Generated by pacms.orera.in on date: 2024-05-21
: M/S. KHUSHI REALCON Pvt. Ltd | : Private Company |
: U45201OR2012PTC015524 | :View |
NA | : S-2/A-42, 43 & 44, MANCHESWAR INDUSTRIAL ESTATE, BHUBANESWAR - 751010 |
: S-2/A-42, 43 & 44, Mancheswar Industrial Estate, Bhubaneswar, Odisha- 751010. | : khushirealconbbsr@gmail.com |
: 2581919 | : 9937261000 |
: AAECK8235G | :View |
: 10 YEARS | : NA |
NA |
: PRADEEP KUMAR THACKER | : |
: Director | : AAKPT7887L |
:PAN Card | : khushirealconbbsr@gmail.com |
: MBA | : 9937261000 |
: 15 YEARS IN REAL ESTATE BUSINESS | |
: Yes | : NA |
: GAURAV AGRAWAL | : |
: Director | : AKGPA9696N |
:PAN Card | : khushirealconbbsr@gmail.com |
: MBA | : 9937261000 |
: 10 YEARS IN REAL ESTATE BUSINESS | |
: Yes | : NA |
: New | : KHUSHI CAPELLA (PHASE- I) |
: Residential | : ( Residential Project, (Block-A)- 2B+G+23, (Block-B)- 2B+S+5, No. of Units- 242 ) |
: Khordha | : Bhubaneswar |
: 752101 | : Urban Local Body |
: BHUBANESWAR MUNICIPAL CORPORATION | |
: RESIDENTIAL APARTMENT BUILDING WITH TOWER 1 (BLOCK-A) - 2B+G+23 TOWER 2 (BLOCK-B) - 2B+S+22 | : NA |
: Yes |
Serial No. | Particulars of the Person | Land/Plot Details | Share of the Person | Document Attached |
---|---|---|---|---|
1 | BISWAJIT SAHA | Plot No. 211/1746 (Khata No. 56/106) & Plot No. 124 (Khata No. 352/101) | 40% | Agreement Copy |
View | View |
Download site plan | 30-03-2025 |
Sl. No. | Description of Conditions | Schedule date of compliance | Present Status |
---|---|---|---|
1 | The building shall be used exclusively for purpose and use shall not be changed to any other use without prior approval of this Authority. | 30-06-2026 | YET TO START |
2 | Storm water from the premises of roof top shall be conveyed and discharged to the rain water recharging pits as per Rule - 47of ODA (Planning & Building Standards) Rules, 2020. | 30-06-2026 | YET TO START |
3 | The space which is meant for parking shall not be changed to any other use and shall not be partitioned/closed in any manner. | 30-06-2026 | YET TO START |
4 | No storm water/water shall be discharged to the public road/public premises and other adjoining plots. | 30-06-2026 | YET TO START |
5 | The Land in Question will be in lawful ownership and peaceful possession of the applicant | 30-06-2026 | YET TO START |
6 | A minimum of 30% parking space shall have facilities to enable Electric Vehicle Charging points | 30-06-2026 | YET TO START |
7 | Plantation shall be strictly adhered as per rule 30 of Planning & Building Standards | 30-06-2026 | YET TO START |
8 | Wherever tests of any material are made to ensure conformity, records of the test data shall be kept available for inspection during construction phase | 30-06-2026 | YET TO START |
9 | Ensure Structural Safety & Stability | 30-06-2026 | YET TO START |
10 | Parking space measuring 13594.10 Sqmt.as shown in the approved plan shall be left for parking of vehicles and no part of it will be used for any other purpose | 30-06-2026 | YET TO START |
11 | The permission granted under these regulations shall remain valid upto Three Years from the date of issue .However the permission shall have to be revalidated before the expiry of the above period on payment of such fee as may be prescribed under rules and such revalidation shall be valid for one year | 30-03-2025 | Permission Recd. from Authorities |
: Yes | : View |
Point No. | Latitude | Longitude |
---|---|---|
1 | 20°20'01.1"N | 85°53'00.2"E |
2 | 20°20'01.5"N | 85°52'59.4"E |
3 | 20°20'02.5"N | 85°52'56.2"E |
4 | 20°20'01.9"N | 85°52'55.5"E |
5 | 20°20'02.7"N | 85°52'54.3"E |
6 | 20°20'04.3"N | 85°52'55.7"E |
7 | 20°20'03.4"N | 85°52'57.0"E |
8 | 20°20'03.5"N | 85°52'57.0"E |
9 | 20°20'03.9"N | 85°52'56.6"E |
10 | 20°20'04.8"N | 85°52'57.5"E |
11 | 20°20'03.9"N | 85°52'58.7"°E |
12 | 20°20'05.1"N | 85°52'59.7"°E |
13 | 20°20'04.8"N | 85°52'59.8"E |
14 | 20°20'02.0"N | 85°52'58.8"E |
15 | 20°20'03.1"N | 85°52'60.0"E |
16 | 20°20'02.8"N | 85°52'57.9"E |
Description* | Scheduled date of completion | Current Status | Site Images |
---|---|---|---|
Site Development | 30-09-2022 | ON GOING | |
Roof Casting | NA | NA | NA |
Ground Floor/Stilt Floor | 31-03-2023 | YET TO START | NA |
1 Floor | 31-06-2023 | YET TO START | NA |
2 Floor | 28-09-2023 | YET TO START | NA |
3 Floor | 30-01-2024 | YET TO START | NA |
4 Floor | 31-05-2024 | YET TO START | NA |
5 Floor | 30-06-2024 | YET TO START | NA |
6 Floor | 31-07-2024 | YET TO START | NA |
7 Floor | 31-08-2024 | YET TO START | NA |
8 Floor | 30-09-2024 | YET TO START | NA |
9 Floor | 31-10-2024 | YET TO START | NA |
10 Floor | 30-11-2024 | YET TO START | NA |
11 Floor | 31-12-2024 | YET TO START | NA |
12 Floor | 31-01-2025 | YET TO START | NA |
13 Floor | 29-02-2025 | YET TO START | NA |
14 Floor | 31-03-2025 | YET TO START | NA |
15 Floor | 30-04-2025 | YET TO START | NA |
16 Floor | 31-05-2025 | YET TO START | NA |
17 Floor | 30-06-2025 | YET TO START | NA |
18 Floor | 31-07-2025 | YET TO START | NA |
19 Floor | 31-05-2025 | YET TO START | NA |
20 Floor | 31-07-2025 | YET TO START | NA |
21 Floor | 31-08-2025 | YET TO START | NA |
22 Floor | 30-09-2025 | YET TO START | NA |
23 Floor | 31-10-2025 | YET TO START | NA |
Brick Work & Plastering | NA | NA | NA |
Ground Floor/Stilt Floor | 30-06-2024 | YET TO START | NA |
1 Floor | 31-07-2024 | YET TO START | NA |
2 Floor | 31-08-2024 | YET TO START | NA |
3 Floor | 30-09-2024 | YET TO START | NA |
4 Floor | 31-10-2024 | YET TO START | NA |
5 Floor | 30-11-2024 | YET TO START | NA |
6 Floor | 31-12-2024 | YET TO START | NA |
7 Floor | 31-01-2025 | YET TO START | NA |
8 Floor | 29-02-2025 | YET TO START | NA |
9 Floor | 31-03-2025 | YET TO START | NA |
10 Floor | 30-04-2025 | YET TO START | NA |
11 Floor | 31-05-2025 | YET TO START | NA |
12 Floor | 30-06-2025 | YET TO START | NA |
13 Floor | 31-07-2025 | YET TO START | NA |
14 Floor | 31-08-2025 | YET TO START | NA |
15 Floor | 30-09-2025 | YET TO START | NA |
16 Floor | 31-10-2025 | YET TO START | NA |
17 Floor | 30-11-2025 | YET TO START | NA |
18 Floor | 31-12-2025 | YET TO START | NA |
19 Floor | 31-01-2026 | YET TO START | NA |
20 Floor | 28-02-2026 | YET TO START | NA |
21 Floor | 31-03-2026 | YET TO START | NA |
22 Floor | 30-04-2026 | YET TO START | NA |
23 Floor | 31-05-2026 | YET TO START | NA |
Electrical Works | 30-09-2026 | YET TO START | NA |
Concealed Cabling including Plugs & switches | 31-12-2026 | YET TO START | NA |
Installation & Charging of Transformer | 31-12-2026 | YET TO START | NA |
Connection to Flats/Apartments | 31-12-2026 | YET TO START | NA |
PH works | 31-12-2026 | YET TO START | NA |
Laying of concealed Pipes | 31-12-2026 | YET TO START | NA |
PH Fittings | 31-01-2027 | YET TO START | NA |
Overhead Water Tanks | 31-01-2027 | YET TO START | NA |
Water Supply Connection to all units | 31-01-2027 | YET TO START | NA |
STP construction and completion | 28-02-2027 | YET TO START | NA |
Distempering & Colouring of all units and exteriors | 28-02-2027 | YET TO START | NA |
Fixation of doors and windows | 31-03-2027 | YET TO START | NA |
Scheduled Date of handing over possession | 30-06-2027 | YET TO START | NA |
Development of common areas, parks, gardens etc | 31-03-2027 | YET TO START | NA |
Site Development | 30-09-2022 | ON GOING | |
NA | NA | NA | NA |
Ground Floor/Stilt Floor | 31-03-2023 | YET TO START | NA |
1 Floor | 31-06-2023 | YET TO START | NA |
2 Floor | 28-09-2023 | YET TO START | NA |
3 Floor | 30-01-2024 | YET TO START | NA |
4 Floor | 31-05-2024 | YET TO START | NA |
5 Floor | 30-06-2024 | YET TO START | NA |
6 Floor | 31-07-2024 | YET TO START | NA |
7 Floor | 31-08-2024 | YET TO START | NA |
8 Floor | 30-09-2024 | YET TO START | NA |
9 Floor | 31-10-2024 | YET TO START | NA |
10 Floor | 30-11-2024 | YET TO START | NA |
11 Floor | 31-12-2024 | YET TO START | NA |
12 Floor | 31-01-2025 | YET TO START | NA |
13 Floor | 29-02-2025 | YET TO START | NA |
14 Floor | 31-03-2025 | YET TO START | NA |
15 Floor | 30-04-2025 | YET TO START | NA |
16 Floor | 31-05-2025 | YET TO START | NA |
17 Floor | 30-06-2025 | YET TO START | NA |
18 Floor | 31-07-2025 | YET TO START | NA |
19 Floor | 31-05-2025 | YET TO START | NA |
20 Floor | 31-07-2025 | YET TO START | NA |
21 Floor | 31-08-2025 | YET TO START | NA |
22 Floor | 30-09-2025 | YET TO START | NA |
23 Floor | 31-10-2025 | YET TO START | NA |
NA | NA | NA | NA |
Ground Floor/Stilt Floor | 30-06-2024 | YET TO START | NA |
1 Floor | 31-07-2024 | YET TO START | NA |
2 Floor | 31-08-2024 | YET TO START | NA |
3 Floor | 30-09-2024 | YET TO START | NA |
4 Floor | 31-10-2024 | YET TO START | NA |
5 Floor | 30-11-2024 | YET TO START | NA |
6 Floor | 31-12-2024 | YET TO START | NA |
7 Floor | 31-01-2025 | YET TO START | NA |
8 Floor | 29-02-2025 | YET TO START | NA |
9 Floor | 31-03-2025 | YET TO START | NA |
10 Floor | 30-04-2025 | YET TO START | NA |
11 Floor | 31-05-2025 | YET TO START | NA |
12 Floor | 30-06-2025 | YET TO START | NA |
13 Floor | 31-07-2025 | YET TO START | NA |
14 Floor | 31-08-2025 | YET TO START | NA |
15 Floor | 30-09-2025 | YET TO START | NA |
16 Floor | 31-10-2025 | YET TO START | NA |
17 Floor | 30-11-2025 | YET TO START | NA |
18 Floor | 31-12-2025 | YET TO START | NA |
19 Floor | 31-01-2026 | YET TO START | NA |
20 Floor | 28-02-2026 | YET TO START | NA |
21 Floor | 31-03-2026 | YET TO START | NA |
22 Floor | 30-04-2026 | YET TO START | NA |
23 Floor | 31-05-2026 | YET TO START | NA |
Electrical Works | 30-09-2026 | YET TO START | NA |
Concealed Cabling including Plugs & switches | 31-12-2026 | YET TO START | NA |
Installation & Charging of Transformer | 31-12-2026 | YET TO START | NA |
Connection to Flats/Apartments | 31-12-2026 | YET TO START | NA |
PH works | 31-12-2026 | YET TO START | NA |
Laying of concealed Pipes | 31-12-2026 | YET TO START | NA |
PH Fittings | 31-01-2027 | YET TO START | NA |
Overhead Water Tanks | 31-01-2027 | YET TO START | NA |
Water Supply Connection to all units | 31-01-2027 | YET TO START | NA |
STP construction and completion | 28-02-2027 | YET TO START | NA |
Distempering & Colouring of all units and exteriors | 28-02-2027 | YET TO START | NA |
Fixation of doors and windows | 31-03-2027 | YET TO START | NA |
Scheduled Date of handing over possession | 30-06-2027 | YET TO START | NA |
Development of common areas, parks, gardens etc | 31-03-2027 | YET TO START | NA |
Site Development | 30-09-2022 | ON GOING | NA |
NA | - | - | NA |
Ground Floor/Stilt Floor | 31-03-2023 | YET TO START | NA |
1 Floor | 31-06-2023 | YET TO START | NA |
2 Floor | 28-09-2023 | YET TO START | NA |
3 Floor | 30-01-2024 | YET TO START | NA |
4 Floor | 31-05-2024 | YET TO START | NA |
5 Floor | 30-06-2024 | YET TO START | NA |
6 Floor | 31-07-2024 | YET TO START | NA |
7 Floor | 31-08-2024 | YET TO START | NA |
8 Floor | 30-09-2024 | YET TO START | NA |
9 Floor | 31-10-2024 | YET TO START | NA |
10 Floor | 30-11-2024 | YET TO START | NA |
11 Floor | 31-12-2024 | YET TO START | NA |
12 Floor | 31-01-2025 | YET TO START | NA |
13 Floor | 29-02-2025 | YET TO START | NA |
14 Floor | 31-03-2025 | YET TO START | NA |
15 Floor | 30-04-2025 | YET TO START | NA |
16 Floor | 31-05-2025 | YET TO START | NA |
17 Floor | 30-06-2025 | YET TO START | NA |
18 Floor | 31-07-2025 | YET TO START | NA |
19 Floor | 31-05-2025 | YET TO START | NA |
20 Floor | 31-07-2025 | YET TO START | NA |
21 Floor | 31-08-2025 | YET TO START | NA |
22 Floor | 30-09-2025 | YET TO START | NA |
23 Floor | 31-10-2025 | YET TO START | NA |
NA | - | - | NA |
Ground Floor/Stilt Floor | 30-06-2024 | YET TO START | NA |
1 Floor | 31-07-2024 | YET TO START | NA |
2 Floor | 31-08-2024 | YET TO START | NA |
3 Floor | 30-09-2024 | YET TO START | NA |
4 Floor | 31-10-2024 | YET TO START | NA |
5 Floor | 30-11-2024 | YET TO START | NA |
6 Floor | 31-12-2024 | YET TO START | NA |
7 Floor | 31-01-2025 | YET TO START | NA |
8 Floor | 29-02-2025 | YET TO START | NA |
9 Floor | 31-03-2025 | YET TO START | NA |
10 Floor | 30-04-2025 | YET TO START | NA |
11 Floor | 31-05-2025 | YET TO START | NA |
12 Floor | 30-06-2025 | YET TO START | NA |
13 Floor | 31-07-2025 | YET TO START | NA |
14 Floor | 31-08-2025 | YET TO START | NA |
15 Floor | 30-09-2025 | YET TO START | NA |
16 Floor | 31-10-2025 | YET TO START | NA |
17 Floor | 30-11-2025 | YET TO START | NA |
18 Floor | 31-12-2025 | YET TO START | NA |
19 Floor | 31-01-2026 | YET TO START | NA |
20 Floor | 28-02-2026 | YET TO START | NA |
21 Floor | 31-03-2026 | YET TO START | NA |
22 Floor | 30-04-2026 | YET TO START | NA |
23 Floor | 31-05-2026 | YET TO START | NA |
Electrical Works | 30-09-2026 | YET TO START | NA |
Concealed Cabling including Plugs & switches | 31-12-2026 | YET TO START | NA |
Installation & Charging of Transformer | 31-12-2026 | YET TO START | NA |
Connection to Flats/Apartments | 31-12-2026 | YET TO START | NA |
PH works | 31-12-2026 | YET TO START | NA |
Laying of concealed Pipes | 31-12-2026 | YET TO START | NA |
PH Fittings | 31-01-2027 | YET TO START | NA |
Overhead Water Tanks | 31-01-2027 | YET TO START | NA |
Water Supply Connection to all units | 31-01-2027 | YET TO START | NA |
STP construction and completion | 28-02-2027 | YET TO START | NA |
Distempering & Colouring of all units and exteriors | 28-02-2027 | YET TO START | NA |
Fixation of doors and windows | 31-03-2027 | YET TO START | NA |
Scheduled Date of handing over possession | 30-06-2027 | YET TO START | NA |
Development of common areas, parks, gardens etc | 31-03-2027 | YET TO START | NA |
Site Development | 31-03-2023 | ON GOING | |
NA | - | - | |
Ground Floor/Stilt Floor | 31-03-2023 | YET TO START | NA |
1 Floor | 31-06-2023 | YET TO START | NA |
2 Floor | 28-09-2023 | YET TO START | NA |
3 Floor | 30-01-2024 | YET TO START | NA |
4 Floor | 31-05-2024 | YET TO START | NA |
5 Floor | 30-06-2024 | YET TO START | NA |
6 Floor | 31-07-2024 | YET TO START | NA |
7 Floor | 31-08-2024 | YET TO START | NA |
8 Floor | 30-09-2024 | YET TO START | NA |
9 Floor | 31-10-2024 | YET TO START | NA |
10 Floor | 30-11-2024 | YET TO START | NA |
11 Floor | 31-12-2024 | YET TO START | NA |
12 Floor | 31-01-2025 | YET TO START | NA |
13 Floor | 29-02-2025 | YET TO START | NA |
14 Floor | 31-03-2025 | YET TO START | NA |
15 Floor | 30-04-2025 | YET TO START | NA |
16 Floor | 31-05-2025 | YET TO START | NA |
17 Floor | 30-06-2025 | YET TO START | NA |
18 Floor | 31-07-2025 | YET TO START | NA |
19 Floor | 31-05-2025 | YET TO START | NA |
20 Floor | 31-07-2025 | YET TO START | NA |
21 Floor | 31-08-2025 | YET TO START | NA |
22 Floor | 30-09-2025 | YET TO START | NA |
23 Floor | 31-10-2025 | YET TO START | NA |
NA | - | - | NA |
Ground Floor/Stilt Floor | 30-06-2024 | YET TO START | NA |
1 Floor | 31-07-2024 | YET TO START | NA |
2 Floor | 31-08-2024 | YET TO START | NA |
3 Floor | 30-09-2024 | YET TO START | NA |
4 Floor | 31-10-2024 | YET TO START | NA |
5 Floor | 30-11-2024 | YET TO START | NA |
6 Floor | 31-12-2024 | YET TO START | NA |
7 Floor | 31-01-2025 | YET TO START | NA |
8 Floor | 29-02-2025 | YET TO START | NA |
9 Floor | 31-03-2025 | YET TO START | NA |
10 Floor | 30-04-2025 | YET TO START | NA |
11 Floor | 31-05-2025 | YET TO START | NA |
12 Floor | 30-06-2025 | YET TO START | NA |
13 Floor | 31-07-2025 | YET TO START | NA |
14 Floor | 31-08-2025 | YET TO START | NA |
15 Floor | 30-09-2025 | YET TO START | NA |
16 Floor | 31-10-2025 | YET TO START | NA |
17 Floor | 30-11-2025 | YET TO START | NA |
18 Floor | 31-12-2025 | YET TO START | NA |
19 Floor | 31-01-2026 | YET TO START | NA |
20 Floor | 28-02-2026 | YET TO START | NA |
21 Floor | 31-03-2026 | YET TO START | NA |
22 Floor | 30-04-2026 | YET TO START | NA |
23 Floor | 31-05-2026 | YET TO START | NA |
Electrical Works | 30-09-2026 | YET TO START | NA |
Concealed Cabling including Plugs & switches | 31-12-2026 | YET TO START | NA |
Installation & Charging of Transformer | 31-12-2026 | YET TO START | NA |
Connection to Flats/Apartments | 31-12-2026 | YET TO START | NA |
PH works | 31-12-2026 | YET TO START | NA |
Laying of concealed Pipes | 31-12-2026 | YET TO START | NA |
PH Fittings | 31-01-2027 | YET TO START | NA |
Overhead Water Tanks | 31-01-2027 | YET TO START | NA |
Water Supply Connection to all units | 31-01-2027 | YET TO START | NA |
STP construction and completion | 28-02-2027 | YET TO START | NA |
Distempering & Colouring of all units and exteriors | 28-02-2027 | YET TO START | NA |
Fixation of doors and windows | 31-03-2027 | YET TO START | NA |
Scheduled Date of handing over possession | 30-06-2027 | YET TO START | NA |
Development of common areas, parks, gardens etc | 31-03-2027 | YET TO START | NA |
Site Development | 31-03-2023 | ON GOING | NA |
NA | - | - | NA |
Ground Floor/Stilt Floor | 31-03-2023 | ONGOING | |
1 Floor | 31-06-2023 | YET TO START | NA |
2 Floor | 28-09-2023 | YET TO START | NA |
3 Floor | 30-01-2024 | YET TO START | NA |
4 Floor | 31-05-2024 | YET TO START | NA |
5 Floor | 30-06-2024 | YET TO START | NA |
6 Floor | 31-07-2024 | YET TO START | NA |
7 Floor | 31-08-2024 | YET TO START | NA |
8 Floor | 30-09-2024 | YET TO START | NA |
9 Floor | 31-10-2024 | YET TO START | NA |
10 Floor | 30-11-2024 | YET TO START | NA |
11 Floor | 31-12-2024 | YET TO START | NA |
12 Floor | 31-01-2025 | YET TO START | NA |
13 Floor | 29-02-2025 | YET TO START | NA |
14 Floor | 31-03-2025 | YET TO START | NA |
15 Floor | 30-04-2025 | YET TO START | NA |
16 Floor | 31-05-2025 | YET TO START | NA |
17 Floor | 30-06-2025 | YET TO START | NA |
18 Floor | 31-07-2025 | YET TO START | NA |
19 Floor | 31-05-2025 | YET TO START | NA |
20 Floor | 31-07-2025 | YET TO START | NA |
21 Floor | 31-08-2025 | YET TO START | NA |
22 Floor | 30-09-2025 | YET TO START | NA |
23 Floor | 31-10-2025 | YET TO START | NA |
NA | - | - | NA |
Ground Floor/Stilt Floor | 30-06-2024 | YET TO START | NA |
1 Floor | 31-07-2024 | YET TO START | NA |
2 Floor | 31-08-2024 | YET TO START | NA |
3 Floor | 30-09-2024 | YET TO START | NA |
4 Floor | 31-10-2024 | YET TO START | NA |
5 Floor | 30-11-2024 | YET TO START | NA |
6 Floor | 31-12-2024 | YET TO START | NA |
7 Floor | 31-01-2025 | YET TO START | NA |
8 Floor | 29-02-2025 | YET TO START | NA |
9 Floor | 31-03-2025 | YET TO START | NA |
10 Floor | 30-04-2025 | YET TO START | NA |
11 Floor | 31-05-2025 | YET TO START | NA |
12 Floor | 30-06-2025 | YET TO START | NA |
13 Floor | 31-07-2025 | YET TO START | NA |
14 Floor | 31-08-2025 | YET TO START | NA |
15 Floor | 30-09-2025 | YET TO START | NA |
16 Floor | 31-10-2025 | YET TO START | NA |
17 Floor | 30-11-2025 | YET TO START | NA |
18 Floor | 31-12-2025 | YET TO START | NA |
19 Floor | 31-01-2026 | YET TO START | NA |
20 Floor | 28-02-2026 | YET TO START | NA |
21 Floor | 31-03-2026 | YET TO START | NA |
22 Floor | 30-04-2026 | YET TO START | NA |
23 Floor | 31-05-2026 | YET TO START | NA |
Electrical Works | 30-09-2026 | YET TO START | NA |
Concealed Cabling including Plugs & switches | 31-12-2026 | YET TO START | NA |
Installation & Charging of Transformer | 31-12-2026 | YET TO START | NA |
Connection to Flats/Apartments | 31-12-2026 | YET TO START | NA |
PH works | 31-12-2026 | YET TO START | NA |
Laying of concealed Pipes | 31-12-2026 | YET TO START | NA |
PH Fittings | 31-01-2027 | YET TO START | NA |
Overhead Water Tanks | 31-01-2027 | YET TO START | NA |
Water Supply Connection to all units | 31-01-2027 | YET TO START | NA |
STP construction and completion | 28-02-2027 | YET TO START | NA |
Distempering & Colouring of all units and exteriors | 28-02-2027 | YET TO START | NA |
Fixation of doors and windows | 31-03-2027 | YET TO START | NA |
Scheduled Date of handing over possession | 30-06-2027 | YET TO START | NA |
Development of common areas, parks, gardens etc | 31-03-2027 | YET TO START | NA |
Site Development | 31-03-2023 | ON GOING | NA |
NA | - | - | NA |
Ground Floor/Stilt Floor | 31-03-2023 | ONGOING | NA |
1 Floor | 31-06-2023 | YET TO START | NA |
2 Floor | 28-09-2023 | YET TO START | NA |
3 Floor | 30-01-2024 | YET TO START | NA |
4 Floor | 31-05-2024 | YET TO START | NA |
5 Floor | 30-06-2024 | YET TO START | NA |
6 Floor | 31-07-2024 | YET TO START | NA |
7 Floor | 31-08-2024 | YET TO START | NA |
8 Floor | 30-09-2024 | YET TO START | NA |
9 Floor | 31-10-2024 | YET TO START | NA |
10 Floor | 30-11-2024 | YET TO START | NA |
11 Floor | 31-12-2024 | YET TO START | NA |
12 Floor | 31-01-2025 | YET TO START | NA |
13 Floor | 29-02-2025 | YET TO START | NA |
14 Floor | 31-03-2025 | YET TO START | NA |
15 Floor | 30-04-2025 | YET TO START | NA |
16 Floor | 31-05-2025 | YET TO START | NA |
17 Floor | 30-06-2025 | YET TO START | NA |
18 Floor | 31-07-2025 | YET TO START | NA |
19 Floor | 31-05-2025 | YET TO START | NA |
20 Floor | 31-07-2025 | YET TO START | NA |
21 Floor | 31-08-2025 | YET TO START | NA |
22 Floor | 30-09-2025 | YET TO START | NA |
23 Floor | 31-10-2025 | YET TO START | NA |
NA | - | - | NA |
Ground Floor/Stilt Floor | 30-06-2024 | YET TO START | NA |
1 Floor | 31-07-2024 | YET TO START | NA |
2 Floor | 31-08-2024 | YET TO START | NA |
3 Floor | 30-09-2024 | YET TO START | NA |
4 Floor | 31-10-2024 | YET TO START | NA |
5 Floor | 30-11-2024 | YET TO START | NA |
6 Floor | 31-12-2024 | YET TO START | NA |
7 Floor | 31-01-2025 | YET TO START | NA |
8 Floor | 29-02-2025 | YET TO START | NA |
9 Floor | 31-03-2025 | YET TO START | NA |
10 Floor | 30-04-2025 | YET TO START | NA |
11 Floor | 31-05-2025 | YET TO START | NA |
12 Floor | 30-06-2025 | YET TO START | NA |
13 Floor | 31-07-2025 | YET TO START | NA |
14 Floor | 31-08-2025 | YET TO START | NA |
15 Floor | 30-09-2025 | YET TO START | NA |
16 Floor | 31-10-2025 | YET TO START | NA |
17 Floor | 30-11-2025 | YET TO START | NA |
18 Floor | 31-12-2025 | YET TO START | NA |
19 Floor | 31-01-2026 | YET TO START | NA |
20 Floor | 28-02-2026 | YET TO START | NA |
21 Floor | 31-03-2026 | YET TO START | NA |
22 Floor | 30-04-2026 | YET TO START | NA |
23 Floor | 31-05-2026 | YET TO START | NA |
Electrical Works | 30-09-2026 | YET TO START | NA |
Concealed Cabling including Plugs & switches | 31-12-2026 | YET TO START | NA |
Installation & Charging of Transformer | 31-12-2026 | YET TO START | NA |
Connection to Flats/Apartments | 31-12-2026 | YET TO START | NA |
PH works | 31-12-2026 | YET TO START | NA |
Laying of concealed Pipes | 31-12-2026 | YET TO START | NA |
PH Fittings | 31-01-2027 | YET TO START | NA |
Overhead Water Tanks | 31-01-2027 | YET TO START | NA |
Water Supply Connection to all units | 31-01-2027 | YET TO START | NA |
STP construction and completion | 28-02-2027 | YET TO START | NA |
Distempering & Colouring of all units and exteriors | 28-02-2027 | YET TO START | NA |
Fixation of doors and windows | 31-03-2027 | YET TO START | NA |
Scheduled Date of handing over possession | 30-06-2027 | YET TO START | NA |
Development of common areas, parks, gardens etc | 31-03-2027 | YET TO START | NA |
Site Development | 31-03-2023 | ON GOING | NA |
NA | - | - | NA |
Ground Floor/Stilt Floor | 31-03-2023 | ONGOING | NA |
1 Floor | 31-06-2023 | YET TO START | NA |
2 Floor | 28-09-2023 | YET TO START | NA |
3 Floor | 30-01-2024 | YET TO START | NA |
4 Floor | 31-05-2024 | YET TO START | NA |
5 Floor | 30-06-2024 | YET TO START | NA |
6 Floor | 31-07-2024 | YET TO START | NA |
7 Floor | 31-08-2024 | YET TO START | NA |
8 Floor | 30-09-2024 | YET TO START | NA |
9 Floor | 31-10-2024 | YET TO START | NA |
10 Floor | 30-11-2024 | YET TO START | NA |
11 Floor | 31-12-2024 | YET TO START | NA |
12 Floor | 31-01-2025 | YET TO START | NA |
13 Floor | 29-02-2025 | YET TO START | NA |
14 Floor | 31-03-2025 | YET TO START | NA |
15 Floor | 30-04-2025 | YET TO START | NA |
16 Floor | 31-05-2025 | YET TO START | NA |
17 Floor | 30-06-2025 | YET TO START | NA |
18 Floor | 31-07-2025 | YET TO START | NA |
19 Floor | 31-05-2025 | YET TO START | NA |
20 Floor | 31-07-2025 | YET TO START | NA |
21 Floor | 31-08-2025 | YET TO START | NA |
22 Floor | 30-09-2025 | YET TO START | NA |
23 Floor | 31-10-2025 | YET TO START | NA |
NA | - | - | NA |
Ground Floor/Stilt Floor | 30-06-2024 | YET TO START | NA |
1 Floor | 31-07-2024 | YET TO START | NA |
2 Floor | 31-08-2024 | YET TO START | NA |
3 Floor | 30-09-2024 | YET TO START | NA |
4 Floor | 31-10-2024 | YET TO START | NA |
5 Floor | 30-11-2024 | YET TO START | NA |
6 Floor | 31-12-2024 | YET TO START | NA |
7 Floor | 31-01-2025 | YET TO START | NA |
8 Floor | 29-02-2025 | YET TO START | NA |
9 Floor | 31-03-2025 | YET TO START | NA |
10 Floor | 30-04-2025 | YET TO START | NA |
11 Floor | 31-05-2025 | YET TO START | NA |
12 Floor | 30-06-2025 | YET TO START | NA |
13 Floor | 31-07-2025 | YET TO START | NA |
14 Floor | 31-08-2025 | YET TO START | NA |
15 Floor | 30-09-2025 | YET TO START | NA |
16 Floor | 31-10-2025 | YET TO START | NA |
17 Floor | 30-11-2025 | YET TO START | NA |
18 Floor | 31-12-2025 | YET TO START | NA |
19 Floor | 31-01-2026 | YET TO START | NA |
20 Floor | 28-02-2026 | YET TO START | NA |
21 Floor | 31-03-2026 | YET TO START | NA |
22 Floor | 30-04-2026 | YET TO START | NA |
23 Floor | 31-05-2026 | YET TO START | NA |
Electrical Works | 30-09-2026 | YET TO START | NA |
Concealed Cabling including Plugs & switches | 31-12-2026 | YET TO START | NA |
Installation & Charging of Transformer | 31-12-2026 | YET TO START | NA |
Connection to Flats/Apartments | 31-12-2026 | YET TO START | NA |
PH works | 31-12-2026 | YET TO START | NA |
Laying of concealed Pipes | 31-12-2026 | YET TO START | NA |
PH Fittings | 31-01-2027 | YET TO START | NA |
Overhead Water Tanks | 31-01-2027 | YET TO START | NA |
Water Supply Connection to all units | 31-01-2027 | YET TO START | NA |
STP construction and completion | 28-02-2027 | YET TO START | NA |
Distempering & Colouring of all units and exteriors | 28-02-2027 | YET TO START | NA |
Fixation of doors and windows | 31-03-2027 | YET TO START | NA |
Scheduled Date of handing over possession | 30-06-2027 | YET TO START | NA |
Development of common areas, parks, gardens etc | 31-03-2027 | YET TO START | NA |
Site Development | 31-03-2023 | ON GOING | NA |
NA | - | - | NA |
Ground Floor/Stilt Floor | 31-03-2023 | ONGOING | NA |
1 Floor | 31-06-2023 | ONGOING | NA |
2 Floor | 28-09-2023 | YET TO START | NA |
3 Floor | 30-01-2024 | YET TO START | NA |
4 Floor | 31-05-2024 | YET TO START | NA |
5 Floor | 30-06-2024 | YET TO START | NA |
6 Floor | 31-07-2024 | YET TO START | NA |
7 Floor | 31-08-2024 | YET TO START | NA |
8 Floor | 30-09-2024 | YET TO START | NA |
9 Floor | 31-10-2024 | YET TO START | NA |
10 Floor | 30-11-2024 | YET TO START | NA |
11 Floor | 31-12-2024 | YET TO START | NA |
12 Floor | 31-01-2025 | YET TO START | NA |
13 Floor | 29-02-2025 | YET TO START | NA |
14 Floor | 31-03-2025 | YET TO START | NA |
15 Floor | 30-04-2025 | YET TO START | NA |
16 Floor | 31-05-2025 | YET TO START | NA |
17 Floor | 30-06-2025 | YET TO START | NA |
18 Floor | 31-07-2025 | YET TO START | NA |
19 Floor | 31-05-2025 | YET TO START | NA |
20 Floor | 31-07-2025 | YET TO START | NA |
21 Floor | 31-08-2025 | YET TO START | NA |
22 Floor | 30-09-2025 | YET TO START | NA |
23 Floor | 31-10-2025 | YET TO START | NA |
NA | - | - | NA |
Ground Floor/Stilt Floor | 30-06-2024 | ONGOING | NA |
1 Floor | 31-07-2024 | ONGOING | NA |
2 Floor | 31-08-2024 | YET TO START | NA |
3 Floor | 30-09-2024 | YET TO START | NA |
4 Floor | 31-10-2024 | YET TO START | NA |
5 Floor | 30-11-2024 | YET TO START | NA |
6 Floor | 31-12-2024 | YET TO START | NA |
7 Floor | 31-01-2025 | YET TO START | NA |
8 Floor | 29-02-2025 | YET TO START | NA |
9 Floor | 31-03-2025 | YET TO START | NA |
10 Floor | 30-04-2025 | YET TO START | NA |
11 Floor | 31-05-2025 | YET TO START | NA |
12 Floor | 30-06-2025 | YET TO START | NA |
13 Floor | 31-07-2025 | YET TO START | NA |
14 Floor | 31-08-2025 | YET TO START | NA |
15 Floor | 30-09-2025 | YET TO START | NA |
16 Floor | 31-10-2025 | YET TO START | NA |
17 Floor | 30-11-2025 | YET TO START | NA |
18 Floor | 31-12-2025 | YET TO START | NA |
19 Floor | 31-01-2026 | YET TO START | NA |
20 Floor | 28-02-2026 | YET TO START | NA |
21 Floor | 31-03-2026 | YET TO START | NA |
22 Floor | 30-04-2026 | YET TO START | NA |
23 Floor | 31-05-2026 | YET TO START | NA |
Electrical Works | 30-09-2026 | YET TO START | NA |
Concealed Cabling including Plugs & switches | 31-12-2026 | YET TO START | NA |
Installation & Charging of Transformer | 31-12-2026 | YET TO START | NA |
Connection to Flats/Apartments | 31-12-2026 | YET TO START | NA |
PH works | 31-12-2026 | YET TO START | NA |
Laying of concealed Pipes | 31-12-2026 | YET TO START | NA |
PH Fittings | 31-01-2027 | YET TO START | NA |
Overhead Water Tanks | 31-01-2027 | YET TO START | NA |
Water Supply Connection to all units | 31-01-2027 | YET TO START | NA |
STP construction and completion | 28-02-2027 | YET TO START | NA |
Distempering & Colouring of all units and exteriors | 28-02-2027 | YET TO START | NA |
Fixation of doors and windows | 31-03-2027 | YET TO START | NA |
Scheduled Date of handing over possession | 30-06-2027 | YET TO START | NA |
Development of common areas, parks, gardens etc | 31-03-2027 | YET TO START | NA |
: Residential | |
: 242
|
|
: 0
|
Residential Flats/ House | |||||
---|---|---|---|---|---|
S. No. | Flat No./ House No. | ||||
Area in square metres |
Ownership | ||||
Carpet Area | Balcony Area | Exclusive Open Terrace Area | |||
1 | A-101 | 127.62 | 23.43 | 00 | Promoter |
2 | A-102 | 133.70 | 21.25 | 00 | Promoter |
3 | A-103 | 113.66 | 11.20 | 00 | Promoter |
4 | A-104 | 115.06 | 13.51 | 7.78 | Promoter |
5 | A-105 | 112.16 | 12.95 | 00 | Promoter |
6 | A-106 | 107.81 | 12.69 | 4.70 | Promoter |
7 | A-201 | 127.62 | 20.02 | 00 | Promoter |
8 | A-202 | 133.70 | 21.25 | 00 | Promoter |
9 | A-203 | 113.66 | 11.20 | 00 | Promoter |
10 | A-204 | 115.06 | 12.66 | 00 | Promoter |
11 | A-205 | 112.16 | 12.09 | 00 | Promoter |
12 | A-206 | 107.81 | 12.69 | 00 | Promoter |
13 | A-301 | 127.62 | 20.02 | 00 | Promoter |
14 | A-302 | 133.70 | 21.25 | 00 | Promoter |
15 | A-303 | 113.66 | 11.20 | 00 | Promoter |
16 | A-304 | 115.06 | 12.66 | 00 | Promoter |
17 | A-305 | 112.16 | 12.09 | 00 | Promoter |
18 | A-306 | 107.81 | 12.69 | 00 | Promoter |
19 | A-401 | 127.62 | 20.02 | 00 | Promoter |
20 | A-402 | 133.70 | 21.25 | 00 | Promoter |
21 | A-403 | 113.66 | 11.20 | 00 | Promoter |
22 | A-404 | 115.06 | 12.66 | 00 | Promoter |
23 | A-405 | 112.16 | 12.09 | 00 | Promoter |
24 | A-406 | 107.81 | 12.69 | 00 | Promoter |
25 | A-501 | 127.62 | 20.02 | 00 | Promoter |
26 | A-502 | 133.70 | 21.25 | 00 | Promoter |
27 | A-503 | 113.66 | 11.20 | 00 | Promoter |
28 | A-504 | 115.06 | 12.66 | 00 | Promoter |
29 | A-505 | 112.16 | 12.09 | 00 | Promoter |
30 | A-506 | 107.81 | 12.69 | 00 | Promoter |
31 | A-601 | 127.62 | 20.02 | 00 | Promoter |
32 | A-602 | 133.70 | 21.25 | 00 | Promoter |
33 | A-603 | 113.66 | 11.20 | 00 | Promoter |
34 | A-604 | 115.06 | 12.66 | 00 | Promoter |
35 | A-605 | 112.16 | 12.09 | 00 | Promoter |
36 | A-606 | 107.81 | 12.69 | 00 | Promoter |
37 | A-701 | 127.62 | 20.02 | 00 | Promoter |
38 | A-702 | 133.70 | 21.25 | 00 | Promoter |
39 | A-703 | 113.66 | 11.20 | 00 | Promoter |
40 | A-704 | 115.06 | 12.66 | 00 | Promoter |
41 | A-705 | 112.16 | 12.09 | 00 | Promoter |
42 | A-706 | 107.81 | 12.69 | 00 | Promoter |
43 | A-801 | 127.62 | 20.02 | 00 | Promoter |
44 | A-802 | 133.70 | 21.25 | 00 | Promoter |
45 | A-803 | 113.66 | 11.20 | 00 | Promoter |
46 | A-804 | 115.06 | 12.66 | 00 | Promoter |
47 | A-805 | 112.16 | 12.09 | 00 | Promoter |
48 | A-806 | 107.81 | 12.69 | 00 | Promoter |
49 | A-901 | 127.62 | 20.02 | 00 | Promoter |
50 | A-902 | 133.70 | 21.25 | 00 | Promoter |
51 | A-903 | 113.66 | 11.20 | 00 | Promoter |
52 | A-904 | 115.06 | 12.66 | 00 | Promoter |
53 | A-905 | 112.16 | 12.09 | 00 | Promoter |
54 | A-906 | 107.81 | 12.69 | 00 | Promoter |
55 | A-1001 | 127.62 | 20.02 | 00 | Promoter |
56 | A-1002 | 133.70 | 21.25 | 00 | Promoter |
57 | A-1003 | 113.66 | 11.20 | 00 | Promoter |
58 | A-1004 | 115.06 | 12.66 | 00 | Promoter |
59 | A-1005 | 112.16 | 12.09 | 00 | Promoter |
60 | A-1006 | 107.81 | 12.69 | 00 | Promoter |
61 | A-1101 | 127.62 | 20.02 | 00 | Promoter |
62 | A-1102 | 133.70 | 21.25 | 00 | Promoter |
63 | A-1103 | 113.66 | 11.20 | 00 | Promoter |
64 | A-1104 | 115.06 | 12.66 | 00 | Promoter |
65 | A-1105 | 112.16 | 12.09 | 00 | Promoter |
66 | A-1106 | 107.81 | 12.69 | 00 | Promoter |
67 | A-1201 | 127.62 | 20.02 | 00 | Promoter |
68 | A-1202 | 133.70 | 21.25 | 00 | Promoter |
69 | A-1203 | 113.66 | 11.20 | 00 | Promoter |
70 | A-1204 | 115.06 | 12.66 | 00 | Promoter |
71 | A-1205 | 112.16 | 12.09 | 00 | Promoter |
72 | A-1206 | 107.81 | 12.69 | 00 | Promoter |
73 | A-1301 | 127.62 | 20.02 | 00 | Promoter |
74 | A-1302 | 133.70 | 21.25 | 00 | Promoter |
75 | A-1303 | 113.66 | 11.20 | 00 | Promoter |
76 | A-1304 | 115.06 | 12.66 | 00 | Promoter |
77 | A-1305 | 112.16 | 12.09 | 00 | Promoter |
78 | A-1306 | 107.81 | 12.69 | 00 | Promoter |
79 | A-1401 | 127.62 | 20.02 | 00 | Promoter |
80 | A-1402 | 133.70 | 21.25 | 00 | Promoter |
81 | A-1403 | 113.66 | 11.20 | 00 | Promoter |
82 | A-1404 | 115.06 | 12.66 | 00 | Promoter |
83 | A-1405 | 112.16 | 12.09 | 00 | Promoter |
84 | A-1406 | 107.81 | 12.69 | 00 | Promoter |
85 | A-1501 | 127.62 | 20.02 | 00 | Promoter |
86 | A-1502 | 133.70 | 21.25 | 00 | Promoter |
87 | A-1503 | 113.66 | 11.20 | 00 | Promoter |
88 | A-1504 | 115.06 | 12.66 | 00 | Promoter |
89 | A-1505 | 112.16 | 12.09 | 00 | Promoter |
90 | A-1506 | 107.81 | 12.69 | 00 | Promoter |
91 | A-1601 | 127.62 | 20.02 | 00 | Promoter |
92 | A-1602 | 133.70 | 21.25 | 00 | Promoter |
93 | A-1603 | 113.66 | 11.20 | 00 | Promoter |
94 | A-1604 | 115.06 | 12.66 | 00 | Promoter |
95 | A-1605 | 112.16 | 12.09 | 00 | Promoter |
96 | A-1606 | 107.81 | 12.69 | 00 | Promoter |
97 | A-1701 | 127.62 | 20.02 | 00 | Promoter |
98 | A-1702 | 133.70 | 21.25 | 00 | Promoter |
99 | A-1703 | 113.66 | 11.20 | 00 | Promoter |
100 | A-1704 | 115.06 | 12.66 | 00 | Promoter |
101 | A-1705 | 112.16 | 12.09 | 00 | Promoter |
102 | A-1706 | 107.81 | 12.69 | 00 | Promoter |
103 | A-1801 | 127.62 | 20.02 | 00 | Promoter |
104 | A-1802 | 133.70 | 21.25 | 00 | Promoter |
105 | A-1803 | 113.66 | 11.20 | 00 | Promoter |
106 | A-1804 | 115.06 | 12.66 | 00 | Promoter |
107 | A-1805 | 112.16 | 12.09 | 00 | Promoter |
108 | A-1806 | 107.81 | 12.69 | 00 | Promoter |
109 | A-1901 | 127.62 | 20.02 | 00 | Promoter |
110 | A-1902 | 133.70 | 21.25 | 00 | Promoter |
111 | A-1903 | 113.66 | 11.20 | 00 | Promoter |
112 | A-1904 | 115.06 | 12.66 | 00 | Promoter |
113 | A-1905 | 112.16 | 12.09 | 00 | Promoter |
114 | A-1906 | 107.81 | 12.69 | 00 | Promoter |
115 | A-2001 | 127.62 | 20.02 | 00 | Promoter |
116 | A-2002 | 133.70 | 21.25 | 00 | Promoter |
117 | A-2003 | 113.66 | 11.20 | 00 | Promoter |
118 | A-2004 | 115.06 | 12.66 | 00 | Promoter |
119 | A-2005 | 112.16 | 12.09 | 00 | Promoter |
120 | A-2006 | 107.81 | 12.69 | 00 | Promoter |
121 | A-2101 | 127.62 | 20.02 | 00 | Promoter |
122 | A-2102 | 133.70 | 21.25 | 00 | Promoter |
123 | A-2103 | 113.66 | 11.20 | 00 | Promoter |
124 | A-2104 | 115.06 | 12.66 | 00 | Promoter |
125 | A-2105 | 112.16 | 12.09 | 00 | Promoter |
126 | A-2106 | 107.81 | 12.69 | 00 | Promoter |
127 | A-2201 | 205.49 | 23.44 | 18.21 | Promoter |
128 | A-2202 | 199.59 | 27.25 | 30.53 | Promoter |
129 | A-2203 | 185.58 | 17.08 | 00 | Promoter |
130 | A-2204 | 202.62 | 13.14 | 00 | Promoter |
131 | A-2205 | 164.16 | 15.30 | 00 | Promoter |
132 | A-2206 | 181.32 | 11.20 | 00 | Promoter |
133 | B-101 | 98.30 | 10.19 | 00 | Promoter |
134 | B-102 | 96.13 | 11.65 | 00 | Promoter |
135 | B-103 | 76.29 | 7.04 | 00 | Promoter |
136 | B-104 | 80.90 | 9.26 | 00 | Promoter |
137 | B-105 | 71.77 | 7.32 | 00 | Promoter |
138 | B-201 | 98.30 | 10.19 | 00 | Promoter |
139 | B-202 | 96.13 | 11.65 | 00 | Promoter |
140 | B-203 | 76.29 | 7.04 | 00 | Promoter |
141 | B-204 | 80.90 | 9.26 | 00 | Promoter |
142 | B-205 | 71.77 | 7.32 | 00 | Promoter |
143 | B-301 | 98.30 | 10.19 | 00 | Promoter |
144 | B-302 | 96.13 | 11.65 | 00 | Promoter |
145 | B-303 | 76.29 | 7.04 | 00 | Promoter |
146 | B-304 | 80.90 | 9.26 | 00 | Promoter |
147 | B-305 | 71.77 | 7.32 | 00 | Promoter |
148 | B-401 | 98.0 | 10.19 | 00 | Promoter |
149 | B-402 | 96.13 | 11.65 | 00 | Promoter |
150 | B-403 | 100.69 | 10.13 | 00 | Promoter |
151 | B-404 | 101.75 | 12.47 | 00 | Promoter |
152 | B-405 | 71.77 | 7.32 | 00 | Promoter |
153 | B-501 | 98.30 | 10.19 | 00 | Promoter |
154 | B-502 | 96.13 | 11.65 | 00 | Promoter |
155 | B-503 | 100.69 | 10.13 | 00 | Promoter |
156 | B-504 | 101.75 | 12.47 | 00 | Promoter |
157 | B-505 | 71.77 | 7.32 | 00 | Promoter |
158 | B-601 | 98.30 | 10.19 | 00 | Promoter |
159 | B-602 | 96.13 | 11.65 | 00 | Promoter |
160 | B-603 | 100.69 | 10.13 | 00 | Promoter |
161 | B-604 | 101.75 | 12.47 | 00 | Promoter |
162 | B-605 | 71.77 | 7.32 | 00 | Promoter |
163 | B-701 | 98.30 | 10.19 | 00 | Promoter |
164 | B-702 | 96.13 | 11.65 | 00 | Promoter |
165 | B-703 | 100.69 | 10.13 | 00 | Promoter |
166 | B-704 | 101.75 | 12.47 | 00 | Promoter |
167 | B-705 | 71.77 | 7.32 | 00 | Promoter |
168 | B-801 | 98.30 | 10.19 | 00 | Promoter |
169 | B-802 | 96.13 | 11.65 | 00 | Promoter |
170 | B-803 | 100.69 | 10.13 | 00 | Promoter |
171 | B-804 | 101.75 | 12.47 | 00 | Promoter |
172 | B-805 | 71.77 | 7.32 | 00 | Promoter |
173 | B-901 | 98.30 | 10.19 | 00 | Promoter |
174 | B-902 | 96.13 | 11.65 | 00 | Promoter |
175 | B-903 | 100.69 | 10.13 | 00 | Promoter |
176 | B-904 | 101.75 | 12.47 | 00 | Promoter |
177 | B-905 | 71.77 | 7.32 | 00 | Promoter |
178 | B-1001 | 98.30 | 10.19 | 00 | Promoter |
179 | B-1002 | 96.13 | 11.665 | 00 | Promoter |
180 | B-1003 | 100.69 | 10.13 | 00 | Promoter |
181 | B-1004 | 101.75 | 12.47 | 00 | Promoter |
182 | B-1005 | 71.77 | 7.32 | 00 | Promoter |
183 | B-1101 | 98.30 | 10.19 | 00 | Promoter |
184 | B-1102 | 96.13 | 11.65 | 00 | Promoter |
185 | B-1103 | 100.69 | 10.13 | 00 | Promoter |
186 | B-1104 | 101.75 | 12.47 | 00 | Promoter |
187 | B-1105 | 71.77 | 7.32 | 00 | Promoter |
188 | B-1201 | 98.30 | 10.19 | 00 | Promoter |
189 | B-1202 | 96.13 | 11.65 | 00 | Promoter |
190 | B-1203 | 100.69 | 10.13 | 00 | Promoter |
191 | B-1204 | 101.75 | 12.47 | 00 | Promoter |
192 | B-1205 | 71.77 | 7.32 | 00 | Promoter |
193 | B-1301 | 98.30 | 10.19 | 00 | Promoter |
194 | B-1302 | 96.13 | 11.65 | 00 | Promoter |
195 | B-1303 | 100.69 | 10.13 | 00 | Promoter |
196 | B-1304 | 101.75 | 12.47 | 00 | Promoter |
197 | B-1305 | 71.77 | 7.32 | 00 | Promoter |
198 | B-1401 | 98.30 | 10.19 | 00 | Promoter |
199 | B-1402 | 96.13 | 11.65 | 00 | Promoter |
200 | B-1403 | 100.69 | 10.13 | 00 | Promoter |
201 | B-1404 | 101.75 | 12.47 | 00 | Promoter |
202 | B-1405 | 71.77 | 7.32 | 00 | Promoter |
203 | B-1501 | 98.30 | 10.19 | 00 | Promoter |
204 | B-1502 | 96.13 | 11.65 | 00 | Promoter |
205 | B-1503 | 100.69 | 10.13 | 00 | Promoter |
206 | B-1504 | 101.75 | 12.47 | 00 | Promoter |
207 | B-1505 | 71.77 | 7.32 | 00 | Promoter |
208 | B-1601 | 98.30 | 10.19 | 00 | Promoter |
209 | B-1602 | 96.13 | 11.65 | 00 | Promoter |
210 | B-1603 | 100.69 | 10.13 | 00 | Promoter |
211 | B-1604 | 101.75 | 12.47 | 00 | Promoter |
212 | B-1605 | 71.77 | 7.32 | 00 | Promoter |
213 | B-1701 | 98.30 | 10.19 | 00 | Promoter |
214 | B-1702 | 96.13 | 11.65 | 00 | Promoter |
215 | B-1703 | 100.69 | 10.13 | 00 | Promoter |
216 | B-1704 | 101.75 | 12.47 | 00 | Promoter |
217 | B-1705 | 71.77 | 7.32 | 00 | Promoter |
218 | B-1801 | 98.30 | 10.19 | 00 | Promoter |
219 | B-1802 | 96.13 | 11.65 | 00 | Promoter |
220 | B-1803 | 100.69 | 10.13 | 00 | Promoter |
221 | B-1804 | 101.75 | 12.47 | 00 | Promoter |
222 | B-1805 | 71.77 | 7.32 | 00 | Promoter |
223 | B-1901 | 98.30 | 10.19 | 00 | Promoter |
224 | B-1902 | 96.13 | 11.65 | 00 | Promoter |
225 | B-1903 | 100.69 | 10.13 | 00 | Promoter |
226 | B-1904 | 101.75 | 12.47 | 00 | Promoter |
227 | B-1905 | 71.77 | 7.32 | 00 | Promoter |
228 | B-2001 | 98.30 | 10.19 | 00 | Promoter |
229 | B-2002 | 96.13 | 11.65 | 00 | Promoter |
230 | B-2003 | 100.69 | 10.13 | 00 | Promoter |
231 | B-2004 | 101.75 | 12.47 | 00 | Promoter |
232 | B-2005 | 71.77 | 7.32 | 00 | Promoter |
233 | B-2101 | 98.30 | 10.19 | 00 | Promoter |
234 | B2102 | 96.13 | 11.65 | 00 | Promoter |
235 | B-2103 | 100.69 | 10.13 | 00 | Promoter |
236 | B-2104 | 101.75 | 12.47 | 00 | Promoter |
237 | B-2105 | 71.77 | 7.32 | 00 | Promoter |
238 | B-2201 | 98.30 | 10.19 | 00 | Promoter |
239 | B-2202 | 96.13 | 11.65 | 00 | Promoter |
240 | B-2203 | 100.69 | 10.13 | 00 | Promoter |
241 | B-2204 | 101.75 | 12.47 | 00 | Promoter |
242 | B-2205 | 71.77 | 7.32 | 00 | Promoter |
Types of garages and parking | ||||||
---|---|---|---|---|---|---|
House No. | Type of Garage/ Parking allotted | Serial No., if any | Dimension (Length x Width) in Metres | Floor area in sq. metres | Garage/Parking area cost is included or additional | |
NA | Covered Parking | 1 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 2 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 3 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 4 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 5 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 6 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 7 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 8 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 9 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 10 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 11 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 12 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 13 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 14 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 15 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 16 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 17 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 18 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 19 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 20 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 21 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 22 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 23 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 24 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 25 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 26 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 27 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 28 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 29 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 30 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 31 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 32 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 33 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 34 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 35 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 36 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 37 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 38 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 39 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 40 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 41 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 42 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 43 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 44 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 45 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 46 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 47 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 48 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 49 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 50 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 51 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 52 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 53 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 54 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 55 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 56 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 57 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 58 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 59 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 60 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 61 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 62 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 63 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 64 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 65 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 66 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 67 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 68 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 69 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 70 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 71 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 72 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 73 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 74 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 75 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 76 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 77 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 78 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 79 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 80 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 81 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 82 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 83 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 84 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 85 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 86 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 87 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 88 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 89 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 90 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 91 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 92 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 93 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 94 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 95 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 96 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 97 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 98 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 99 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 100 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 101 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 102 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 103 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 104 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 105 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 106 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 107 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 108 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 109 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 110 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 111 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 112 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 113 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 114 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 115 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 116 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 117 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 118 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 119 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 120 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 121 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 122 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 123 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 124 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 125 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 126 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 127 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 128 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 129 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 130 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 131 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 132 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 133 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 134 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 135 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 136 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 137 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 138 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 139 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 140 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 141 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 142 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 143 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 144 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 145 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 146 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 147 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 148 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 149 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 150 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 151 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 152 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 153 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 154 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 155 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 156 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 157 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 158 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 159 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 160 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 161 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 162 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 163 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 164 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 165 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 166 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 167 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 168 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 169 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 170 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 171 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 172 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 173 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 174 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 175 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 176 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 177 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 178 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 179 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 180 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 181 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 182 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 183 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 184 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 185 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 186 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 187 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 188 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 189 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 190 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 191 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 192 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 193 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 194 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 195 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 196 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 197 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 198 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 199 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 200 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 201 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 202 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 203 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 204 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 205 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 206 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 207 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 208 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 209 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 210 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 211 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 212 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 213 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 214 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 215 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 216 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 217 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 218 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 219 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 220 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 221 | 2.5X5 | 12.50 | Included | NA | Covered Parking | 222 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 223 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 224 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 225 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 226 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 227 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 228 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 229 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 230 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 231 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 232 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 233 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 234 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 235 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 236 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 237 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 238 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 239 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 240 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 241 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | 242 | 2.25X4.5 | 10.125 | Included | NA | Covered Parking | NA | NA | NA | Included |
Particulars of Facilities | Status of the facility | Brief description of facility |
---|---|---|
Drinking Water Facility | Ground Water | Copy of Consent Letter |
Fire Fighting Facility | Yes | SPRINKLERS AT BASEMENT AND WET RISER AT EACH FLOOR |
Emergency Evacuation Services | Yes | TOWER-1 (Block-A) STAIRCASE 2 NOS, TOWER-2 (Block-B)STAIRCASE 4 NOS & TOWER-3 STAIRCASE 2 NOS |
Use of Renewable Energy | Yes | SOLAR WATER HEATER & PV CELLS |
Lift Facility | Yes | Tower-1(Block-A) OTIS 6 NOS WITH ARD, Tower-2(Block-B) OTIS 6 Nos with ARD, Tower-3 OTIS 6 Nos with ARD with capacity of 8 persons in each Lift |
Market Complex | Yes | 4 Nos of Convenience shop at Ground floor |
Community Hall | Yes | 1993.53 sqm, Stilt Floor, Tower-2 |
Gymnasium | Yes | 177.10 sqm |
Swimming Pool | Yes | 198.90 sqm 3rd Floor, Tower-2 |
Play Ground | Yes | 412.9 sqm |
Park/Garden | No | |
Plantation Area | Yes | 1943.10 sqm |
Others(Please Specify) | No | |
Internal Road | Yes | 7.5 mtr Concrete Road |
External Road | Yes | NH-16, 91.44 MTR WIDTH Black Top Road |
Elecricity Supply | Yes | Copy of Consent Letter |
Other Amenities | No |
Generated by pacms.orera.in on date: 2024-05-21