached
Audit Report 2019-20 Attached
Audit Report 2020-21 Attached
Audit Report 2021-22 Attached


Other documents

“I undertake that the information submitted by me in this application are correct and true to best my knowledge. I also understand that providing false or wrong information is punishable under the Section-60 of the Real Estate (Regulation & Development) Act, 2016. I also further understand that furnishing wrong or false information will lead to rejection of my application registration of the project with forfeiture of registration fee and other charges deposited by me.”
  

Construction Progress

Updated Construction Progress

SL NO. Description Scheduled date of completion Current Status Remarks
1 Site Development 30-06-2022 IN PROGRESS
2 Roof Casting NA NA NA
3 Ground Floor/Stilt Floor 30-11-2022 NOT STARTED NA
4 1 Floor 31-01-2023 NOT STARTED NA
5 2 Floor 31-03-2023 NOT STARTED NA
6 3 Floor 31-05-2023 NOT STARTED NA
7 4 Floor 31-07-2023 NOT STARTED NA
8 Brick Work & Plastering NA NA NA
9 Ground Floor/Stilt Floor 31-05-2023 NOT STARTED NA
10 1 Floor 31-07-2023 NOT STARTED NA
11 2 Floor 30-09-2023 NOT STARTED NA
12 3 Floor 30-11-2023 NOT STARTED NA
13 4 Floor 31-01-2024 NOT STARTED NA
14 Electrical Works 30-06-2024 NOT STARTED NA
15 Concealed Cabling including Plugs & switches 30-06-2024 NOT STARTED NA
16 Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
17 Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
18 PH works 30-11-2024 NOT STARTED NA
19 Laying of concealed Pipes 30-11-2024 NOT STARTED NA
20 PH Fittings 30-11-2024 NOT STARTED NA
21 Overhead Water Tanks 30-11-2024 NOT STARTED NA
22 Water Supply Connection to all units 30-11-2024 NOT STARTED NA
23 STP construction and completion 31-01-2025 NOT STARTED NA
24 Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
25 Fixation of doors and windows 31-03-2025 NOT STARTED NA
26 Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
27 Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA
Updated Changes on 15-10-2022
28 Site Development 30-06-2022 IN PROGRESS NA
29 NA NA NA NA
30 Ground Floor/Stilt Floor 30-11-2022 NOT STARTED NA
31 1 Floor 31-01-2023 NOT STARTED NA
32 2 Floor 31-03-2023 NOT STARTED NA
33 3 Floor 31-05-2023 NOT STARTED NA
34 4 Floor 31-07-2023 NOT STARTED NA
35 NA NA NA NA
36 Ground Floor/Stilt Floor 31-05-2023 NOT STARTED NA
37 1 Floor 31-07-2023 NOT STARTED NA
38 2 Floor 30-09-2023 NOT STARTED NA
39 3 Floor 30-11-2023 NOT STARTED NA
40 4 Floor 31-01-2024 NOT STARTED NA
41 Electrical Works 30-06-2024 NOT STARTED NA
42 Concealed Cabling including Plugs & switches 30-06-2024 NOT STARTED NA
43 Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
44 Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
45 PH works 30-11-2024 NOT STARTED NA
46 Laying of concealed Pipes 30-11-2024 NOT STARTED NA
47 PH Fittings 30-11-2024 NOT STARTED NA
48 Overhead Water Tanks 30-11-2024 NOT STARTED NA
49 Water Supply Connection to all units 30-11-2024 NOT STARTED NA
50 STP construction and completion 31-01-2025 NOT STARTED NA
51 Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
52 Fixation of doors and windows 31-03-2025 NOT STARTED NA
53 Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
54 Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA
Updated Changes on 07-01-2023
55 Site Development 30-06-2022 IN PROGRESS NA
56 NA NA NA NA
57 Ground Floor/Stilt Floor 30-11-2022 NOT STARTED NA
58 1 Floor 31-01-2023 NOT STARTED NA
59 2 Floor 31-03-2023 NOT STARTED NA
60 3 Floor 31-05-2023 NOT STARTED NA
61 4 Floor 31-07-2023 NOT STARTED NA
62 NA NA NA NA
63 Ground Floor/Stilt Floor 31-05-2023 NOT STARTED NA
64 1 Floor 31-07-2023 NOT STARTED NA
65 2 Floor 30-09-2023 NOT STARTED NA
66 3 Floor 30-11-2023 NOT STARTED NA
67 4 Floor 31-01-2024 NOT STARTED NA
68 Electrical Works 30-06-2024 NOT STARTED NA
69 Concealed Cabling including Plugs & switches 30-06-2024 NOT STARTED NA
70 Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
71 Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
72 PH works 30-11-2024 NOT STARTED NA
73 Laying of concealed Pipes 30-11-2024 NOT STARTED NA
74 PH Fittings 30-11-2024 NOT STARTED NA
75 Overhead Water Tanks 30-11-2024 NOT STARTED NA
76 Water Supply Connection to all units 30-11-2024 NOT STARTED NA
77 STP construction and completion 31-01-2025 NOT STARTED NA
78 Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
79 Fixation of doors and windows 31-03-2025 NOT STARTED NA
80 Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
81 Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA
Updated Changes on 08-04-2023
82 Site Development 30-06-2022 IN PROGRESS NA
83 NA NA NA NA
84 Ground Floor/Stilt Floor 30-11-2022 NOT STARTED NA
85 1 Floor 31-01-2023 NOT STARTED NA
86 2 Floor 31-03-2023 NOT STARTED NA
87 3 Floor 31-05-2023 NOT STARTED NA
88 4 Floor 31-07-2023 NOT STARTED NA
89 NA NA NA NA
90 Ground Floor/Stilt Floor 31-05-2023 NOT STARTED NA
91 1 Floor 31-07-2023 NOT STARTED NA
92 2 Floor 30-09-2023 NOT STARTED NA
93 3 Floor 30-11-2023 NOT STARTED NA
94 4 Floor 31-01-2024 NOT STARTED NA
95 Electrical Works 30-06-2024 NOT STARTED NA
96 Concealed Cabling including Plugs & switches 30-06-2024 NOT STARTED NA
97 Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
98 Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
99 PH works 30-11-2024 NOT STARTED NA
100 Laying of concealed Pipes 30-11-2024 NOT STARTED NA
101 PH Fittings 30-11-2024 NOT STARTED NA
102 Overhead Water Tanks 30-11-2024 NOT STARTED NA
103 Water Supply Connection to all units 30-11-2024 NOT STARTED NA
104 STP construction and completion 31-01-2025 NOT STARTED NA
105 Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
106 Fixation of doors and windows 31-03-2025 NOT STARTED NA
107 Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
108 Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA
Updated Changes on 15-07-2023
109 Site Development 30-06-2022 IN PROGRESS NA
110 NA NA NA NA
111 Ground Floor/Stilt Floor 30-11-2022 IN PROGRESS NA
112 1 Floor 31-01-2023 NOT STARTED NA
113 2 Floor 31-03-2023 NOT STARTED NA
114 3 Floor 31-05-2023 NOT STARTED NA
115 4 Floor 31-07-2023 NOT STARTED NA
116 NA NA NA NA
117 Ground Floor/Stilt Floor 31-05-2023 NOT STARTED NA
118 1 Floor 31-07-2023 NOT STARTED NA
119 2 Floor 30-09-2023 NOT STARTED NA
120 3 Floor 30-11-2023 NOT STARTED NA
121 4 Floor 31-01-2024 NOT STARTED NA
122 Electrical Works 30-06-2024 NOT STARTED NA
123 Concealed Cabling including Plugs & switches 30-06-2024 NOT STARTED NA
124 Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
125 Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
126 PH works 30-11-2024 NOT STARTED NA
127 Laying of concealed Pipes 30-11-2024 NOT STARTED NA
128 PH Fittings 30-11-2024 NOT STARTED NA
129 Overhead Water Tanks 30-11-2024 NOT STARTED NA
130 Water Supply Connection to all units 30-11-2024 NOT STARTED NA
131 STP construction and completion 31-01-2025 NOT STARTED NA
132 Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
133 Fixation of doors and windows 31-03-2025 NOT STARTED NA
134 Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
135 Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA
Updated Changes on 07-10-2023
136 Site Development 30-06-2022 IN PROGRESS NA
137 NA NA NA NA
138 Ground Floor/Stilt Floor 30-11-2022 COMPLETED NA
139 1 Floor 31-01-2023 COMPLETED NA
140 2 Floor 31-03-2023 COMPLETED NA
141 3 Floor 31-05-2023 NOT STARTED NA
142 4 Floor 31-07-2023 NOT STARTED NA
143 NA NA NA NA
144 Ground Floor/Stilt Floor 31-05-2023 NOT STARTED NA
145 1 Floor 31-07-2023 NOT STARTED NA
146 2 Floor 30-09-2023 NOT STARTED NA
147 3 Floor 30-11-2023 NOT STARTED NA
148 4 Floor 31-01-2024 NOT STARTED NA
149 Electrical Works 30-06-2024 NOT STARTED NA
150 Concealed Cabling including Plugs & switches 30-06-2024 NOT STARTED NA
151 Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
152 Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
153 PH works 30-11-2024 NOT STARTED NA
154 Laying of concealed Pipes 30-11-2024 NOT STARTED NA
155 PH Fittings 30-11-2024 NOT STARTED NA
156 Overhead Water Tanks 30-11-2024 NOT STARTED NA
157 Water Supply Connection to all units 30-11-2024 NOT STARTED NA
158 STP construction and completion 31-01-2025 NOT STARTED NA
159 Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
160 Fixation of doors and windows 31-03-2025 NOT STARTED NA
161 Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
162 Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA
Updated Changes on 06-01-2024
163 Site Development 30-06-2022 IN PROGRESS NA
164 NA NA NA NA
165 Ground Floor/Stilt Floor 30-11-2022 COMPLETED NA
166 1 Floor 31-01-2023 COMPLETED NA
167 2 Floor 31-03-2023 COMPLETED NA
168 3 Floor 31-05-2023 IN PROGRESS NA
169 4 Floor 31-07-2023 NOT STARTED NA
170 NA NA NA NA
171 Ground Floor/Stilt Floor 31-05-2023 COMPLETED NA
172 1 Floor 31-07-2023 IN PROGRESS NA
173 2 Floor 30-09-2023 NOT STARTED NA
174 3 Floor 30-11-2023 NOT STARTED NA
175 4 Floor 31-01-2024 NOT STARTED NA
176 Electrical Works 30-06-2024 NOT STARTED NA
177 Concealed Cabling including Plugs & switches 30-06-2024 NOT STARTED NA
178 Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
179 Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
180 PH works 30-11-2024 NOT STARTED NA
181 Laying of concealed Pipes 30-11-2024 NOT STARTED NA
182 PH Fittings 30-11-2024 NOT STARTED NA
183 Overhead Water Tanks 30-11-2024 NOT STARTED NA
184 Water Supply Connection to all units 30-11-2024 NOT STARTED NA
185 STP construction and completion 31-01-2025 NOT STARTED NA
186 Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
187 Fixation of doors and windows 31-03-2025 NOT STARTED NA
188 Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
189 Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA
Updated Changes on 15-04-2024
190 Site Development 30-06-2022 IN PROGRESS NA
191 NA 15-04-2024 NA NA
192 Ground Floor/Stilt Floor 30-11-2022 COMPLETED NA
193 1 Floor 31-01-2023 COMPLETED NA
194 2 Floor 31-03-2023 COMPLETED NA
195 3 Floor 31-05-2023 COMPLETED NA
196 4 Floor 31-07-2023 COMPLETED NA
197 NA 15-04-2024 NA NA
198 Ground Floor/Stilt Floor 31-05-2023 COMPLETED NA
199 1 Floor 31-07-2023 COMPLETED NA
200 2 Floor 30-09-2023 IN PROGRESS NA
201 3 Floor 30-11-2023 NOT STARTED NA
202 4 Floor 31-01-2024 NOT STARTED NA
203 Electrical Works 30-06-2024 NOT STARTED NA
204 Concealed Cabling including Plugs & switches 30-06-2024 NOT STARTED NA
205 Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
206 Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
207 PH works 30-11-2024 NOT STARTED NA
208 Laying of concealed Pipes 30-11-2024 NOT STARTED NA
209 PH Fittings 30-11-2024 NOT STARTED NA
210 Overhead Water Tanks 30-11-2024 NOT STARTED NA
211 Water Supply Connection to all units 30-11-2024 NOT STARTED NA
212 STP construction and completion 31-01-2025 NOT STARTED NA
213 Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
214 Fixation of doors and windows 31-03-2025 NOT STARTED NA
215 Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
216 Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA
Updated Changes on 10-07-2024
217 Site Development 30-06-2022 IN PROGRESS NA
218 NA 15-04-2024 NA NA
219 Ground Floor/Stilt Floor 30-11-2022 COMPLETED NA
220 1 Floor 31-01-2023 COMPLETED NA
221 2 Floor 31-03-2023 COMPLETED NA
222 3 Floor 31-05-2023 COMPLETED NA
223 4 Floor 31-07-2023 COMPLETED NA
224 NA 15-04-2024 NA NA
225 Ground Floor/Stilt Floor 31-05-2023 COMPLETED NA
226 1 Floor 31-07-2023 COMPLETED NA
227 2 Floor 30-09-2023 COMPLETED NA
228 3 Floor 30-11-2023 COMPLETED NA
229 4 Floor 31-01-2024 IN PROGRESS NA
230 Electrical Works 30-06-2024 IN PROGRESS NA
231 Concealed Cabling including Plugs & switches 30-06-2024 IN PROGRESS NA
232 Installation & Charging of Transformer 30-06-2024 NOT STARTED NA
233 Connection to Flats/Apartments 30-06-2024 NOT STARTED NA
234 PH works 30-11-2024 IN PROGRESS NA
235 Laying of concealed Pipes 30-11-2024 COMPLETED NA
236 PH Fittings 30-11-2024 NOT STARTED NA
237 Overhead Water Tanks 30-11-2024 NOT STARTED NA
238 Water Supply Connection to all units 30-11-2024 NOT STARTED NA
239 STP construction and completion 31-01-2025 NOT STARTED NA
240 Distempering & Colouring of all units and exteriors 28-02-2025 NOT STARTED NA
241 Fixation of doors and windows 31-03-2025 NOT STARTED NA
242 Scheduled Date of handing over possession 30-04-2025 NOT STARTED NA
243 Development of common areas, parks, gardens etc 31-03-2025 NOT STARTED NA

Booking Status

Residential Flats/ House
S. No. Flat No./ House No.

Area in square metres

Ownership Status
Carpet Area Balcony Area Exclusive Open Terrace Area
1 001 112.08 4.44 0 Promoter
2 002 91.35 3.87 0 Land Owner
3 003 82.80 4.05 0 Land Owner
4 004 68.58 4.03 0 Land Owner
5 101 112.08 4.44 0 Promoter
6 102 91.35 3.87 0 Land Owner
7 103 82.80 4.05 0 Land Owner
8 104 68.58 4.03 0 Land Owner
9 201 112.08 4.44 0 Promoter
10 202 91.35 3.87 0 Land Owner
11 203 82.80 4.05 0 Land Owner
12 204 68.58 4.03 0 Promoter
13 301 112.08 4.44 0 Promoter
14 302 91.35 3.87 0 Promoter
15 303 82.80 4.05 0 Land Owner
16 304 68.58 4.03 0 Promoter
17 401 112.08 4.44 0 Promoter
18 402 91.35 3.87 0 Land Owner
19 403 82.80 4.05 0 Land Owner

Financial Status

SL No. Funds Collected from the Allottees Funds Borrowed from Financial Institutions Funds Employed from Own Sources Expenditure As On Date Status
1 0 0 9400000 9400000 30-09-2022 IN PROGRESS
2 0 0 359525 9759525 31-12-2022 IN PROGRESS
3 9475012 0 9759525 15405463 31-03-2023 IN PROGRESS
4 11795012 0 9759525 17781463 30-06-2023 IN PROGRESS
5 11795012 0 12868601 20890539 30-09-2023 IN PROGRESS
6 17314012 0 12868601 24397539 31-12-2023 IN PROGRESS
7 19667155 0 14062488 27490426 31-03-2024 IN PROGRESS
8 21880870 0 14062488 29038426 30-06-2024 IN PROGRESS

Updated Conditions of building plan approval

Sl. No. Description of Conditions Schedule date of compliance Present Status
1 Parking space measuring 430.77 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 11-06-2022 NOT STARTED
2 The land over which construction is proposed is accessible by an approved means of access of 9.14 M (Nine point One Four) in width. 11-06-2022 NOT STARTED
3 Obtain, wherever applicable, from the competent Authority permissions/clearance required in connection with the proposed work; 11-06-2022 NOT STARTED
4 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 11-06-2022 NOT STARTED
5 Register the said Apartment project over scheduled property under the Real Estate(Regulation & Development)-Act-2016. 11-06-2022 IN PROGRESS
6 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC from PHED vide Letter No- 14412 dt. 17.11.2021 & AAI NOC Vide Letter No-BHUB/EAST/B/072321/564459, dt. 12/08/2021. 11-06-2022 WILL COMPLY AS PER THE PERMISSION
7 The applicant shall obtain NOC from the Central Ground Water Board towards extraction of ground water before start of construction. 11-06-2022 NOT STARTED
8 Storm water from the premises of roof top shall be conveyed and discharged to the rainwater recharging pits as per ODA (Planning & Building Standards) Rules, 2020. 11-06-2022 NOT STARTED
9 Plantation as required under the provision under Rule 30 of ODA (Planning & Building Standards) Rules, 2020 shall be strictly adhered. 11-06-2022 NOT STARTED
10 The applicant shall obtain EIDP towards development of Infrastructure & clearance from Engineering Wing of BMC before obtaining Occupancy Certificate. 11-06-2022 NOT STARTED
Updated Changes on 15-10-2022
11 Parking space measuring 430.77 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 11-06-2022 NOT STARTED
12 The land over which construction is proposed is accessible by an approved means of access of 9.14 M (Nine point One Four) in width. 11-06-2022 IN PROGRESS
13 Obtain, wherever applicable, from the competent Authority permissions/clearance required in connection with the proposed work; 11-06-2022 NOT STARTED
14 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 11-06-2022 NOT STARTED
15 Register the said Apartment project over scheduled property under the Real Estate(Regulation & Development)-Act-2016. 11-06-2022 IN PROGRESS
16 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC from PHED vide Letter No- 14412 dt. 17.11.2021 & AAI NOC Vide Letter No-BHUB/EAST/B/072321/564459, dt. 12/08/2021. 11-06-2022 WILL COMPLY AS PER THE PERMISSION
17 The applicant shall obtain NOC from the Central Ground Water Board towards extraction of ground water before start of construction. 11-06-2022 NOT STARTED
18 Storm water from the premises of roof top shall be conveyed and discharged to the rainwater recharging pits as per ODA (Planning & Building Standards) Rules, 2020. 11-06-2022 NOT STARTED
19 Plantation as required under the provision under Rule 30 of ODA (Planning & Building Standards) Rules, 2020 shall be strictly adhered. 11-06-2022 NOT STARTED
20 The applicant shall obtain EIDP towards development of Infrastructure & clearance from Engineering Wing of BMC before obtaining Occupancy Certificate. 11-06-2022 NOT STARTED
Updated Changes on 07-01-2023
21 Parking space measuring 430.77 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 11-06-2022 NOT STARTED
22 The land over which construction is proposed is accessible by an approved means of access of 9.14 M (Nine point One Four) in width. 11-06-2022 IN PROGRESS
23 Obtain, wherever applicable, from the competent Authority permissions/clearance required in connection with the proposed work; 11-06-2022 NOT STARTED
24 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 11-06-2022 NOT STARTED
25 Register the said Apartment project over scheduled property under the Real Estate(Regulation & Development)-Act-2016. 11-06-2022 IN PROGRESS
26 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC from PHED vide Letter No- 14412 dt. 17.11.2021 & AAI NOC Vide Letter No-BHUB/EAST/B/072321/564459, dt. 12/08/2021. 11-06-2022 WILL COMPLY AS PER THE PERMISSION
27 The applicant shall obtain NOC from the Central Ground Water Board towards extraction of ground water before start of construction. 11-06-2022 NOT STARTED
28 Storm water from the premises of roof top shall be conveyed and discharged to the rainwater recharging pits as per ODA (Planning & Building Standards) Rules, 2020. 11-06-2022 NOT STARTED
29 Plantation as required under the provision under Rule 30 of ODA (Planning & Building Standards) Rules, 2020 shall be strictly adhered. 11-06-2022 NOT STARTED
30 The applicant shall obtain EIDP towards development of Infrastructure & clearance from Engineering Wing of BMC before obtaining Occupancy Certificate. 11-06-2022 NOT STARTED
Updated Changes on 08-04-2023
31 Parking space measuring 430.77 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 11-06-2022 NOT STARTED
32 The land over which construction is proposed is accessible by an approved means of access of 9.14 M (Nine point One Four) in width. 11-06-2022 COMPLETED
33 Obtain, wherever applicable, from the competent Authority permissions/clearance required in connection with the proposed work; 11-06-2022 NOT STARTED
34 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 11-06-2022 NOT STARTED
35 Register the said Apartment project over scheduled property under the Real Estate(Regulation & Development)-Act-2016. 11-06-2022 IN PROGRESS
36 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC from PHED vide Letter No- 14412 dt. 17.11.2021 & AAI NOC Vide Letter No-BHUB/EAST/B/072321/564459, dt. 12/08/2021. 11-06-2022 WILL COMPLY AS PER THE PERMISSION
37 The applicant shall obtain NOC from the Central Ground Water Board towards extraction of ground water before start of construction. 11-06-2022 NOT STARTED
38 Storm water from the premises of roof top shall be conveyed and discharged to the rainwater recharging pits as per ODA (Planning & Building Standards) Rules, 2020. 11-06-2022 NOT STARTED
39 Plantation as required under the provision under Rule 30 of ODA (Planning & Building Standards) Rules, 2020 shall be strictly adhered. 11-06-2022 NOT STARTED
40 The applicant shall obtain EIDP towards development of Infrastructure & clearance from Engineering Wing of BMC before obtaining Occupancy Certificate. 11-06-2022 NOT STARTED
Updated Changes on 15-07-2023
41 Parking space measuring 430.77 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 11-06-2022 NOT STARTED
42 The land over which construction is proposed is accessible by an approved means of access of 9.14 M (Nine point One Four) in width. 11-06-2022 COMPLETED
43 Obtain, wherever applicable, from the competent Authority permissions/clearance required in connection with the proposed work; 11-06-2022 NOT STARTED
44 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 11-06-2022 NOT STARTED
45 Register the said Apartment project over scheduled property under the Real Estate(Regulation & Development)-Act-2016. 11-06-2022 COMPLETED
46 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC from PHED vide Letter No- 14412 dt. 17.11.2021 & AAI NOC Vide Letter No-BHUB/EAST/B/072321/564459, dt. 12/08/2021. 11-06-2022 WILL COMPLY AS PER THE PERMISSION
47 The applicant shall obtain NOC from the Central Ground Water Board towards extraction of ground water before start of construction. 11-06-2022 NOT STARTED
48 Storm water from the premises of roof top shall be conveyed and discharged to the rainwater recharging pits as per ODA (Planning & Building Standards) Rules, 2020. 11-06-2022 NOT STARTED
49 Plantation as required under the provision under Rule 30 of ODA (Planning & Building Standards) Rules, 2020 shall be strictly adhered. 11-06-2022 NOT STARTED
50 The applicant shall obtain EIDP towards development of Infrastructure & clearance from Engineering Wing of BMC before obtaining Occupancy Certificate. 11-06-2022 NOT STARTED
Updated Changes on 07-10-2023
51 Parking space measuring 430.77 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 11-06-2022 NOT STARTED
52 The land over which construction is proposed is accessible by an approved means of access of 9.14 M (Nine point One Four) in width. 11-06-2022 COMPLETED
53 Obtain, wherever applicable, from the competent Authority permissions/clearance required in connection with the proposed work; 11-06-2022 NOT STARTED
54 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 11-06-2022 NOT STARTED
55 Register the said Apartment project over scheduled property under the Real Estate(Regulation & Development)-Act-2016. 11-06-2022 COMPLETED
56 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC from PHED vide Letter No- 14412 dt. 17.11.2021 & AAI NOC Vide Letter No-BHUB/EAST/B/072321/564459, dt. 12/08/2021. 11-06-2022 WILL COMPLY AS PER THE PERMISSION
57 The applicant shall obtain NOC from the Central Ground Water Board towards extraction of ground water before start of construction. 11-06-2022 NOT STARTED
58 Storm water from the premises of roof top shall be conveyed and discharged to the rainwater recharging pits as per ODA (Planning & Building Standards) Rules, 2020. 11-06-2022 NOT STARTED
59 Plantation as required under the provision under Rule 30 of ODA (Planning & Building Standards) Rules, 2020 shall be strictly adhered. 11-06-2022 NOT STARTED
60 The applicant shall obtain EIDP towards development of Infrastructure & clearance from Engineering Wing of BMC before obtaining Occupancy Certificate. 11-06-2022 NOT STARTED
Updated Changes on 06-01-2024
61 Parking space measuring 430.77 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 11-06-2022 IN PROGRESS
62 The land over which construction is proposed is accessible by an approved means of access of 9.14 M (Nine point One Four) in width. 11-06-2022 COMPLETED
63 Obtain, wherever applicable, from the competent Authority permissions/clearance required in connection with the proposed work; 11-06-2022 NOT STARTED
64 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 11-06-2022 NOT STARTED
65 Register the said Apartment project over scheduled property under the Real Estate(Regulation & Development)-Act-2016. 11-06-2022 COMPLETED
66 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC from PHED vide Letter No- 14412 dt. 17.11.2021 & AAI NOC Vide Letter No-BHUB/EAST/B/072321/564459, dt. 12/08/2021. 11-06-2022 WILL COMPLY AS PER THE PERMISSION
67 The applicant shall obtain NOC from the Central Ground Water Board towards extraction of ground water before start of construction. 11-06-2022 NOT STARTED
68 Storm water from the premises of roof top shall be conveyed and discharged to the rainwater recharging pits as per ODA (Planning & Building Standards) Rules, 2020. 11-06-2022 NOT STARTED
69 Plantation as required under the provision under Rule 30 of ODA (Planning & Building Standards) Rules, 2020 shall be strictly adhered. 11-06-2022 NOT STARTED
70 The applicant shall obtain EIDP towards development of Infrastructure & clearance from Engineering Wing of BMC before obtaining Occupancy Certificate. 11-06-2022 NOT STARTED
Updated Changes on 15-04-2024
71 Parking space measuring 430.77 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 11-06-2022 IN PROGRESS
72 The land over which construction is proposed is accessible by an approved means of access of 9.14 M (Nine point One Four) in width. 11-06-2022 COMPLETED
73 Obtain, wherever applicable, from the competent Authority permissions/clearance required in connection with the proposed work; 11-06-2022 NOT STARTED
74 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 11-06-2022 NOT STARTED
75 Register the said Apartment project over scheduled property under the Real Estate(Regulation & Development)-Act-2016. 11-06-2022 COMPLETED
76 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC from PHED vide Letter No- 14412 dt. 17.11.2021 & AAI NOC Vide Letter No-BHUB/EAST/B/072321/564459, dt. 12/08/2021. 11-06-2022 WILL COMPLY AS PER THE PERMISSION
77 The applicant shall obtain NOC from the Central Ground Water Board towards extraction of ground water before start of construction. 11-06-2022 NOT STARTED
78 Storm water from the premises of roof top shall be conveyed and discharged to the rainwater recharging pits as per ODA (Planning & Building Standards) Rules, 2020. 11-06-2022 NOT STARTED
79 Plantation as required under the provision under Rule 30 of ODA (Planning & Building Standards) Rules, 2020 shall be strictly adhered. 11-06-2022 NOT STARTED
80 The applicant shall obtain EIDP towards development of Infrastructure & clearance from Engineering Wing of BMC before obtaining Occupancy Certificate. 11-06-2022 NOT STARTED
Updated Changes on 10-07-2024
81 Parking space measuring 430.77 Sqm as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose and shall not be partitioned/closed in any manner. 11-06-2022 IN PROGRESS
82 The land over which construction is proposed is accessible by an approved means of access of 9.14 M (Nine point One Four) in width. 11-06-2022 COMPLETED
83 Obtain, wherever applicable, from the competent Authority permissions/clearance required in connection with the proposed work; 11-06-2022 NOT STARTED
84 Obtain an Occupancy Certificate from the Authority prior to occupation of building in full or part. 11-06-2022 NOT STARTED
85 Register the said Apartment project over scheduled property under the Real Estate(Regulation & Development)-Act-2016. 11-06-2022 COMPLETED
86 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC from PHED vide Letter No- 14412 dt. 17.11.2021 & AAI NOC Vide Letter No-BHUB/EAST/B/072321/564459, dt. 12/08/2021. 11-06-2022 WILL COMPLY AS PER THE PERMISSION
87 The applicant shall obtain NOC from the Central Ground Water Board towards extraction of ground water before start of construction. 11-06-2022 NOT STARTED
88 Storm water from the premises of roof top shall be conveyed and discharged to the rainwater recharging pits as per ODA (Planning & Building Standards) Rules, 2020. 11-06-2022 NOT STARTED
89 Plantation as required under the provision under Rule 30 of ODA (Planning & Building Standards) Rules, 2020 shall be strictly adhered. 11-06-2022 NOT STARTED
90 The applicant shall obtain EIDP towards development of Infrastructure & clearance from Engineering Wing of BMC before obtaining Occupancy Certificate. 11-06-2022 IN PROGRESS

Updated Project Documents

Sl. No. Title of the document Upload Document
1 PROFORMA-I,II WITH COVER LETTER (QPR: JUL-2022 TO SEPT-2022)
2 BANK STATEMENT
3 QPR Submission Letter (Quarter: Oct, 2022 to Dec, 2022)
4 Proforma-I (Quarter: Oct, 2022 to Dec, 2022)
5 Proforma-II (Quarter: Oct, 2022 to Dec, 2022)
6 Bank Statement (Quarter: Oct, 2022 to Dec, 2022)
7 Proforma-I (Quarter: JAN, 2023 to MAR, 2023)
8 Proforma-II (Quarter: JAN, 2023 to MAR, 2023)
9 Bank Statement
10 SALE AGREEMENTS
11 PROFORMA-I & II(APR-2023 TO JUN-2023)
12 ANNUAL AUDIT CERTIFICATE
13 BANK STATEMENT
14 PROFORMA-I & II(JUL-2023 TO SEPT-2023)
15 PROFORMA-II(JUL-2023 TO SEPT-2023)
16 BANK STATEMENTS
17 PROFORMA-I (OCT-2023 -DEC-2023)
18 PROFORMA-II (OCT-2023 -DEC-2023)
19 BANK STATEMENT (OCT-2023 -DEC-2023)
20 PROFORMA-1 QUARTER ENDED MAR, 2024
21 PROFORMA-2 QUARTER ENDED MAR, 2024
22 AAC FY 2023-24
23 BANK STATEMENT 70% QUARTER ENDED MAR, 2024
24 BANK STATEMENT 100% QUARTER ENDED MAR, 2024
25 PROFORMA-I (APR, 2024 TO JUN, 2024)
26 PROFORMA-II (APR, 2024 TO JUN, 2024)
27 BANK STATEMENT (APR, 2024 TO JUN, 2024)
:  AMARESH PARIDA :  
NA :  AWNPP5239R
:PAN Card :  amareshnsui.odisha@gmail.com
:  B.TECH :  9938212981
:  10 YEARS OF EXPERIENCE
:  Yes :  NA
:  MANAS KUMAR PAL :  
NA :  BCLPP4414K
:PAN Card :  manasindus@gmail.com
:  B.TECH :  9438840739
:  2 YEARS OF EXPERIENCE
:  Yes :  NA

Particulars of Architect/Construction Engineer/Contractor/Chartered Accountant

Name position Address with mobile number and email address Registration number Key real estate projects Is active Effective date
RUPAK PANDA Architect PLOT NO.491/2, SAHID NAGAR, BHUBANESWAR-751007, MOB-9437017543, EMAIL-OFFICE@RPASSOCIATES.IN Reg.No.AR/013/BDA NA
PITABASH PANDA Construction Engineer PLOT NO.491/2, SAHID NAGAR, BHUBANESWAR-751007, MOB-9437017543, EMAIL-OFFICE@RPASSOCIATES.IN Reg.No.105369/4 NA
AMITABH SAHU Chartered Accountant 409/410, Forum Mart, 89, Kharabela Nagar, Bhubaneswar - 751001, MOB-9937006491, EMAIL-bsa.amit@gmail.com M.No.064676 NA

Updated Units

House No. Type of Garage/ Parking allotted Serial No., if any Dimension (Length x Width) in Metres Floor area in sq. metres Garage/Parking area cost is included or additional
Updated Changes
001 Covered Parking 001 4.26Mx3.04M 12.95 SQM Included
002 Covered Parking 002 4.26Mx3.04M 12.95 SQM Included
003 Covered Parking 003 4.26Mx3.04M 12.95 SQM Included
004 Covered Parking 004 4.26Mx3.04M 12.95 SQM Included
101 Covered Parking 101 4.26Mx3.04M 12.95 SQM Included
102 Covered Parking 102 4.26Mx3.04M 12.95 SQM Included
103 Covered Parking 103 4.26Mx3.04M 12.95 SQM Included
104 Covered Parking 104 4.26Mx3.04M 12.95 SQM Included
201 Covered Parking 201 4.26Mx3.04M 12.95 SQM Included
202 Covered Parking 202 4.26Mx3.04M 12.95 SQM Included
203 Covered Parking 203 4.26Mx3.04M 12.95 SQM Included
204 Covered Parking 204 4.26Mx3.04M 12.95 SQM Included
301 Covered Parking 301 4.26Mx3.04M 12.95 SQM Included
302 Covered Parking 302 4.26Mx3.04M 12.95 SQM Included
303 Covered Parking 303 4.26Mx3.04M 12.95 SQM Included
304 Covered Parking 304 4.26Mx3.04M 12.95 SQM Included
401 Open Parking 401 4.26Mx3.04M 12.95 SQM Included
402 Open Parking 402 4.26Mx3.04M 12.95 SQM Included
403 Open Parking 403 4.26Mx3.04M 12.95 SQM Included