1 |
PARKING SPACE MEASURING 673.40 SQM. AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE
|
30-04-2026
|
NOT STARTED
|
2 |
THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 9.14 MTR. IN WIDTH.
|
30-04-2026
|
NOT STARTED
|
3 |
PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES, FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS
|
30-04-2026
|
NOT STARTED
|
4 |
OBTAIN, WHEREVER APPLICABLE, FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK;
|
30-04-2026
|
NOT STARTED
|
5 |
SUBMIT STAGE WISE CONSTRUCTION REPORT. PENALITY SHALL BE IMPOSED AS PER RULE 14 OF ODA (P&BS) RULES 2020 IN CASE OF NON-SUBMISSION OF THE SAME.
|
30-04-2026
|
NOT STARTED
|
6 |
ENAGAGE AN ACCREDITED PERSON FOR THIRD PARTY VERIFICATION AT PLINTH AND GROUND FLOOR ROOF LEVEL. UPON DETECTION OF UNAUTHORISED CONSTRUCTION IN THE THIRD PARTY CERIFICATION RPORT THE APPLICATNT SHALL BE IMPSED A FINE AS PRESCRIBED UNDER SUB-RULE 3 OF RULE 15 OF ODA (P&BS RULES,2020)
|
30-04-2026
|
NOT STARTED
|
7 |
ENSURE THAT THE COMPLETION CERTIFICATE IN FORM XVII AS APPENDED TO ODA CAF RULES 2016 IS ISSUED BY THE PROJECT MANAGEMENT ORGANISATION ENGAGED BY HIM ON COMPETION OF THE BUILDING FOR SUBMISSION OF THE SAME TO THE AUTHORITY FOR VERIFICATION AND ISSUEANCE OF OCCUPANCY CERTIFICATE.
|
30-04-2026
|
NOT STARTED
|
8 |
OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART.
|
30-04-2026
|
NOT STARTED
|
9 |
WHEREVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE,RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY.
|
30-04-2026
|
NOT STARTED
|
10 |
THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER WITHOUT PRIOR APPROVAL UNDER SECTION 16 OF THE ODA ACT, 1982.
|
30-04-2026
|
NOT STARTED
|
11 |
STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE – 47 OF ODA (PLANNING & BUILDING STANDARDS) RULES,2020
|
30-04-2026
|
NOT STARTED
|
12 |
ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS)RULES,2020.
|
30-04-2026
|
NOT STARTED
|
13 |
THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED/CLOSED IN ANY MANNER.
|
30-04-2026
|
NOT STARTED
|
14 |
AT LEAST 50% OF THE OPEN SPACE SHALL BE PERVIOUS AND PLANTATION @ ONE TREE PER 80 SQ.MTR. OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES, 2020.
|
30-04-2026
|
NOT STARTED
|
15 |
RAINWATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER.
|
30-04-2026
|
NOT STARTED
|
16 |
GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @ 6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA.
|
30-04-2026
|
NOT STARTED
|
17 |
AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER SUB-RULE (12) OF RULE 37 OF ODA (P&BS) RULES 2020.
|
30-04-2026
|
NOT STARTED
|
18 |
ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FORABSORPTION OF RAINWATER AND SEE PAGE INTO THE GROUND.
|
30-04-2026
|
NOT STARTED
|
19 |
HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR
|
30-04-2026
|
NOT STARTED
|
20 |
SPACE PER FLAT SHALL BE PROVIDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN12SQUARE METERS.
|
30-04-2026
|
NOT STARTED
|
21 |
ICT LANDING POINT AS PER RULE 57 OF ODA (P&BS) RULES, 2020 SHALL BE PROVIDED.
|
30-04-2026
|
NOT STARTED
|
22 |
STP AND OTHER UTILITIES, IF PROVIDED WITHIN MINIMUM SETBACK AREA SHALL NOT BE ALLOWED ABOVE GROUND LEVEL AND SHALL ONLY BE CONSTRUCTED BELOW GROUND LEVEL; AND THE SAME SHALL BE APPROPRIATELY COVERED FOR MOVEMENT OF VEHICLE/PEOPLE ABOVE IT.
|
30-04-2026
|
NOT STARTED
|
23 |
GUARD ROOM, ELECTRIC CABIN, SUB-STATION, AREA FOR GENERATOR SET, ATM, ETC, IF PROVIDED SHALL NOT BE ALLOWED WITHIN MINIMUM SETBACK AREA.
|
30-04-2026
|
NOT STARTED
|
24 |
THE APPLICANT SHALL OBTAIN INFRASTRUCTURAL SPECIFICATION AND SUBSEQUENT CLEARANCE WITH REGARD TO DEVELOPMENT OF INFRASGTRUCTURE FOR EIDP BEFORE COMMENCEMENT OF CONSTRUCTION.
|
30-04-2026
|
NOT STARTED
|
25 |
THE APPLICANT SHALL GET THE EXTERNAL INFRASTRUCTURE DEVELOPMENT PLAN (EIDP) APPROVED BY THE COMMITTEE AS SPECIFIED UNDER CLAUSE 3.2.3 OF THE SOP NOTIFIED VIDE NO. 2360/BDA DATED 18.01.2021AND EXECUTE THE APPROVED EIDP IN ACCORDANCE WITH CLAUSE NO. 3.2.4. AFTER COMPLETION OF THE EXTERNAL INFRASTRUCTURE, THE APPLICANT SHALL OBTAIN THE WRITTEN RECOMMENDATION OF THE EIDP COMMITTEE REGARDING SATISFACTORY COMPLETION OF INFRASTRUCTURE AS PER THE APPROVED EIDP. THE APPLICANT SHALL APPLY FOR ISSUE OF NOC FROM ENGINEER MEMBER, BDA AFTER RECOMMENDATION OF THE COMMITTEE.
|
30-04-2026
|
NOT STARTED
|
26 |
OCCUPANCY CERTIFICATE SHALL BE ISSUED ONLY AFTER OBTAINING THE NOC FROM ENGINEER MEMBER, BDA IN ACCORDANCE WITH CLAUSE 3.2.6.
|
30-04-2026
|
NOT STARTED
|
27 |
THE APPLICANT SHALL OBTAIN ORERA REGISTRATION AS PER THE AFFIDAVIT SUBMITTED BY APPLICANT AND SUBMIT THE ORERA REGISTRATION CERTIFICATE AT THE TIME OF SUBMISSION OF APPLICATION FOR ISSUE OF OCCUPANCY CERTIFICATE.
|
30-04-2026
|
NOT STARTED
|
28 |
THE OWNER/ APPLICANT/ TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/CLEARANCE GIVEN BY CENTRAL GROUND WATER AUTHORITY (CGWA) VIDE LETTER NO. CGWA/ NOC/ INF/ ORIG/2022/17054 DATED 17.11.2022.
|
30-04-2026
|
NOT STARTED
|
Updated Changes on 13-07-2023 |
29 |
PARKING SPACE MEASURING 673.40 SQM. AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE
|
30-04-2026
|
NOT STARTED
|
30 |
THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 9.14 MTR. IN WIDTH.
|
30-04-2026
|
NOT STARTED
|
31 |
PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES, FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS
|
30-04-2026
|
NOT STARTED
|
32 |
OBTAIN, WHEREVER APPLICABLE, FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK;
|
30-04-2026
|
NOT STARTED
|
33 |
SUBMIT STAGE WISE CONSTRUCTION REPORT. PENALITY SHALL BE IMPOSED AS PER RULE 14 OF ODA (P&BS) RULES 2020 IN CASE OF NON-SUBMISSION OF THE SAME.
|
30-04-2026
|
NOT STARTED
|
34 |
ENAGAGE AN ACCREDITED PERSON FOR THIRD PARTY VERIFICATION AT PLINTH AND GROUND FLOOR ROOF LEVEL. UPON DETECTION OF UNAUTHORISED CONSTRUCTION IN THE THIRD PARTY CERIFICATION RPORT THE APPLICATNT SHALL BE IMPSED A FINE AS PRESCRIBED UNDER SUB-RULE 3 OF RULE 15 OF ODA (P&BS RULES,2020)
|
30-04-2026
|
NOT STARTED
|
35 |
ENSURE THAT THE COMPLETION CERTIFICATE IN FORM XVII AS APPENDED TO ODA CAF RULES 2016 IS ISSUED BY THE PROJECT MANAGEMENT ORGANISATION ENGAGED BY HIM ON COMPETION OF THE BUILDING FOR SUBMISSION OF THE SAME TO THE AUTHORITY FOR VERIFICATION AND ISSUEANCE OF OCCUPANCY CERTIFICATE.
|
30-04-2026
|
NOT STARTED
|
36 |
OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART.
|
30-04-2026
|
NOT STARTED
|
37 |
WHEREVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE,RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY.
|
30-04-2026
|
NOT STARTED
|
38 |
THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER WITHOUT PRIOR APPROVAL UNDER SECTION 16 OF THE ODA ACT, 1982.
|
30-04-2026
|
NOT STARTED
|
39 |
STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE – 47 OF ODA (PLANNING & BUILDING STANDARDS) RULES,2020
|
30-04-2026
|
NOT STARTED
|
40 |
ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS)RULES,2020.
|
30-04-2026
|
NOT STARTED
|
41 |
THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED/CLOSED IN ANY MANNER.
|
30-04-2026
|
NOT STARTED
|
42 |
AT LEAST 50% OF THE OPEN SPACE SHALL BE PERVIOUS AND PLANTATION @ ONE TREE PER 80 SQ.MTR. OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES, 2020.
|
30-04-2026
|
NOT STARTED
|
43 |
RAINWATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER.
|
30-04-2026
|
NOT STARTED
|
44 |
GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @ 6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA.
|
30-04-2026
|
NOT STARTED
|
45 |
AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER SUB-RULE (12) OF RULE 37 OF ODA (P&BS) RULES 2020.
|
30-04-2026
|
NOT STARTED
|
46 |
ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FORABSORPTION OF RAINWATER AND SEE PAGE INTO THE GROUND.
|
30-04-2026
|
NOT STARTED
|
47 |
HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR
|
30-04-2026
|
NOT STARTED
|
48 |
SPACE PER FLAT SHALL BE PROVIDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN12SQUARE METERS.
|
30-04-2026
|
NOT STARTED
|
49 |
ICT LANDING POINT AS PER RULE 57 OF ODA (P&BS) RULES, 2020 SHALL BE PROVIDED.
|
30-04-2026
|
NOT STARTED
|
50 |
STP AND OTHER UTILITIES, IF PROVIDED WITHIN MINIMUM SETBACK AREA SHALL NOT BE ALLOWED ABOVE GROUND LEVEL AND SHALL ONLY BE CONSTRUCTED BELOW GROUND LEVEL; AND THE SAME SHALL BE APPROPRIATELY COVERED FOR MOVEMENT OF VEHICLE/PEOPLE ABOVE IT.
|
30-04-2026
|
NOT STARTED
|
51 |
GUARD ROOM, ELECTRIC CABIN, SUB-STATION, AREA FOR GENERATOR SET, ATM, ETC, IF PROVIDED SHALL NOT BE ALLOWED WITHIN MINIMUM SETBACK AREA.
|
30-04-2026
|
NOT STARTED
|
52 |
THE APPLICANT SHALL OBTAIN INFRASTRUCTURAL SPECIFICATION AND SUBSEQUENT CLEARANCE WITH REGARD TO DEVELOPMENT OF INFRASGTRUCTURE FOR EIDP BEFORE COMMENCEMENT OF CONSTRUCTION.
|
30-04-2026
|
NOT STARTED
|
53 |
THE APPLICANT SHALL GET THE EXTERNAL INFRASTRUCTURE DEVELOPMENT PLAN (EIDP) APPROVED BY THE COMMITTEE AS SPECIFIED UNDER CLAUSE 3.2.3 OF THE SOP NOTIFIED VIDE NO. 2360/BDA DATED 18.01.2021AND EXECUTE THE APPROVED EIDP IN ACCORDANCE WITH CLAUSE NO. 3.2.4. AFTER COMPLETION OF THE EXTERNAL INFRASTRUCTURE, THE APPLICANT SHALL OBTAIN THE WRITTEN RECOMMENDATION OF THE EIDP COMMITTEE REGARDING SATISFACTORY COMPLETION OF INFRASTRUCTURE AS PER THE APPROVED EIDP. THE APPLICANT SHALL APPLY FOR ISSUE OF NOC FROM ENGINEER MEMBER, BDA AFTER RECOMMENDATION OF THE COMMITTEE.
|
30-04-2026
|
NOT STARTED
|
54 |
OCCUPANCY CERTIFICATE SHALL BE ISSUED ONLY AFTER OBTAINING THE NOC FROM ENGINEER MEMBER, BDA IN ACCORDANCE WITH CLAUSE 3.2.6.
|
30-04-2026
|
NOT STARTED
|
55 |
THE APPLICANT SHALL OBTAIN ORERA REGISTRATION AS PER THE AFFIDAVIT SUBMITTED BY APPLICANT AND SUBMIT THE ORERA REGISTRATION CERTIFICATE AT THE TIME OF SUBMISSION OF APPLICATION FOR ISSUE OF OCCUPANCY CERTIFICATE.
|
30-04-2026
|
NOT STARTED
|
56 |
THE OWNER/ APPLICANT/ TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/CLEARANCE GIVEN BY CENTRAL GROUND WATER AUTHORITY (CGWA) VIDE LETTER NO. CGWA/ NOC/ INF/ ORIG/2022/17054 DATED 17.11.2022.
|
30-04-2026
|
NOT STARTED
|
Updated Changes on 30-10-2023 |
57 |
PARKING SPACE MEASURING 673.40 SQM. AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE
|
30-04-2026
|
NOT STARTED
|
58 |
THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 9.14 MTR. IN WIDTH.
|
30-04-2026
|
NOT STARTED
|
59 |
PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES, FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS
|
30-04-2026
|
NOT STARTED
|
60 |
OBTAIN, WHEREVER APPLICABLE, FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK;
|
30-04-2026
|
NOT STARTED
|
61 |
SUBMIT STAGE WISE CONSTRUCTION REPORT. PENALITY SHALL BE IMPOSED AS PER RULE 14 OF ODA (P&BS) RULES 2020 IN CASE OF NON-SUBMISSION OF THE SAME.
|
30-04-2026
|
NOT STARTED
|
62 |
ENAGAGE AN ACCREDITED PERSON FOR THIRD PARTY VERIFICATION AT PLINTH AND GROUND FLOOR ROOF LEVEL. UPON DETECTION OF UNAUTHORISED CONSTRUCTION IN THE THIRD PARTY CERIFICATION RPORT THE APPLICATNT SHALL BE IMPSED A FINE AS PRESCRIBED UNDER SUB-RULE 3 OF RULE 15 OF ODA (P&BS RULES,2020)
|
30-04-2026
|
NOT STARTED
|
63 |
ENSURE THAT THE COMPLETION CERTIFICATE IN FORM XVII AS APPENDED TO ODA CAF RULES 2016 IS ISSUED BY THE PROJECT MANAGEMENT ORGANISATION ENGAGED BY HIM ON COMPETION OF THE BUILDING FOR SUBMISSION OF THE SAME TO THE AUTHORITY FOR VERIFICATION AND ISSUEANCE OF OCCUPANCY CERTIFICATE.
|
30-04-2026
|
NOT STARTED
|
64 |
OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART.
|
30-04-2026
|
NOT STARTED
|
65 |
WHEREVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE,RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY.
|
30-04-2026
|
NOT STARTED
|
66 |
THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER WITHOUT PRIOR APPROVAL UNDER SECTION 16 OF THE ODA ACT, 1982.
|
30-04-2026
|
NOT STARTED
|
67 |
STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE – 47 OF ODA (PLANNING & BUILDING STANDARDS) RULES,2020
|
30-04-2026
|
NOT STARTED
|
68 |
ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS)RULES,2020.
|
30-04-2026
|
NOT STARTED
|
69 |
THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED/CLOSED IN ANY MANNER.
|
30-04-2026
|
NOT STARTED
|
70 |
AT LEAST 50% OF THE OPEN SPACE SHALL BE PERVIOUS AND PLANTATION @ ONE TREE PER 80 SQ.MTR. OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES, 2020.
|
30-04-2026
|
NOT STARTED
|
71 |
RAINWATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER.
|
30-04-2026
|
NOT STARTED
|
72 |
GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @ 6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA.
|
30-04-2026
|
NOT STARTED
|
73 |
AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER SUB-RULE (12) OF RULE 37 OF ODA (P&BS) RULES 2020.
|
30-04-2026
|
NOT STARTED
|
74 |
ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FORABSORPTION OF RAINWATER AND SEE PAGE INTO THE GROUND.
|
30-04-2026
|
NOT STARTED
|
75 |
HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR
|
30-04-2026
|
NOT STARTED
|
76 |
SPACE PER FLAT SHALL BE PROVIDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN12SQUARE METERS.
|
30-04-2026
|
NOT STARTED
|
77 |
ICT LANDING POINT AS PER RULE 57 OF ODA (P&BS) RULES, 2020 SHALL BE PROVIDED.
|
30-04-2026
|
NOT STARTED
|
78 |
STP AND OTHER UTILITIES, IF PROVIDED WITHIN MINIMUM SETBACK AREA SHALL NOT BE ALLOWED ABOVE GROUND LEVEL AND SHALL ONLY BE CONSTRUCTED BELOW GROUND LEVEL; AND THE SAME SHALL BE APPROPRIATELY COVERED FOR MOVEMENT OF VEHICLE/PEOPLE ABOVE IT.
|
30-04-2026
|
NOT STARTED
|
79 |
GUARD ROOM, ELECTRIC CABIN, SUB-STATION, AREA FOR GENERATOR SET, ATM, ETC, IF PROVIDED SHALL NOT BE ALLOWED WITHIN MINIMUM SETBACK AREA.
|
30-04-2026
|
NOT STARTED
|
80 |
THE APPLICANT SHALL OBTAIN INFRASTRUCTURAL SPECIFICATION AND SUBSEQUENT CLEARANCE WITH REGARD TO DEVELOPMENT OF INFRASGTRUCTURE FOR EIDP BEFORE COMMENCEMENT OF CONSTRUCTION.
|
30-04-2026
|
NOT STARTED
|
81 |
THE APPLICANT SHALL GET THE EXTERNAL INFRASTRUCTURE DEVELOPMENT PLAN (EIDP) APPROVED BY THE COMMITTEE AS SPECIFIED UNDER CLAUSE 3.2.3 OF THE SOP NOTIFIED VIDE NO. 2360/BDA DATED 18.01.2021AND EXECUTE THE APPROVED EIDP IN ACCORDANCE WITH CLAUSE NO. 3.2.4. AFTER COMPLETION OF THE EXTERNAL INFRASTRUCTURE, THE APPLICANT SHALL OBTAIN THE WRITTEN RECOMMENDATION OF THE EIDP COMMITTEE REGARDING SATISFACTORY COMPLETION OF INFRASTRUCTURE AS PER THE APPROVED EIDP. THE APPLICANT SHALL APPLY FOR ISSUE OF NOC FROM ENGINEER MEMBER, BDA AFTER RECOMMENDATION OF THE COMMITTEE.
|
30-04-2026
|
NOT STARTED
|
82 |
OCCUPANCY CERTIFICATE SHALL BE ISSUED ONLY AFTER OBTAINING THE NOC FROM ENGINEER MEMBER, BDA IN ACCORDANCE WITH CLAUSE 3.2.6.
|
30-04-2026
|
NOT STARTED
|
83 |
THE APPLICANT SHALL OBTAIN ORERA REGISTRATION AS PER THE AFFIDAVIT SUBMITTED BY APPLICANT AND SUBMIT THE ORERA REGISTRATION CERTIFICATE AT THE TIME OF SUBMISSION OF APPLICATION FOR ISSUE OF OCCUPANCY CERTIFICATE.
|
30-04-2026
|
NOT STARTED
|
84 |
THE OWNER/ APPLICANT/ TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/CLEARANCE GIVEN BY CENTRAL GROUND WATER AUTHORITY (CGWA) VIDE LETTER NO. CGWA/ NOC/ INF/ ORIG/2022/17054 DATED 17.11.2022.
|
30-04-2026
|
NOT STARTED
|
Updated Changes on 02-04-2024 |
85 |
PARKING SPACE MEASURING 673.40 SQM. AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE
|
30-04-2026
|
NOT STARTED
|
86 |
THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 9.14 MTR. IN WIDTH.
|
30-04-2026
|
NOT STARTED
|
87 |
PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES, FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS
|
30-04-2026
|
NOT STARTED
|
88 |
OBTAIN, WHEREVER APPLICABLE, FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK;
|
30-04-2026
|
NOT STARTED
|
89 |
SUBMIT STAGE WISE CONSTRUCTION REPORT. PENALITY SHALL BE IMPOSED AS PER RULE 14 OF ODA (P&BS) RULES 2020 IN CASE OF NON-SUBMISSION OF THE SAME.
|
30-04-2026
|
NOT STARTED
|
90 |
ENAGAGE AN ACCREDITED PERSON FOR THIRD PARTY VERIFICATION AT PLINTH AND GROUND FLOOR ROOF LEVEL. UPON DETECTION OF UNAUTHORISED CONSTRUCTION IN THE THIRD PARTY CERIFICATION RPORT THE APPLICATNT SHALL BE IMPSED A FINE AS PRESCRIBED UNDER SUB-RULE 3 OF RULE 15 OF ODA (P&BS RULES,2020)
|
30-04-2026
|
NOT STARTED
|
91 |
ENSURE THAT THE COMPLETION CERTIFICATE IN FORM XVII AS APPENDED TO ODA CAF RULES 2016 IS ISSUED BY THE PROJECT MANAGEMENT ORGANISATION ENGAGED BY HIM ON COMPETION OF THE BUILDING FOR SUBMISSION OF THE SAME TO THE AUTHORITY FOR VERIFICATION AND ISSUEANCE OF OCCUPANCY CERTIFICATE.
|
30-04-2026
|
NOT STARTED
|
92 |
OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART.
|
30-04-2026
|
NOT STARTED
|
93 |
WHEREVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE,RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY.
|
30-04-2026
|
NOT STARTED
|
94 |
THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER WITHOUT PRIOR APPROVAL UNDER SECTION 16 OF THE ODA ACT, 1982.
|
30-04-2026
|
NOT STARTED
|
95 |
STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE – 47 OF ODA (PLANNING & BUILDING STANDARDS) RULES,2020
|
30-04-2026
|
NOT STARTED
|
96 |
ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS)RULES,2020.
|
30-04-2026
|
NOT STARTED
|
97 |
THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED/CLOSED IN ANY MANNER.
|
30-04-2026
|
NOT STARTED
|
98 |
AT LEAST 50% OF THE OPEN SPACE SHALL BE PERVIOUS AND PLANTATION @ ONE TREE PER 80 SQ.MTR. OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES, 2020.
|
30-04-2026
|
NOT STARTED
|
99 |
RAINWATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER.
|
30-04-2026
|
NOT STARTED
|
100 |
GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @ 6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA.
|
30-04-2026
|
NOT STARTED
|
101 |
AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER SUB-RULE (12) OF RULE 37 OF ODA (P&BS) RULES 2020.
|
30-04-2026
|
NOT STARTED
|
102 |
ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FORABSORPTION OF RAINWATER AND SEE PAGE INTO THE GROUND.
|
30-04-2026
|
NOT STARTED
|
103 |
HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR
|
30-04-2026
|
NOT STARTED
|
104 |
SPACE PER FLAT SHALL BE PROVIDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN12SQUARE METERS.
|
30-04-2026
|
NOT STARTED
|
105 |
ICT LANDING POINT AS PER RULE 57 OF ODA (P&BS) RULES, 2020 SHALL BE PROVIDED.
|
30-04-2026
|
NOT STARTED
|
106 |
STP AND OTHER UTILITIES, IF PROVIDED WITHIN MINIMUM SETBACK AREA SHALL NOT BE ALLOWED ABOVE GROUND LEVEL AND SHALL ONLY BE CONSTRUCTED BELOW GROUND LEVEL; AND THE SAME SHALL BE APPROPRIATELY COVERED FOR MOVEMENT OF VEHICLE/PEOPLE ABOVE IT.
|
30-04-2026
|
NOT STARTED
|
107 |
GUARD ROOM, ELECTRIC CABIN, SUB-STATION, AREA FOR GENERATOR SET, ATM, ETC, IF PROVIDED SHALL NOT BE ALLOWED WITHIN MINIMUM SETBACK AREA.
|
30-04-2026
|
NOT STARTED
|
108 |
THE APPLICANT SHALL OBTAIN INFRASTRUCTURAL SPECIFICATION AND SUBSEQUENT CLEARANCE WITH REGARD TO DEVELOPMENT OF INFRASGTRUCTURE FOR EIDP BEFORE COMMENCEMENT OF CONSTRUCTION.
|
30-04-2026
|
NOT STARTED
|
109 |
THE APPLICANT SHALL GET THE EXTERNAL INFRASTRUCTURE DEVELOPMENT PLAN (EIDP) APPROVED BY THE COMMITTEE AS SPECIFIED UNDER CLAUSE 3.2.3 OF THE SOP NOTIFIED VIDE NO. 2360/BDA DATED 18.01.2021AND EXECUTE THE APPROVED EIDP IN ACCORDANCE WITH CLAUSE NO. 3.2.4. AFTER COMPLETION OF THE EXTERNAL INFRASTRUCTURE, THE APPLICANT SHALL OBTAIN THE WRITTEN RECOMMENDATION OF THE EIDP COMMITTEE REGARDING SATISFACTORY COMPLETION OF INFRASTRUCTURE AS PER THE APPROVED EIDP. THE APPLICANT SHALL APPLY FOR ISSUE OF NOC FROM ENGINEER MEMBER, BDA AFTER RECOMMENDATION OF THE COMMITTEE.
|
30-04-2026
|
NOT STARTED
|
110 |
OCCUPANCY CERTIFICATE SHALL BE ISSUED ONLY AFTER OBTAINING THE NOC FROM ENGINEER MEMBER, BDA IN ACCORDANCE WITH CLAUSE 3.2.6.
|
30-04-2026
|
NOT STARTED
|
111 |
THE APPLICANT SHALL OBTAIN ORERA REGISTRATION AS PER THE AFFIDAVIT SUBMITTED BY APPLICANT AND SUBMIT THE ORERA REGISTRATION CERTIFICATE AT THE TIME OF SUBMISSION OF APPLICATION FOR ISSUE OF OCCUPANCY CERTIFICATE.
|
30-04-2026
|
NOT STARTED
|
112 |
THE OWNER/ APPLICANT/ TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/CLEARANCE GIVEN BY CENTRAL GROUND WATER AUTHORITY (CGWA) VIDE LETTER NO. CGWA/ NOC/ INF/ ORIG/2022/17054 DATED 17.11.2022.
|
30-04-2026
|
NOT STARTED
|
Updated Changes on 30-04-2024 |
113 |
PARKING SPACE MEASURING 673.40 SQM. AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE
|
30-04-2026
|
NOT STARTED
|
114 |
THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 9.14 MTR. IN WIDTH.
|
30-04-2026
|
NOT STARTED
|
115 |
PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES, FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS
|
30-04-2026
|
NOT STARTED
|
116 |
OBTAIN, WHEREVER APPLICABLE, FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK;
|
30-04-2026
|
NOT STARTED
|
117 |
SUBMIT STAGE WISE CONSTRUCTION REPORT. PENALITY SHALL BE IMPOSED AS PER RULE 14 OF ODA (P&BS) RULES 2020 IN CASE OF NON-SUBMISSION OF THE SAME.
|
30-04-2026
|
NOT STARTED
|
118 |
ENAGAGE AN ACCREDITED PERSON FOR THIRD PARTY VERIFICATION AT PLINTH AND GROUND FLOOR ROOF LEVEL. UPON DETECTION OF UNAUTHORISED CONSTRUCTION IN THE THIRD PARTY CERIFICATION RPORT THE APPLICATNT SHALL BE IMPSED A FINE AS PRESCRIBED UNDER SUB-RULE 3 OF RULE 15 OF ODA (P&BS RULES,2020)
|
30-04-2026
|
NOT STARTED
|
119 |
ENSURE THAT THE COMPLETION CERTIFICATE IN FORM XVII AS APPENDED TO ODA CAF RULES 2016 IS ISSUED BY THE PROJECT MANAGEMENT ORGANISATION ENGAGED BY HIM ON COMPETION OF THE BUILDING FOR SUBMISSION OF THE SAME TO THE AUTHORITY FOR VERIFICATION AND ISSUEANCE OF OCCUPANCY CERTIFICATE.
|
30-04-2026
|
NOT STARTED
|
120 |
OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART.
|
30-04-2026
|
NOT STARTED
|
121 |
WHEREVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE,RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY.
|
30-04-2026
|
NOT STARTED
|
122 |
THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER WITHOUT PRIOR APPROVAL UNDER SECTION 16 OF THE ODA ACT, 1982.
|
30-04-2026
|
NOT STARTED
|
123 |
STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE – 47 OF ODA (PLANNING & BUILDING STANDARDS) RULES,2020
|
30-04-2026
|
NOT STARTED
|
124 |
ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS)RULES,2020.
|
30-04-2026
|
NOT STARTED
|
125 |
THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED/CLOSED IN ANY MANNER.
|
30-04-2026
|
NOT STARTED
|
126 |
AT LEAST 50% OF THE OPEN SPACE SHALL BE PERVIOUS AND PLANTATION @ ONE TREE PER 80 SQ.MTR. OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES, 2020.
|
30-04-2026
|
NOT STARTED
|
127 |
RAINWATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER.
|
30-04-2026
|
NOT STARTED
|
128 |
GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @ 6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA.
|
30-04-2026
|
NOT STARTED
|
129 |
AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER SUB-RULE (12) OF RULE 37 OF ODA (P&BS) RULES 2020.
|
30-04-2026
|
NOT STARTED
|
130 |
ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FORABSORPTION OF RAINWATER AND SEE PAGE INTO THE GROUND.
|
30-04-2026
|
NOT STARTED
|
131 |
HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR
|
30-04-2026
|
NOT STARTED
|
132 |
SPACE PER FLAT SHALL BE PROVIDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN12SQUARE METERS.
|
30-04-2026
|
NOT STARTED
|
133 |
ICT LANDING POINT AS PER RULE 57 OF ODA (P&BS) RULES, 2020 SHALL BE PROVIDED.
|
30-04-2026
|
NOT STARTED
|
134 |
STP AND OTHER UTILITIES, IF PROVIDED WITHIN MINIMUM SETBACK AREA SHALL NOT BE ALLOWED ABOVE GROUND LEVEL AND SHALL ONLY BE CONSTRUCTED BELOW GROUND LEVEL; AND THE SAME SHALL BE APPROPRIATELY COVERED FOR MOVEMENT OF VEHICLE/PEOPLE ABOVE IT.
|
30-04-2026
|
NOT STARTED
|
135 |
GUARD ROOM, ELECTRIC CABIN, SUB-STATION, AREA FOR GENERATOR SET, ATM, ETC, IF PROVIDED SHALL NOT BE ALLOWED WITHIN MINIMUM SETBACK AREA.
|
30-04-2026
|
NOT STARTED
|
136 |
THE APPLICANT SHALL OBTAIN INFRASTRUCTURAL SPECIFICATION AND SUBSEQUENT CLEARANCE WITH REGARD TO DEVELOPMENT OF INFRASGTRUCTURE FOR EIDP BEFORE COMMENCEMENT OF CONSTRUCTION.
|
30-04-2026
|
NOT STARTED
|
137 |
THE APPLICANT SHALL GET THE EXTERNAL INFRASTRUCTURE DEVELOPMENT PLAN (EIDP) APPROVED BY THE COMMITTEE AS SPECIFIED UNDER CLAUSE 3.2.3 OF THE SOP NOTIFIED VIDE NO. 2360/BDA DATED 18.01.2021AND EXECUTE THE APPROVED EIDP IN ACCORDANCE WITH CLAUSE NO. 3.2.4. AFTER COMPLETION OF THE EXTERNAL INFRASTRUCTURE, THE APPLICANT SHALL OBTAIN THE WRITTEN RECOMMENDATION OF THE EIDP COMMITTEE REGARDING SATISFACTORY COMPLETION OF INFRASTRUCTURE AS PER THE APPROVED EIDP. THE APPLICANT SHALL APPLY FOR ISSUE OF NOC FROM ENGINEER MEMBER, BDA AFTER RECOMMENDATION OF THE COMMITTEE.
|
30-04-2026
|
NOT STARTED
|
138 |
OCCUPANCY CERTIFICATE SHALL BE ISSUED ONLY AFTER OBTAINING THE NOC FROM ENGINEER MEMBER, BDA IN ACCORDANCE WITH CLAUSE 3.2.6.
|
30-04-2026
|
NOT STARTED
|
139 |
THE APPLICANT SHALL OBTAIN ORERA REGISTRATION AS PER THE AFFIDAVIT SUBMITTED BY APPLICANT AND SUBMIT THE ORERA REGISTRATION CERTIFICATE AT THE TIME OF SUBMISSION OF APPLICATION FOR ISSUE OF OCCUPANCY CERTIFICATE.
|
30-04-2026
|
NOT STARTED
|
140 |
THE OWNER/ APPLICANT/ TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/CLEARANCE GIVEN BY CENTRAL GROUND WATER AUTHORITY (CGWA) VIDE LETTER NO. CGWA/ NOC/ INF/ ORIG/2022/17054 DATED 17.11.2022.
|
30-04-2026
|
NOT STARTED
|