Promoter Details
Promoter Name :
KALINGA KESHARI RATH
Project Name :
Evos Avante Phase -I
Project Location :
(Residential Project, Stilt + 4 storied Residential Apartment (MIG Category) building, No. of Units-24)

Form- I

A. Promoter's Details

:  M/s. Evos Buildcon Private Limited :  Private Company
:  U70101OR2010PTC012674 :View
NA :   Plot No.- M/76, Housing Board Colony, Baramunda, Ps- Bharatpur, Bhubaneswar, Dist- Khordha, Odisha- 751003
:  Plot No.- M/76, Housing Board Colony, Baramunda, PS- Bharatpur, Bhubaneswar, Dist- Khordha, Odisha- 751003. :  kkrath@evos.co.in
:  2355100 :  9040051152
:  AACCE5477G :View
:  11 :  N/A
:  https://evosbuildcon.com/

B. Details of Board of Directors / Partners / MC Members

:  KALINGA KESHARI RATH :  
:  Managing Director :  ALWPR1547G
:PAN Card :  kkrath@evos.co.in
:  B.TECH, MBA :  9040051152
:  11 YEARS
:  Yes :  NA
:  SRUJANIKA MISHRA :  
:  Director :  DYZPM0589Q
:PAN Card :  kkrath@evos.co.in
:  B.A. :  9040051152
:  6 YEARS
:  Yes :  NA
:  DEEPAK DAS :  
:  Director :  BGDPD0699E
:PAN Card :  deepakds961@gmail.com
:  Graduation and Diploma in H.M :  9040077993
:  5 YEARS
:  Yes :  NA

Annexure-1

Details of last projects already implemented (Ongoing or Complete)

Annexure-2

Details of the project to be registered

:   New :  Evos Avante Phase -I
:  Residential :  (Residential Project, Stilt + 4 storied Residential Apartment (MIG Category) building, No. of Units-24)
:  Khordha :  Jatni
:  752054 :  Development Authority
:  Bhubaneswar Development Authority
:  S+4 :  NA

Land Details of the Project

:  601/2324 :  229/1407
:  JAGASARA :  2295
:  No :  1081.12
No :  View
:  View
:  Promoter

Development Agreement

: No

Building Plan

  View   View
  Download site plan 30-04-2026
01-05-2023

Conditions of building plan approval

Sl. No. Description of Conditions Schedule date of compliance Present Status
1 PARKING SPACE MEASURING 673.40 SQM. AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE 30-04-2026 NOT STARTED
2 THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 9.14 MTR. IN WIDTH. 30-04-2026 NOT STARTED
3 PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES, FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS 30-04-2026 NOT STARTED
4 OBTAIN, WHEREVER APPLICABLE, FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK; 30-04-2026 NOT STARTED
5 SUBMIT STAGE WISE CONSTRUCTION REPORT. PENALITY SHALL BE IMPOSED AS PER RULE 14 OF ODA (P&BS) RULES 2020 IN CASE OF NON-SUBMISSION OF THE SAME. 30-04-2026 NOT STARTED
6 ENAGAGE AN ACCREDITED PERSON FOR THIRD PARTY VERIFICATION AT PLINTH AND GROUND FLOOR ROOF LEVEL. UPON DETECTION OF UNAUTHORISED CONSTRUCTION IN THE THIRD PARTY CERIFICATION RPORT THE APPLICATNT SHALL BE IMPSED A FINE AS PRESCRIBED UNDER SUB-RULE 3 OF RULE 15 OF ODA (P&BS RULES,2020) 30-04-2026 NOT STARTED
7 ENSURE THAT THE COMPLETION CERTIFICATE IN FORM XVII AS APPENDED TO ODA CAF RULES 2016 IS ISSUED BY THE PROJECT MANAGEMENT ORGANISATION ENGAGED BY HIM ON COMPETION OF THE BUILDING FOR SUBMISSION OF THE SAME TO THE AUTHORITY FOR VERIFICATION AND ISSUEANCE OF OCCUPANCY CERTIFICATE. 30-04-2026 NOT STARTED
8 OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART. 30-04-2026 NOT STARTED
9 WHEREVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE,RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY. 30-04-2026 NOT STARTED
10 THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER WITHOUT PRIOR APPROVAL UNDER SECTION 16 OF THE ODA ACT, 1982. 30-04-2026 NOT STARTED
11 STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE – 47 OF ODA (PLANNING & BUILDING STANDARDS) RULES,2020 30-04-2026 NOT STARTED
12 ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS)RULES,2020. 30-04-2026 NOT STARTED
13 THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED/CLOSED IN ANY MANNER. 30-04-2026 NOT STARTED
14 AT LEAST 50% OF THE OPEN SPACE SHALL BE PERVIOUS AND PLANTATION @ ONE TREE PER 80 SQ.MTR. OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES, 2020. 30-04-2026 NOT STARTED
15 RAINWATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER. 30-04-2026 NOT STARTED
16 GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @ 6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA. 30-04-2026 NOT STARTED
17 AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER SUB-RULE (12) OF RULE 37 OF ODA (P&BS) RULES 2020. 30-04-2026 NOT STARTED
18 ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FORABSORPTION OF RAINWATER AND SEE PAGE INTO THE GROUND. 30-04-2026 NOT STARTED
19 HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR 30-04-2026 NOT STARTED
20 SPACE PER FLAT SHALL BE PROVIDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN12SQUARE METERS. 30-04-2026 NOT STARTED
21 ICT LANDING POINT AS PER RULE 57 OF ODA (P&BS) RULES, 2020 SHALL BE PROVIDED. 30-04-2026 NOT STARTED
22 STP AND OTHER UTILITIES, IF PROVIDED WITHIN MINIMUM SETBACK AREA SHALL NOT BE ALLOWED ABOVE GROUND LEVEL AND SHALL ONLY BE CONSTRUCTED BELOW GROUND LEVEL; AND THE SAME SHALL BE APPROPRIATELY COVERED FOR MOVEMENT OF VEHICLE/PEOPLE ABOVE IT. 30-04-2026 NOT STARTED
23 GUARD ROOM, ELECTRIC CABIN, SUB-STATION, AREA FOR GENERATOR SET, ATM, ETC, IF PROVIDED SHALL NOT BE ALLOWED WITHIN MINIMUM SETBACK AREA. 30-04-2026 NOT STARTED
24 THE APPLICANT SHALL OBTAIN INFRASTRUCTURAL SPECIFICATION AND SUBSEQUENT CLEARANCE WITH REGARD TO DEVELOPMENT OF INFRASGTRUCTURE FOR EIDP BEFORE COMMENCEMENT OF CONSTRUCTION. 30-04-2026 NOT STARTED
25 THE APPLICANT SHALL GET THE EXTERNAL INFRASTRUCTURE DEVELOPMENT PLAN (EIDP) APPROVED BY THE COMMITTEE AS SPECIFIED UNDER CLAUSE 3.2.3 OF THE SOP NOTIFIED VIDE NO. 2360/BDA DATED 18.01.2021AND EXECUTE THE APPROVED EIDP IN ACCORDANCE WITH CLAUSE NO. 3.2.4. AFTER COMPLETION OF THE EXTERNAL INFRASTRUCTURE, THE APPLICANT SHALL OBTAIN THE WRITTEN RECOMMENDATION OF THE EIDP COMMITTEE REGARDING SATISFACTORY COMPLETION OF INFRASTRUCTURE AS PER THE APPROVED EIDP. THE APPLICANT SHALL APPLY FOR ISSUE OF NOC FROM ENGINEER MEMBER, BDA AFTER RECOMMENDATION OF THE COMMITTEE. 30-04-2026 NOT STARTED
26 OCCUPANCY CERTIFICATE SHALL BE ISSUED ONLY AFTER OBTAINING THE NOC FROM ENGINEER MEMBER, BDA IN ACCORDANCE WITH CLAUSE 3.2.6. 30-04-2026 NOT STARTED
27 THE APPLICANT SHALL OBTAIN ORERA REGISTRATION AS PER THE AFFIDAVIT SUBMITTED BY APPLICANT AND SUBMIT THE ORERA REGISTRATION CERTIFICATE AT THE TIME OF SUBMISSION OF APPLICATION FOR ISSUE OF OCCUPANCY CERTIFICATE. 30-04-2026 NOT STARTED
28 THE OWNER/ APPLICANT/ TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/CLEARANCE GIVEN BY CENTRAL GROUND WATER AUTHORITY (CGWA) VIDE LETTER NO. CGWA/ NOC/ INF/ ORIG/2022/17054 DATED 17.11.2022. 30-04-2026 NOT STARTED

Layout Plan

: Yes :  View

Location Map with geo-coordinates of bend points

Point No. Latitude Longitude
1 20°15'06.6"N 85°43'15.0"E
2 20°15'06.6"N 85°43'14.6"E
3 20°15'06.2"N 85°43'14.5"E
4 20°15'06.4"N 85°43'13.8"E
5 20°15'07.1"N 85°43'14.2"E
6 20°15'07.6"N 85°43'14.5"E
7 20°15'07.5"N 85°43'15.1"E
8 20°15'07.2"N 85°43'15.1"E
9 20°15'07.1"N 85°43'15.2"E
View

Milestone of Project Construction

Description* Scheduled date of completion Current Status Site Images
Site Development 05-05-2023 IN PROGRESS
Roof Casting NA NA NA
Ground Floor/Stilt Floor 30-09-2023 NOT STARTED NA
1 Floor 30-11-2023 NOT STARTED NA
2 Floor 31-01-2024 NOT STARTED NA
3 Floor 31-03-2024 NOT STARTED NA
4 Floor 31-05-2024 NOT STARTED NA
Brick Work & Plastering NA NA NA
Ground Floor/Stilt Floor 31-03-2024 NOT STARTED NA
1 Floor 15-05-2024 NOT STARTED NA
2 Floor 30-06-2024 NOT STARTED NA
3 Floor 15-08-2024 NOT STARTED NA
4 Floor 30-09-2024 NOT STARTED NA
Electrical Works 28-02-2025 NOT STARTED NA
Concealed Cabling including Plugs & switches 28-02-2025 NOT STARTED NA
Installation & Charging of Transformer 28-02-2025 NOT STARTED NA
Connection to Flats/Apartments 28-02-2025 NOT STARTED NA
PH works 31-07-2025 NOT STARTED NA
Laying of concealed Pipes 31-07-2025 NOT STARTED NA
PH Fittings 31-07-2025 NOT STARTED NA
Overhead Water Tanks 31-07-2025 NOT STARTED NA
Water Supply Connection to all units 31-07-2025 NOT STARTED NA
STP construction and completion 31-07-2025 NOT STARTED NA
Distempering & Colouring of all units and exteriors 30-09-2025 NOT STARTED NA
Fixation of doors and windows 30-11-2025 NOT STARTED NA
Scheduled Date of handing over possession 01-06-2026 NOT STARTED NA
Development of common areas, parks, gardens etc 31-01-2026 NOT STARTED NA
Site Development 05-05-2023 IN PROGRESS
NA NA NA NA
Ground Floor/Stilt Floor 30-09-2023 NOT STARTED NA
1 Floor 30-11-2023 NOT STARTED NA
2 Floor 31-01-2024 NOT STARTED NA
3 Floor 31-03-2024 NOT STARTED NA
4 Floor 31-05-2024 NOT STARTED NA
NA NA NA NA
Ground Floor/Stilt Floor 31-03-2024 NOT STARTED NA
1 Floor 15-05-2024 NOT STARTED NA
2 Floor 30-06-2024 NOT STARTED NA
3 Floor 15-08-2024 NOT STARTED NA
4 Floor 30-09-2024 NOT STARTED NA
Electrical Works 28-02-2025 NOT STARTED NA
Concealed Cabling including Plugs & switches 28-02-2025 NOT STARTED NA
Installation & Charging of Transformer 28-02-2025 NOT STARTED NA
Connection to Flats/Apartments 28-02-2025 NOT STARTED NA
PH works 31-07-2025 NOT STARTED NA
Laying of concealed Pipes 31-07-2025 NOT STARTED NA
PH Fittings 31-07-2025 NOT STARTED NA
Overhead Water Tanks 31-07-2025 NOT STARTED NA
Water Supply Connection to all units 31-07-2025 NOT STARTED NA
STP construction and completion 31-07-2025 NOT STARTED NA
Distempering & Colouring of all units and exteriors 30-09-2025 NOT STARTED NA
Fixation of doors and windows 30-11-2025 NOT STARTED NA
Scheduled Date of handing over possession 01-06-2026 NOT STARTED NA
Development of common areas, parks, gardens etc 31-01-2026 NOT STARTED NA
Site Development 05-05-2023 IN PROGRESS NA
NA 17-11-2023 IN PROGRESS
Ground Floor/Stilt Floor 30-09-2023 IN PROGRESS
1 Floor 30-11-2023 IN PROGRESS
2 Floor 31-01-2024 IN PROGRESS
3 Floor 31-03-2024 NOT STARTED NA
4 Floor 31-05-2024 31-05-2024 NA
NA 31-05-2024 31-05-2024 NA
Ground Floor/Stilt Floor 31-03-2024 NOT STARTED NA
1 Floor 15-05-2024 NOT STARTED NA
2 Floor 30-06-2024 NOT STARTED NA
3 Floor 15-08-2024 NOT STARTED NA
4 Floor 30-09-2024 NOT STARTED NA
Electrical Works 28-02-2025 NOT STARTED NA
Concealed Cabling including Plugs & switches 28-02-2025 NOT STARTED NA
Installation & Charging of Transformer 28-02-2025 NOT STARTED NA
Connection to Flats/Apartments 28-02-2025 NOT STARTED NA
PH works 31-07-2025 NOT STARTED NA
Laying of concealed Pipes 31-07-2025 NOT STARTED NA
PH Fittings 31-07-2025 NOT STARTED NA
Overhead Water Tanks 31-07-2025 NOT STARTED NA
Water Supply Connection to all units 31-07-2025 NOT STARTED NA
STP construction and completion 31-07-2025 NOT STARTED NA
Distempering & Colouring of all units and exteriors 30-09-2025 NOT STARTED NA
Fixation of doors and windows 30-11-2025 NOT STARTED NA
Scheduled Date of handing over possession 01-06-2026 NOT STARTED NA
Development of common areas, parks, gardens etc 31-01-2026 NOT STARTED NA
Site Development 05-05-2023 IN PROGRESS
NA 17-11-2023 IN PROGRESS
Ground Floor/Stilt Floor 30-09-2023 IN PROGRESS
1 Floor 30-11-2023 IN PROGRESS
2 Floor 31-01-2024 IN PROGRESS
3 Floor 31-03-2024 IN PROGRESS
4 Floor 31-05-2024 31-05-2024 NA
NA 31-05-2024 31-05-2024 NA
Ground Floor/Stilt Floor 31-03-2024 NOT STARTED NA
1 Floor 15-05-2024 NOT STARTED NA
2 Floor 30-06-2024 NOT STARTED NA
3 Floor 15-08-2024 NOT STARTED NA
4 Floor 30-09-2024 NOT STARTED NA
Electrical Works 28-02-2025 NOT STARTED NA
Concealed Cabling including Plugs & switches 28-02-2025 NOT STARTED NA
Installation & Charging of Transformer 28-02-2025 NOT STARTED NA
Connection to Flats/Apartments 28-02-2025 NOT STARTED NA
PH works 31-07-2025 NOT STARTED NA
Laying of concealed Pipes 31-07-2025 NOT STARTED NA
PH Fittings 31-07-2025 NOT STARTED NA
Overhead Water Tanks 31-07-2025 NOT STARTED NA
Water Supply Connection to all units 31-07-2025 NOT STARTED NA
STP construction and completion 31-07-2025 NOT STARTED NA
Distempering & Colouring of all units and exteriors 30-09-2025 NOT STARTED NA
Fixation of doors and windows 30-11-2025 NOT STARTED NA
Scheduled Date of handing over possession 01-06-2026 NOT STARTED NA
Development of common areas, parks, gardens etc 31-01-2026 NOT STARTED NA
Site Development 05-05-2023 IN PROGRESS NA
NA 17-11-2023 IN PROGRESS NA
Ground Floor/Stilt Floor 30-09-2023 IN PROGRESS NA
1 Floor 30-11-2023 IN PROGRESS NA
2 Floor 31-01-2024 IN PROGRESS NA
3 Floor 31-03-2024 IN PROGRESS NA
4 Floor 31-05-2024 31-05-2024 NA
NA 31-05-2024 31-05-2024 NA
Ground Floor/Stilt Floor 31-03-2024 NOT STARTED NA
1 Floor 15-05-2024 NOT STARTED NA
2 Floor 30-06-2024 NOT STARTED NA
3 Floor 15-08-2024 NOT STARTED NA
4 Floor 30-09-2024 NOT STARTED NA
Electrical Works 28-02-2025 NOT STARTED NA
Concealed Cabling including Plugs & switches 28-02-2025 NOT STARTED NA
Installation & Charging of Transformer 28-02-2025 NOT STARTED NA
Connection to Flats/Apartments 28-02-2025 NOT STARTED NA
PH works 31-07-2025 NOT STARTED NA
Laying of concealed Pipes 31-07-2025 NOT STARTED NA
PH Fittings 31-07-2025 NOT STARTED NA
Overhead Water Tanks 31-07-2025 NOT STARTED NA
Water Supply Connection to all units 31-07-2025 NOT STARTED NA
STP construction and completion 31-07-2025 NOT STARTED NA
Distempering & Colouring of all units and exteriors 30-09-2025 NOT STARTED NA
Fixation of doors and windows 30-11-2025 NOT STARTED NA
Scheduled Date of handing over possession 01-06-2026 NOT STARTED NA
Development of common areas, parks, gardens etc 31-01-2026 NOT STARTED NA

Category and no. of units to be developed

:  Residential
:  
:  24
:  
:  
:  
Residential Flats/ House
S. No. Flat No./ House No.

Area in square metres

Ownership
Carpet Area Balcony Area Exclusive Open Terrace Area
1 101 79.24 7.69 0 Promoter
2 102 80.14 5.85 0 Promoter
3 103 78.77 4.25 0 Promoter
4 104 93.92 8.85 0 Promoter
5 105 80.59 4.84 0 Promoter
6 106 98.24 7.92 0 Promoter
7 201 79.24 7.69 0 Promoter
8 202 80.14 5.85 0 Promoter
9 203 78.77 4.25 0 Promoter
10 204 93.92 8.85 0 Promoter
11 205 80.59 4.84 0 Promoter
12 206 98.24 7.92 0 Promoter
13 301 79.24 7.69 0 Promoter
14 302 80.14 5.85 0 Promoter
15 303 78.77 4.25 0 Promoter
16 304 93.92 8.85 0 Promoter
17 305 80.59 4.84 0 Promoter
18 306 98.24 7.92 0 Promoter
19 401 79.24 7.69 0 Promoter
20 402 80.14 5.85 0 Promoter
21 403 78.77 4.25 0 Promoter
22 404 93.92 8.85 0 Promoter
23 405 80.59 4.84 0 Promoter
24 406 98.24 7.92 0 Promoter
Types of garages and parking
House No. Type of Garage/ Parking allotted Serial No., if any Dimension (Length x Width) in Metres Floor area in sq. metres Garage/Parking area cost is included or additional
101 Covered Parking 101 5 M X3 M 15 SQM Included
102 Covered Parking 102 5 M X3 M 15 SQM Included
103 Covered Parking 103 5 M X3 M 15 SQM Included
104 Covered Parking 104 5 M X3 M 15 SQM Included
105 Covered Parking 105 5 M X3 M 15 SQM Included
106 Covered Parking 106 5 M X3 M 15 SQM Included
201 Covered Parking 201 5 M X3 M 15 SQM Included
202 Covered Parking 202 5 M X3 M 15 SQM Included
203 Covered Parking 203 5 M X3 M 15 SQM Included
204 Covered Parking 204 5 M X3 M 15 SQM Included
205 Covered Parking 205 5 M X3 M 15 SQM Included
206 Covered Parking 206 5 M X3 M 15 SQM Included
301 Covered Parking 301 5 M X3 M 15 SQM Included
302 Covered Parking 302 5 M X3 M 15 SQM Included
303 Covered Parking 303 5 M X3 M 15 SQM Included
304 Covered Parking 304 5 M X3 M 15 SQM Included
305 Covered Parking 305 5 M X3 M 15 SQM Included
306 Covered Parking 306 5 M X3 M 15 SQM Included
401 Covered Parking 401 5 M X3 M 15 SQM Included
402 Covered Parking 402 5 M X3 M 15 SQM Included
403 Covered Parking 403 5 M X3 M 15 SQM Included
404 Covered Parking 404 5 M X3 M 15 SQM Included
405 Covered Parking 405 5 M X3 M 15 SQM Included
406 Covered Parking 406 5 M X3 M 15 SQM Included
No
NA

Facilities to be provided

Particulars of Facilities Status of the facility Brief description of facility
Drinking Water Facility Ground Water Copy of Consent Letter
Fire Fighting Facility No
Emergency Evacuation Services Yes STAIRCASE
Use of Renewable Energy No
Lift Facility Yes 2 NOS OF LIFT (OTIS OR EQUIVALENT) with ARD FACILITY
Market Complex No
Community Hall Yes 24.04 SQM WITH TILE FLOORING
Gymnasium No
Swimming Pool No
Play Ground No
Park/Garden No
Plantation Area Yes 112 SQM
Others(Please Specify) No
Internal Road Yes 2.82 MTR WIDTH & 141.15 MTR LENGTH INTERNAL ROAD WITH PAVER BLOCK FLOORING
External Road Yes 9.14 MTR WIDE EXTERNAL ROAD ADJACENT TO PROJECT PLOT
Elecricity Supply Yes Copy of Consent Letter
Other Amenities No

Bank Particulars of the Project

  STATE BANK OF INDIA
  Bapuji Nagar
  41867484263
  SBIN0004256
   View
  2597490
  9437557490

Particulars of Architect/Construction Engineer/Contractor/Chartered Accountant

Name position Address with mobile number and email address Registration number Key real estate projects Is active Effective date
SAMIR KUMAR PATEL Architect PLOT NO-A-610,RAJENDRA BIHAR APARTMENT FOREST PARK,BHUBANSWAR.MOB-9437033229,email-sk.patel@gmail.com CA/2006/38244 EVOS GALAXY
SUDHANSU SEKHAR PANDA Construction Engineer BHUBANPUR, JAGATPUR, ,CUTTACK-754021, PHONE:8917573014, Email: sudhansup02@gmail.com RTP/DTP(STER)012/2017 EVOS GALAXY
GOURAV CHOUDHRY Chartered Accountant BAPUJI NAGAR,BHUBANSWAR-751019,MOB-9776022240, email-gourav.choudhurt1988@gmail.com FRN-329356E EVOS GALAXY

Financial Details

:  640.2 :   View
  30-04-2028 :  140
:  500.2 :  0

Documents Attached

Description of Document Option Documents
Fire Safety Certificate Undertaking Attached
Affidavit in Form-A as per clause-l of sub-section-2 of section-4 of the Act Yes Attached
Allotment letter format Yes Attached
Conveyance Deed Format Yes Attached
Affidavit to adopt agreement for sale format as per Rule-8(1) of ORE (R and D) Rules, 2017 Yes Attached
Annual Report 2020-21 Attached
Annual Report 2021-22 Attached
Annual Report 2022-23 Attached
IT Return 2020-21 Attached
IT Return 2021-22 Attached
IT Return 2022-23 Attached
Audit Report 2020-21 Attached
Audit Report 2021-22 Attached
Audit Report 2022-23 Attached

Additional Documents Attached

Sl. No. Title of the document Upload Document
1 ROAD CLARIFICATION
2 CLARIFICATION

Other documents

“I undertake that the information submitted by me in this application are correct and true to best my knowledge. I also understand that providing false or wrong information is punishable under the Section-60 of the Real Estate (Regulation & Development) Act, 2016. I also further understand that furnishing wrong or false information will lead to rejection of my application registration of the project with forfeiture of registration fee and other charges deposited by me.”
  

Construction Progress

Updated Construction Progress

SL NO. Description Scheduled date of completion Current Status Remarks
1 Site Development 05-05-2023 IN PROGRESS
2 Roof Casting NA NA NA
3 Ground Floor/Stilt Floor 30-09-2023 NOT STARTED NA
4 1 Floor 30-11-2023 NOT STARTED NA
5 2 Floor 31-01-2024 NOT STARTED NA
6 3 Floor 31-03-2024 NOT STARTED NA
7 4 Floor 31-05-2024 NOT STARTED NA
8 Brick Work & Plastering NA NA NA
9 Ground Floor/Stilt Floor 31-03-2024 NOT STARTED NA
10 1 Floor 15-05-2024 NOT STARTED NA
11 2 Floor 30-06-2024 NOT STARTED NA
12 3 Floor 15-08-2024 NOT STARTED NA
13 4 Floor 30-09-2024 NOT STARTED NA
14 Electrical Works 28-02-2025 NOT STARTED NA
15 Concealed Cabling including Plugs & switches 28-02-2025 NOT STARTED NA
16 Installation & Charging of Transformer 28-02-2025 NOT STARTED NA
17 Connection to Flats/Apartments 28-02-2025 NOT STARTED NA
18 PH works 31-07-2025 NOT STARTED NA
19 Laying of concealed Pipes 31-07-2025 NOT STARTED NA
20 PH Fittings 31-07-2025 NOT STARTED NA
21 Overhead Water Tanks 31-07-2025 NOT STARTED NA
22 Water Supply Connection to all units 31-07-2025 NOT STARTED NA
23 STP construction and completion 31-07-2025 NOT STARTED NA
24 Distempering & Colouring of all units and exteriors 30-09-2025 NOT STARTED NA
25 Fixation of doors and windows 30-11-2025 NOT STARTED NA
26 Scheduled Date of handing over possession 01-06-2026 NOT STARTED NA
27 Development of common areas, parks, gardens etc 31-01-2026 NOT STARTED NA
Updated Changes on 13-07-2023
28 Site Development 05-05-2023 IN PROGRESS
29 NA NA NA NA
30 Ground Floor/Stilt Floor 30-09-2023 NOT STARTED NA
31 1 Floor 30-11-2023 NOT STARTED NA
32 2 Floor 31-01-2024 NOT STARTED NA
33 3 Floor 31-03-2024 NOT STARTED NA
34 4 Floor 31-05-2024 NOT STARTED NA
35 NA NA NA NA
36 Ground Floor/Stilt Floor 31-03-2024 NOT STARTED NA
37 1 Floor 15-05-2024 NOT STARTED NA
38 2 Floor 30-06-2024 NOT STARTED NA
39 3 Floor 15-08-2024 NOT STARTED NA
40 4 Floor 30-09-2024 NOT STARTED NA
41 Electrical Works 28-02-2025 NOT STARTED NA
42 Concealed Cabling including Plugs & switches 28-02-2025 NOT STARTED NA
43 Installation & Charging of Transformer 28-02-2025 NOT STARTED NA
44 Connection to Flats/Apartments 28-02-2025 NOT STARTED NA
45 PH works 31-07-2025 NOT STARTED NA
46 Laying of concealed Pipes 31-07-2025 NOT STARTED NA
47 PH Fittings 31-07-2025 NOT STARTED NA
48 Overhead Water Tanks 31-07-2025 NOT STARTED NA
49 Water Supply Connection to all units 31-07-2025 NOT STARTED NA
50 STP construction and completion 31-07-2025 NOT STARTED NA
51 Distempering & Colouring of all units and exteriors 30-09-2025 NOT STARTED NA
52 Fixation of doors and windows 30-11-2025 NOT STARTED NA
53 Scheduled Date of handing over possession 01-06-2026 NOT STARTED NA
54 Development of common areas, parks, gardens etc 31-01-2026 NOT STARTED NA
Updated Changes on 17-11-2023
55 Site Development 05-05-2023 IN PROGRESS NA
56 NA 17-11-2023 IN PROGRESS
57 Ground Floor/Stilt Floor 30-09-2023 IN PROGRESS
58 1 Floor 30-11-2023 IN PROGRESS
59 2 Floor 31-01-2024 IN PROGRESS
60 3 Floor 31-03-2024 NOT STARTED NA
61 4 Floor 31-05-2024 31-05-2024 NA
62 NA 31-05-2024 31-05-2024 NA
63 Ground Floor/Stilt Floor 31-03-2024 NOT STARTED NA
64 1 Floor 15-05-2024 NOT STARTED NA
65 2 Floor 30-06-2024 NOT STARTED NA
66 3 Floor 15-08-2024 NOT STARTED NA
67 4 Floor 30-09-2024 NOT STARTED NA
68 Electrical Works 28-02-2025 NOT STARTED NA
69 Concealed Cabling including Plugs & switches 28-02-2025 NOT STARTED NA
70 Installation & Charging of Transformer 28-02-2025 NOT STARTED NA
71 Connection to Flats/Apartments 28-02-2025 NOT STARTED NA
72 PH works 31-07-2025 NOT STARTED NA
73 Laying of concealed Pipes 31-07-2025 NOT STARTED NA
74 PH Fittings 31-07-2025 NOT STARTED NA
75 Overhead Water Tanks 31-07-2025 NOT STARTED NA
76 Water Supply Connection to all units 31-07-2025 NOT STARTED NA
77 STP construction and completion 31-07-2025 NOT STARTED NA
78 Distempering & Colouring of all units and exteriors 30-09-2025 NOT STARTED NA
79 Fixation of doors and windows 30-11-2025 NOT STARTED NA
80 Scheduled Date of handing over possession 01-06-2026 NOT STARTED NA
81 Development of common areas, parks, gardens etc 31-01-2026 NOT STARTED NA
Updated Changes on 02-04-2024
82 Site Development 05-05-2023 IN PROGRESS
83 NA 17-11-2023 IN PROGRESS
84 Ground Floor/Stilt Floor 30-09-2023 IN PROGRESS
85 1 Floor 30-11-2023 IN PROGRESS
86 2 Floor 31-01-2024 IN PROGRESS
87 3 Floor 31-03-2024 IN PROGRESS
88 4 Floor 31-05-2024 31-05-2024 NA
89 NA 31-05-2024 31-05-2024 NA
90 Ground Floor/Stilt Floor 31-03-2024 NOT STARTED NA
91 1 Floor 15-05-2024 NOT STARTED NA
92 2 Floor 30-06-2024 NOT STARTED NA
93 3 Floor 15-08-2024 NOT STARTED NA
94 4 Floor 30-09-2024 NOT STARTED NA
95 Electrical Works 28-02-2025 NOT STARTED NA
96 Concealed Cabling including Plugs & switches 28-02-2025 NOT STARTED NA
97 Installation & Charging of Transformer 28-02-2025 NOT STARTED NA
98 Connection to Flats/Apartments 28-02-2025 NOT STARTED NA
99 PH works 31-07-2025 NOT STARTED NA
100 Laying of concealed Pipes 31-07-2025 NOT STARTED NA
101 PH Fittings 31-07-2025 NOT STARTED NA
102 Overhead Water Tanks 31-07-2025 NOT STARTED NA
103 Water Supply Connection to all units 31-07-2025 NOT STARTED NA
104 STP construction and completion 31-07-2025 NOT STARTED NA
105 Distempering & Colouring of all units and exteriors 30-09-2025 NOT STARTED NA
106 Fixation of doors and windows 30-11-2025 NOT STARTED NA
107 Scheduled Date of handing over possession 01-06-2026 NOT STARTED NA
108 Development of common areas, parks, gardens etc 31-01-2026 NOT STARTED NA
Updated Changes on 30-04-2024
109 Site Development 05-05-2023 IN PROGRESS NA
110 NA 17-11-2023 IN PROGRESS NA
111 Ground Floor/Stilt Floor 30-09-2023 IN PROGRESS NA
112 1 Floor 30-11-2023 IN PROGRESS NA
113 2 Floor 31-01-2024 IN PROGRESS NA
114 3 Floor 31-03-2024 IN PROGRESS NA
115 4 Floor 31-05-2024 31-05-2024 NA
116 NA 31-05-2024 31-05-2024 NA
117 Ground Floor/Stilt Floor 31-03-2024 NOT STARTED NA
118 1 Floor 15-05-2024 NOT STARTED NA
119 2 Floor 30-06-2024 NOT STARTED NA
120 3 Floor 15-08-2024 NOT STARTED NA
121 4 Floor 30-09-2024 NOT STARTED NA
122 Electrical Works 28-02-2025 NOT STARTED NA
123 Concealed Cabling including Plugs & switches 28-02-2025 NOT STARTED NA
124 Installation & Charging of Transformer 28-02-2025 NOT STARTED NA
125 Connection to Flats/Apartments 28-02-2025 NOT STARTED NA
126 PH works 31-07-2025 NOT STARTED NA
127 Laying of concealed Pipes 31-07-2025 NOT STARTED NA
128 PH Fittings 31-07-2025 NOT STARTED NA
129 Overhead Water Tanks 31-07-2025 NOT STARTED NA
130 Water Supply Connection to all units 31-07-2025 NOT STARTED NA
131 STP construction and completion 31-07-2025 NOT STARTED NA
132 Distempering & Colouring of all units and exteriors 30-09-2025 NOT STARTED NA
133 Fixation of doors and windows 30-11-2025 NOT STARTED NA
134 Scheduled Date of handing over possession 01-06-2026 NOT STARTED NA
135 Development of common areas, parks, gardens etc 31-01-2026 NOT STARTED NA

Booking Status

Residential Flats/ House
S. No. Flat No./ House No.

Area in square metres

Ownership Status
Carpet Area Balcony Area Exclusive Open Terrace Area
1 101 79.24 7.69 0 Promoter
2 102 80.14 5.85 0 Promoter
3 103 78.77 4.25 0 Promoter
4 104 93.92 8.85 0 Promoter
5 105 80.59 4.84 0 Promoter
6 106 98.24 7.92 0 Promoter
7 201 79.24 7.69 0 Promoter
8 202 80.14 5.85 0 Promoter
9 203 78.77 4.25 0 Promoter
10 204 93.92 8.85 0 Promoter
11 205 80.59 4.84 0 Promoter
12 206 98.24 7.92 0 Promoter
13 301 79.24 7.69 0 Promoter
14 302 80.14 5.85 0 Promoter
15 303 78.77 4.25 0 Promoter
16 304 93.92 8.85 0 Promoter
17 305 80.59 4.84 0 Promoter
18 306 98.24 7.92 0 Promoter
19 401 79.24 7.69 0 Promoter
20 402 80.14 5.85 0 Promoter
21 403 78.77 4.25 0 Promoter
22 404 93.92 8.85 0 Promoter
23 405 80.59 4.84 0 Promoter
24 406 98.24 7.92 0 Promoter

Financial Status

SL No. Funds Collected from the Allottees Funds Borrowed from Financial Institutions Funds Employed from Own Sources Expenditure As On Date Status
1 4939232 0 14000000 16096437 30-06-2023 9971.80
2 101488482 0 0 71041937 02-03-2024 As on 31-12-2023
3 103967939 0 0 71041937 31-03-2024 31-03-2024

Updated Conditions of building plan approval

Sl. No. Description of Conditions Schedule date of compliance Present Status
1 PARKING SPACE MEASURING 673.40 SQM. AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE 30-04-2026 NOT STARTED
2 THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 9.14 MTR. IN WIDTH. 30-04-2026 NOT STARTED
3 PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES, FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS 30-04-2026 NOT STARTED
4 OBTAIN, WHEREVER APPLICABLE, FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK; 30-04-2026 NOT STARTED
5 SUBMIT STAGE WISE CONSTRUCTION REPORT. PENALITY SHALL BE IMPOSED AS PER RULE 14 OF ODA (P&BS) RULES 2020 IN CASE OF NON-SUBMISSION OF THE SAME. 30-04-2026 NOT STARTED
6 ENAGAGE AN ACCREDITED PERSON FOR THIRD PARTY VERIFICATION AT PLINTH AND GROUND FLOOR ROOF LEVEL. UPON DETECTION OF UNAUTHORISED CONSTRUCTION IN THE THIRD PARTY CERIFICATION RPORT THE APPLICATNT SHALL BE IMPSED A FINE AS PRESCRIBED UNDER SUB-RULE 3 OF RULE 15 OF ODA (P&BS RULES,2020) 30-04-2026 NOT STARTED
7 ENSURE THAT THE COMPLETION CERTIFICATE IN FORM XVII AS APPENDED TO ODA CAF RULES 2016 IS ISSUED BY THE PROJECT MANAGEMENT ORGANISATION ENGAGED BY HIM ON COMPETION OF THE BUILDING FOR SUBMISSION OF THE SAME TO THE AUTHORITY FOR VERIFICATION AND ISSUEANCE OF OCCUPANCY CERTIFICATE. 30-04-2026 NOT STARTED
8 OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART. 30-04-2026 NOT STARTED
9 WHEREVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE,RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY. 30-04-2026 NOT STARTED
10 THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER WITHOUT PRIOR APPROVAL UNDER SECTION 16 OF THE ODA ACT, 1982. 30-04-2026 NOT STARTED
11 STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE – 47 OF ODA (PLANNING & BUILDING STANDARDS) RULES,2020 30-04-2026 NOT STARTED
12 ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS)RULES,2020. 30-04-2026 NOT STARTED
13 THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED/CLOSED IN ANY MANNER. 30-04-2026 NOT STARTED
14 AT LEAST 50% OF THE OPEN SPACE SHALL BE PERVIOUS AND PLANTATION @ ONE TREE PER 80 SQ.MTR. OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES, 2020. 30-04-2026 NOT STARTED
15 RAINWATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER. 30-04-2026 NOT STARTED
16 GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @ 6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA. 30-04-2026 NOT STARTED
17 AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER SUB-RULE (12) OF RULE 37 OF ODA (P&BS) RULES 2020. 30-04-2026 NOT STARTED
18 ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FORABSORPTION OF RAINWATER AND SEE PAGE INTO THE GROUND. 30-04-2026 NOT STARTED
19 HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR 30-04-2026 NOT STARTED
20 SPACE PER FLAT SHALL BE PROVIDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN12SQUARE METERS. 30-04-2026 NOT STARTED
21 ICT LANDING POINT AS PER RULE 57 OF ODA (P&BS) RULES, 2020 SHALL BE PROVIDED. 30-04-2026 NOT STARTED
22 STP AND OTHER UTILITIES, IF PROVIDED WITHIN MINIMUM SETBACK AREA SHALL NOT BE ALLOWED ABOVE GROUND LEVEL AND SHALL ONLY BE CONSTRUCTED BELOW GROUND LEVEL; AND THE SAME SHALL BE APPROPRIATELY COVERED FOR MOVEMENT OF VEHICLE/PEOPLE ABOVE IT. 30-04-2026 NOT STARTED
23 GUARD ROOM, ELECTRIC CABIN, SUB-STATION, AREA FOR GENERATOR SET, ATM, ETC, IF PROVIDED SHALL NOT BE ALLOWED WITHIN MINIMUM SETBACK AREA. 30-04-2026 NOT STARTED
24 THE APPLICANT SHALL OBTAIN INFRASTRUCTURAL SPECIFICATION AND SUBSEQUENT CLEARANCE WITH REGARD TO DEVELOPMENT OF INFRASGTRUCTURE FOR EIDP BEFORE COMMENCEMENT OF CONSTRUCTION. 30-04-2026 NOT STARTED
25 THE APPLICANT SHALL GET THE EXTERNAL INFRASTRUCTURE DEVELOPMENT PLAN (EIDP) APPROVED BY THE COMMITTEE AS SPECIFIED UNDER CLAUSE 3.2.3 OF THE SOP NOTIFIED VIDE NO. 2360/BDA DATED 18.01.2021AND EXECUTE THE APPROVED EIDP IN ACCORDANCE WITH CLAUSE NO. 3.2.4. AFTER COMPLETION OF THE EXTERNAL INFRASTRUCTURE, THE APPLICANT SHALL OBTAIN THE WRITTEN RECOMMENDATION OF THE EIDP COMMITTEE REGARDING SATISFACTORY COMPLETION OF INFRASTRUCTURE AS PER THE APPROVED EIDP. THE APPLICANT SHALL APPLY FOR ISSUE OF NOC FROM ENGINEER MEMBER, BDA AFTER RECOMMENDATION OF THE COMMITTEE. 30-04-2026 NOT STARTED
26 OCCUPANCY CERTIFICATE SHALL BE ISSUED ONLY AFTER OBTAINING THE NOC FROM ENGINEER MEMBER, BDA IN ACCORDANCE WITH CLAUSE 3.2.6. 30-04-2026 NOT STARTED
27 THE APPLICANT SHALL OBTAIN ORERA REGISTRATION AS PER THE AFFIDAVIT SUBMITTED BY APPLICANT AND SUBMIT THE ORERA REGISTRATION CERTIFICATE AT THE TIME OF SUBMISSION OF APPLICATION FOR ISSUE OF OCCUPANCY CERTIFICATE. 30-04-2026 NOT STARTED
28 THE OWNER/ APPLICANT/ TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/CLEARANCE GIVEN BY CENTRAL GROUND WATER AUTHORITY (CGWA) VIDE LETTER NO. CGWA/ NOC/ INF/ ORIG/2022/17054 DATED 17.11.2022. 30-04-2026 NOT STARTED
Updated Changes on 13-07-2023
29 PARKING SPACE MEASURING 673.40 SQM. AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE 30-04-2026 NOT STARTED
30 THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 9.14 MTR. IN WIDTH. 30-04-2026 NOT STARTED
31 PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES, FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS 30-04-2026 NOT STARTED
32 OBTAIN, WHEREVER APPLICABLE, FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK; 30-04-2026 NOT STARTED
33 SUBMIT STAGE WISE CONSTRUCTION REPORT. PENALITY SHALL BE IMPOSED AS PER RULE 14 OF ODA (P&BS) RULES 2020 IN CASE OF NON-SUBMISSION OF THE SAME. 30-04-2026 NOT STARTED
34 ENAGAGE AN ACCREDITED PERSON FOR THIRD PARTY VERIFICATION AT PLINTH AND GROUND FLOOR ROOF LEVEL. UPON DETECTION OF UNAUTHORISED CONSTRUCTION IN THE THIRD PARTY CERIFICATION RPORT THE APPLICATNT SHALL BE IMPSED A FINE AS PRESCRIBED UNDER SUB-RULE 3 OF RULE 15 OF ODA (P&BS RULES,2020) 30-04-2026 NOT STARTED
35 ENSURE THAT THE COMPLETION CERTIFICATE IN FORM XVII AS APPENDED TO ODA CAF RULES 2016 IS ISSUED BY THE PROJECT MANAGEMENT ORGANISATION ENGAGED BY HIM ON COMPETION OF THE BUILDING FOR SUBMISSION OF THE SAME TO THE AUTHORITY FOR VERIFICATION AND ISSUEANCE OF OCCUPANCY CERTIFICATE. 30-04-2026 NOT STARTED
36 OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART. 30-04-2026 NOT STARTED
37 WHEREVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE,RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY. 30-04-2026 NOT STARTED
38 THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER WITHOUT PRIOR APPROVAL UNDER SECTION 16 OF THE ODA ACT, 1982. 30-04-2026 NOT STARTED
39 STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE – 47 OF ODA (PLANNING & BUILDING STANDARDS) RULES,2020 30-04-2026 NOT STARTED
40 ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS)RULES,2020. 30-04-2026 NOT STARTED
41 THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED/CLOSED IN ANY MANNER. 30-04-2026 NOT STARTED
42 AT LEAST 50% OF THE OPEN SPACE SHALL BE PERVIOUS AND PLANTATION @ ONE TREE PER 80 SQ.MTR. OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES, 2020. 30-04-2026 NOT STARTED
43 RAINWATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER. 30-04-2026 NOT STARTED
44 GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @ 6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA. 30-04-2026 NOT STARTED
45 AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER SUB-RULE (12) OF RULE 37 OF ODA (P&BS) RULES 2020. 30-04-2026 NOT STARTED
46 ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FORABSORPTION OF RAINWATER AND SEE PAGE INTO THE GROUND. 30-04-2026 NOT STARTED
47 HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR 30-04-2026 NOT STARTED
48 SPACE PER FLAT SHALL BE PROVIDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN12SQUARE METERS. 30-04-2026 NOT STARTED
49 ICT LANDING POINT AS PER RULE 57 OF ODA (P&BS) RULES, 2020 SHALL BE PROVIDED. 30-04-2026 NOT STARTED
50 STP AND OTHER UTILITIES, IF PROVIDED WITHIN MINIMUM SETBACK AREA SHALL NOT BE ALLOWED ABOVE GROUND LEVEL AND SHALL ONLY BE CONSTRUCTED BELOW GROUND LEVEL; AND THE SAME SHALL BE APPROPRIATELY COVERED FOR MOVEMENT OF VEHICLE/PEOPLE ABOVE IT. 30-04-2026 NOT STARTED
51 GUARD ROOM, ELECTRIC CABIN, SUB-STATION, AREA FOR GENERATOR SET, ATM, ETC, IF PROVIDED SHALL NOT BE ALLOWED WITHIN MINIMUM SETBACK AREA. 30-04-2026 NOT STARTED
52 THE APPLICANT SHALL OBTAIN INFRASTRUCTURAL SPECIFICATION AND SUBSEQUENT CLEARANCE WITH REGARD TO DEVELOPMENT OF INFRASGTRUCTURE FOR EIDP BEFORE COMMENCEMENT OF CONSTRUCTION. 30-04-2026 NOT STARTED
53 THE APPLICANT SHALL GET THE EXTERNAL INFRASTRUCTURE DEVELOPMENT PLAN (EIDP) APPROVED BY THE COMMITTEE AS SPECIFIED UNDER CLAUSE 3.2.3 OF THE SOP NOTIFIED VIDE NO. 2360/BDA DATED 18.01.2021AND EXECUTE THE APPROVED EIDP IN ACCORDANCE WITH CLAUSE NO. 3.2.4. AFTER COMPLETION OF THE EXTERNAL INFRASTRUCTURE, THE APPLICANT SHALL OBTAIN THE WRITTEN RECOMMENDATION OF THE EIDP COMMITTEE REGARDING SATISFACTORY COMPLETION OF INFRASTRUCTURE AS PER THE APPROVED EIDP. THE APPLICANT SHALL APPLY FOR ISSUE OF NOC FROM ENGINEER MEMBER, BDA AFTER RECOMMENDATION OF THE COMMITTEE. 30-04-2026 NOT STARTED
54 OCCUPANCY CERTIFICATE SHALL BE ISSUED ONLY AFTER OBTAINING THE NOC FROM ENGINEER MEMBER, BDA IN ACCORDANCE WITH CLAUSE 3.2.6. 30-04-2026 NOT STARTED
55 THE APPLICANT SHALL OBTAIN ORERA REGISTRATION AS PER THE AFFIDAVIT SUBMITTED BY APPLICANT AND SUBMIT THE ORERA REGISTRATION CERTIFICATE AT THE TIME OF SUBMISSION OF APPLICATION FOR ISSUE OF OCCUPANCY CERTIFICATE. 30-04-2026 NOT STARTED
56 THE OWNER/ APPLICANT/ TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/CLEARANCE GIVEN BY CENTRAL GROUND WATER AUTHORITY (CGWA) VIDE LETTER NO. CGWA/ NOC/ INF/ ORIG/2022/17054 DATED 17.11.2022. 30-04-2026 NOT STARTED
Updated Changes on 30-10-2023
57 PARKING SPACE MEASURING 673.40 SQM. AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE 30-04-2026 NOT STARTED
58 THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 9.14 MTR. IN WIDTH. 30-04-2026 NOT STARTED
59 PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES, FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS 30-04-2026 NOT STARTED
60 OBTAIN, WHEREVER APPLICABLE, FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK; 30-04-2026 NOT STARTED
61 SUBMIT STAGE WISE CONSTRUCTION REPORT. PENALITY SHALL BE IMPOSED AS PER RULE 14 OF ODA (P&BS) RULES 2020 IN CASE OF NON-SUBMISSION OF THE SAME. 30-04-2026 NOT STARTED
62 ENAGAGE AN ACCREDITED PERSON FOR THIRD PARTY VERIFICATION AT PLINTH AND GROUND FLOOR ROOF LEVEL. UPON DETECTION OF UNAUTHORISED CONSTRUCTION IN THE THIRD PARTY CERIFICATION RPORT THE APPLICATNT SHALL BE IMPSED A FINE AS PRESCRIBED UNDER SUB-RULE 3 OF RULE 15 OF ODA (P&BS RULES,2020) 30-04-2026 NOT STARTED
63 ENSURE THAT THE COMPLETION CERTIFICATE IN FORM XVII AS APPENDED TO ODA CAF RULES 2016 IS ISSUED BY THE PROJECT MANAGEMENT ORGANISATION ENGAGED BY HIM ON COMPETION OF THE BUILDING FOR SUBMISSION OF THE SAME TO THE AUTHORITY FOR VERIFICATION AND ISSUEANCE OF OCCUPANCY CERTIFICATE. 30-04-2026 NOT STARTED
64 OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART. 30-04-2026 NOT STARTED
65 WHEREVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE,RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY. 30-04-2026 NOT STARTED
66 THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER WITHOUT PRIOR APPROVAL UNDER SECTION 16 OF THE ODA ACT, 1982. 30-04-2026 NOT STARTED
67 STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE – 47 OF ODA (PLANNING & BUILDING STANDARDS) RULES,2020 30-04-2026 NOT STARTED
68 ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS)RULES,2020. 30-04-2026 NOT STARTED
69 THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED/CLOSED IN ANY MANNER. 30-04-2026 NOT STARTED
70 AT LEAST 50% OF THE OPEN SPACE SHALL BE PERVIOUS AND PLANTATION @ ONE TREE PER 80 SQ.MTR. OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES, 2020. 30-04-2026 NOT STARTED
71 RAINWATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER. 30-04-2026 NOT STARTED
72 GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @ 6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA. 30-04-2026 NOT STARTED
73 AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER SUB-RULE (12) OF RULE 37 OF ODA (P&BS) RULES 2020. 30-04-2026 NOT STARTED
74 ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FORABSORPTION OF RAINWATER AND SEE PAGE INTO THE GROUND. 30-04-2026 NOT STARTED
75 HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR 30-04-2026 NOT STARTED
76 SPACE PER FLAT SHALL BE PROVIDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN12SQUARE METERS. 30-04-2026 NOT STARTED
77 ICT LANDING POINT AS PER RULE 57 OF ODA (P&BS) RULES, 2020 SHALL BE PROVIDED. 30-04-2026 NOT STARTED
78 STP AND OTHER UTILITIES, IF PROVIDED WITHIN MINIMUM SETBACK AREA SHALL NOT BE ALLOWED ABOVE GROUND LEVEL AND SHALL ONLY BE CONSTRUCTED BELOW GROUND LEVEL; AND THE SAME SHALL BE APPROPRIATELY COVERED FOR MOVEMENT OF VEHICLE/PEOPLE ABOVE IT. 30-04-2026 NOT STARTED
79 GUARD ROOM, ELECTRIC CABIN, SUB-STATION, AREA FOR GENERATOR SET, ATM, ETC, IF PROVIDED SHALL NOT BE ALLOWED WITHIN MINIMUM SETBACK AREA. 30-04-2026 NOT STARTED
80 THE APPLICANT SHALL OBTAIN INFRASTRUCTURAL SPECIFICATION AND SUBSEQUENT CLEARANCE WITH REGARD TO DEVELOPMENT OF INFRASGTRUCTURE FOR EIDP BEFORE COMMENCEMENT OF CONSTRUCTION. 30-04-2026 NOT STARTED
81 THE APPLICANT SHALL GET THE EXTERNAL INFRASTRUCTURE DEVELOPMENT PLAN (EIDP) APPROVED BY THE COMMITTEE AS SPECIFIED UNDER CLAUSE 3.2.3 OF THE SOP NOTIFIED VIDE NO. 2360/BDA DATED 18.01.2021AND EXECUTE THE APPROVED EIDP IN ACCORDANCE WITH CLAUSE NO. 3.2.4. AFTER COMPLETION OF THE EXTERNAL INFRASTRUCTURE, THE APPLICANT SHALL OBTAIN THE WRITTEN RECOMMENDATION OF THE EIDP COMMITTEE REGARDING SATISFACTORY COMPLETION OF INFRASTRUCTURE AS PER THE APPROVED EIDP. THE APPLICANT SHALL APPLY FOR ISSUE OF NOC FROM ENGINEER MEMBER, BDA AFTER RECOMMENDATION OF THE COMMITTEE. 30-04-2026 NOT STARTED
82 OCCUPANCY CERTIFICATE SHALL BE ISSUED ONLY AFTER OBTAINING THE NOC FROM ENGINEER MEMBER, BDA IN ACCORDANCE WITH CLAUSE 3.2.6. 30-04-2026 NOT STARTED
83 THE APPLICANT SHALL OBTAIN ORERA REGISTRATION AS PER THE AFFIDAVIT SUBMITTED BY APPLICANT AND SUBMIT THE ORERA REGISTRATION CERTIFICATE AT THE TIME OF SUBMISSION OF APPLICATION FOR ISSUE OF OCCUPANCY CERTIFICATE. 30-04-2026 NOT STARTED
84 THE OWNER/ APPLICANT/ TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/CLEARANCE GIVEN BY CENTRAL GROUND WATER AUTHORITY (CGWA) VIDE LETTER NO. CGWA/ NOC/ INF/ ORIG/2022/17054 DATED 17.11.2022. 30-04-2026 NOT STARTED
Updated Changes on 02-04-2024
85 PARKING SPACE MEASURING 673.40 SQM. AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE 30-04-2026 NOT STARTED
86 THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 9.14 MTR. IN WIDTH. 30-04-2026 NOT STARTED
87 PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES, FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS 30-04-2026 NOT STARTED
88 OBTAIN, WHEREVER APPLICABLE, FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK; 30-04-2026 NOT STARTED
89 SUBMIT STAGE WISE CONSTRUCTION REPORT. PENALITY SHALL BE IMPOSED AS PER RULE 14 OF ODA (P&BS) RULES 2020 IN CASE OF NON-SUBMISSION OF THE SAME. 30-04-2026 NOT STARTED
90 ENAGAGE AN ACCREDITED PERSON FOR THIRD PARTY VERIFICATION AT PLINTH AND GROUND FLOOR ROOF LEVEL. UPON DETECTION OF UNAUTHORISED CONSTRUCTION IN THE THIRD PARTY CERIFICATION RPORT THE APPLICATNT SHALL BE IMPSED A FINE AS PRESCRIBED UNDER SUB-RULE 3 OF RULE 15 OF ODA (P&BS RULES,2020) 30-04-2026 NOT STARTED
91 ENSURE THAT THE COMPLETION CERTIFICATE IN FORM XVII AS APPENDED TO ODA CAF RULES 2016 IS ISSUED BY THE PROJECT MANAGEMENT ORGANISATION ENGAGED BY HIM ON COMPETION OF THE BUILDING FOR SUBMISSION OF THE SAME TO THE AUTHORITY FOR VERIFICATION AND ISSUEANCE OF OCCUPANCY CERTIFICATE. 30-04-2026 NOT STARTED
92 OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART. 30-04-2026 NOT STARTED
93 WHEREVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE,RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY. 30-04-2026 NOT STARTED
94 THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER WITHOUT PRIOR APPROVAL UNDER SECTION 16 OF THE ODA ACT, 1982. 30-04-2026 NOT STARTED
95 STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE – 47 OF ODA (PLANNING & BUILDING STANDARDS) RULES,2020 30-04-2026 NOT STARTED
96 ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS)RULES,2020. 30-04-2026 NOT STARTED
97 THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED/CLOSED IN ANY MANNER. 30-04-2026 NOT STARTED
98 AT LEAST 50% OF THE OPEN SPACE SHALL BE PERVIOUS AND PLANTATION @ ONE TREE PER 80 SQ.MTR. OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES, 2020. 30-04-2026 NOT STARTED
99 RAINWATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER. 30-04-2026 NOT STARTED
100 GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @ 6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA. 30-04-2026 NOT STARTED
101 AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER SUB-RULE (12) OF RULE 37 OF ODA (P&BS) RULES 2020. 30-04-2026 NOT STARTED
102 ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FORABSORPTION OF RAINWATER AND SEE PAGE INTO THE GROUND. 30-04-2026 NOT STARTED
103 HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR 30-04-2026 NOT STARTED
104 SPACE PER FLAT SHALL BE PROVIDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN12SQUARE METERS. 30-04-2026 NOT STARTED
105 ICT LANDING POINT AS PER RULE 57 OF ODA (P&BS) RULES, 2020 SHALL BE PROVIDED. 30-04-2026 NOT STARTED
106 STP AND OTHER UTILITIES, IF PROVIDED WITHIN MINIMUM SETBACK AREA SHALL NOT BE ALLOWED ABOVE GROUND LEVEL AND SHALL ONLY BE CONSTRUCTED BELOW GROUND LEVEL; AND THE SAME SHALL BE APPROPRIATELY COVERED FOR MOVEMENT OF VEHICLE/PEOPLE ABOVE IT. 30-04-2026 NOT STARTED
107 GUARD ROOM, ELECTRIC CABIN, SUB-STATION, AREA FOR GENERATOR SET, ATM, ETC, IF PROVIDED SHALL NOT BE ALLOWED WITHIN MINIMUM SETBACK AREA. 30-04-2026 NOT STARTED
108 THE APPLICANT SHALL OBTAIN INFRASTRUCTURAL SPECIFICATION AND SUBSEQUENT CLEARANCE WITH REGARD TO DEVELOPMENT OF INFRASGTRUCTURE FOR EIDP BEFORE COMMENCEMENT OF CONSTRUCTION. 30-04-2026 NOT STARTED
109 THE APPLICANT SHALL GET THE EXTERNAL INFRASTRUCTURE DEVELOPMENT PLAN (EIDP) APPROVED BY THE COMMITTEE AS SPECIFIED UNDER CLAUSE 3.2.3 OF THE SOP NOTIFIED VIDE NO. 2360/BDA DATED 18.01.2021AND EXECUTE THE APPROVED EIDP IN ACCORDANCE WITH CLAUSE NO. 3.2.4. AFTER COMPLETION OF THE EXTERNAL INFRASTRUCTURE, THE APPLICANT SHALL OBTAIN THE WRITTEN RECOMMENDATION OF THE EIDP COMMITTEE REGARDING SATISFACTORY COMPLETION OF INFRASTRUCTURE AS PER THE APPROVED EIDP. THE APPLICANT SHALL APPLY FOR ISSUE OF NOC FROM ENGINEER MEMBER, BDA AFTER RECOMMENDATION OF THE COMMITTEE. 30-04-2026 NOT STARTED
110 OCCUPANCY CERTIFICATE SHALL BE ISSUED ONLY AFTER OBTAINING THE NOC FROM ENGINEER MEMBER, BDA IN ACCORDANCE WITH CLAUSE 3.2.6. 30-04-2026 NOT STARTED
111 THE APPLICANT SHALL OBTAIN ORERA REGISTRATION AS PER THE AFFIDAVIT SUBMITTED BY APPLICANT AND SUBMIT THE ORERA REGISTRATION CERTIFICATE AT THE TIME OF SUBMISSION OF APPLICATION FOR ISSUE OF OCCUPANCY CERTIFICATE. 30-04-2026 NOT STARTED
112 THE OWNER/ APPLICANT/ TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/CLEARANCE GIVEN BY CENTRAL GROUND WATER AUTHORITY (CGWA) VIDE LETTER NO. CGWA/ NOC/ INF/ ORIG/2022/17054 DATED 17.11.2022. 30-04-2026 NOT STARTED
Updated Changes on 30-04-2024
113 PARKING SPACE MEASURING 673.40 SQM. AS SHOWN IN THE APPROVED PLAN SHALL BE LEFT FOR PARKING OF VEHICLES AND NO PART OF IT WILL BE USED FOR ANY OTHER PURPOSE 30-04-2026 NOT STARTED
114 THE LAND OVER WHICH CONSTRUCTION IS PROPOSED IS ACCESSIBLE BY AN APPROVED MEANS OF ACCESS OF 9.14 MTR. IN WIDTH. 30-04-2026 NOT STARTED
115 PERMIT THE AUTHORITY TO ENTER THE BUILDING OR PREMISES, FOR WHICH THE PERMISSION HAS BEEN GRANTED AT ANY REASONABLE TIME FOR THE PURPOSE OF ENFORCING THE REGULATIONS 30-04-2026 NOT STARTED
116 OBTAIN, WHEREVER APPLICABLE, FROM THE COMPETENT AUTHORITY PERMISSIONS/CLEARANCE REQUIRED IN CONNECTION WITH THE PROPOSED WORK; 30-04-2026 NOT STARTED
117 SUBMIT STAGE WISE CONSTRUCTION REPORT. PENALITY SHALL BE IMPOSED AS PER RULE 14 OF ODA (P&BS) RULES 2020 IN CASE OF NON-SUBMISSION OF THE SAME. 30-04-2026 NOT STARTED
118 ENAGAGE AN ACCREDITED PERSON FOR THIRD PARTY VERIFICATION AT PLINTH AND GROUND FLOOR ROOF LEVEL. UPON DETECTION OF UNAUTHORISED CONSTRUCTION IN THE THIRD PARTY CERIFICATION RPORT THE APPLICATNT SHALL BE IMPSED A FINE AS PRESCRIBED UNDER SUB-RULE 3 OF RULE 15 OF ODA (P&BS RULES,2020) 30-04-2026 NOT STARTED
119 ENSURE THAT THE COMPLETION CERTIFICATE IN FORM XVII AS APPENDED TO ODA CAF RULES 2016 IS ISSUED BY THE PROJECT MANAGEMENT ORGANISATION ENGAGED BY HIM ON COMPETION OF THE BUILDING FOR SUBMISSION OF THE SAME TO THE AUTHORITY FOR VERIFICATION AND ISSUEANCE OF OCCUPANCY CERTIFICATE. 30-04-2026 NOT STARTED
120 OBTAIN AN OCCUPANCY CERTIFICATE FROM THE AUTHORITY PRIOR TO OCCUPATION OF BUILDING IN FULL OR PART. 30-04-2026 NOT STARTED
121 WHEREVER TESTS OF ANY MATERIAL ARE MADE TO ENSURE CONFORMITY OF THE REQUIREMENTS OF THE REGULATIONS IN FORCE,RECORDS OF THE TEST DATA SHALL BE KEPT AVAILABLE FOR INSPECTION DURING THE CONSTRUCTION OF BUILDING AND FOR SUCH PERIOD THEREAFTER AS REQUIRED BY THE AUTHORITY. 30-04-2026 NOT STARTED
122 THE NUMBER OF DWELLING UNITS SO APPROVED SHALL NOT BE CHANGED IN ANY MANNER WITHOUT PRIOR APPROVAL UNDER SECTION 16 OF THE ODA ACT, 1982. 30-04-2026 NOT STARTED
123 STORM WATER FROM THE PREMISES OF ROOF TOP SHALL BE CONVEYED AND DISCHARGED TO THE RAIN WATER RECHARGING PITS AS PER RULE – 47 OF ODA (PLANNING & BUILDING STANDARDS) RULES,2020 30-04-2026 NOT STARTED
124 ROOFTOP SOLAR ENERGY INSTALLATION SHALL BE PROVIDED AS PER ODA (PLANNING & BUILDING STANDARDS)RULES,2020. 30-04-2026 NOT STARTED
125 THE SPACE WHICH IS MEANT FOR PARKING SHALL NOT BE CHANGED TO ANY OTHER USE AND SHALL NOT BE PARTITIONED/CLOSED IN ANY MANNER. 30-04-2026 NOT STARTED
126 AT LEAST 50% OF THE OPEN SPACE SHALL BE PERVIOUS AND PLANTATION @ ONE TREE PER 80 SQ.MTR. OF THE PLOT AREA SHALL BE MADE BY THE APPLICANT AS PER PROVISION UNDER RULE-30 OF ODA (P&BS) RULES, 2020. 30-04-2026 NOT STARTED
127 RAINWATER HARVESTING STRUCTURES SHALL BE PROVIDED WITHIN THE PREMISES FOR COLLECTION AND USE OF ROOFTOP RAINWATER. 30-04-2026 NOT STARTED
128 GROUNDWATER RECHARGING PITS SHALL BE PROVIDED @ 6 CUBIC METERS FOR EVERY 100 SQUARE METER OF ROOF AREA. 30-04-2026 NOT STARTED
129 AT LEAST 10% OF PARKING IN HOUSING PROJECT/APARTMENT BUILDING SHALL BE EARMARKED FOR VISITORS AND SHALL BE OPEN TO ALL VISITORS AND IN ALL OTHER CASES AS PER NORMS UNDER SUB-RULE (12) OF RULE 37 OF ODA (P&BS) RULES 2020. 30-04-2026 NOT STARTED
130 ALL THE PASSAGES AROUND THE BUILDING SHALL BE DEVELOPED WITH PERMEABLE PAVERS BLOCK FORABSORPTION OF RAINWATER AND SEE PAGE INTO THE GROUND. 30-04-2026 NOT STARTED
131 HOUSE OWNER’S SOCIETY OFFICE AND ASSEMBLY AREA AT THE RATE OF ONE SQUARE METER FLOOR 30-04-2026 NOT STARTED
132 SPACE PER FLAT SHALL BE PROVIDED AND THE MINIMUM AREA SHALL NOT BE LESS THAN12SQUARE METERS. 30-04-2026 NOT STARTED
133 ICT LANDING POINT AS PER RULE 57 OF ODA (P&BS) RULES, 2020 SHALL BE PROVIDED. 30-04-2026 NOT STARTED
134 STP AND OTHER UTILITIES, IF PROVIDED WITHIN MINIMUM SETBACK AREA SHALL NOT BE ALLOWED ABOVE GROUND LEVEL AND SHALL ONLY BE CONSTRUCTED BELOW GROUND LEVEL; AND THE SAME SHALL BE APPROPRIATELY COVERED FOR MOVEMENT OF VEHICLE/PEOPLE ABOVE IT. 30-04-2026 NOT STARTED
135 GUARD ROOM, ELECTRIC CABIN, SUB-STATION, AREA FOR GENERATOR SET, ATM, ETC, IF PROVIDED SHALL NOT BE ALLOWED WITHIN MINIMUM SETBACK AREA. 30-04-2026 NOT STARTED
136 THE APPLICANT SHALL OBTAIN INFRASTRUCTURAL SPECIFICATION AND SUBSEQUENT CLEARANCE WITH REGARD TO DEVELOPMENT OF INFRASGTRUCTURE FOR EIDP BEFORE COMMENCEMENT OF CONSTRUCTION. 30-04-2026 NOT STARTED
137 THE APPLICANT SHALL GET THE EXTERNAL INFRASTRUCTURE DEVELOPMENT PLAN (EIDP) APPROVED BY THE COMMITTEE AS SPECIFIED UNDER CLAUSE 3.2.3 OF THE SOP NOTIFIED VIDE NO. 2360/BDA DATED 18.01.2021AND EXECUTE THE APPROVED EIDP IN ACCORDANCE WITH CLAUSE NO. 3.2.4. AFTER COMPLETION OF THE EXTERNAL INFRASTRUCTURE, THE APPLICANT SHALL OBTAIN THE WRITTEN RECOMMENDATION OF THE EIDP COMMITTEE REGARDING SATISFACTORY COMPLETION OF INFRASTRUCTURE AS PER THE APPROVED EIDP. THE APPLICANT SHALL APPLY FOR ISSUE OF NOC FROM ENGINEER MEMBER, BDA AFTER RECOMMENDATION OF THE COMMITTEE. 30-04-2026 NOT STARTED
138 OCCUPANCY CERTIFICATE SHALL BE ISSUED ONLY AFTER OBTAINING THE NOC FROM ENGINEER MEMBER, BDA IN ACCORDANCE WITH CLAUSE 3.2.6. 30-04-2026 NOT STARTED
139 THE APPLICANT SHALL OBTAIN ORERA REGISTRATION AS PER THE AFFIDAVIT SUBMITTED BY APPLICANT AND SUBMIT THE ORERA REGISTRATION CERTIFICATE AT THE TIME OF SUBMISSION OF APPLICATION FOR ISSUE OF OCCUPANCY CERTIFICATE. 30-04-2026 NOT STARTED
140 THE OWNER/ APPLICANT/ TECHNICAL PERSON SHALL STRICTLY ADHERE TO THE TERMS AND CONDITIONS IMPOSED IN THE NOC/CLEARANCE GIVEN BY CENTRAL GROUND WATER AUTHORITY (CGWA) VIDE LETTER NO. CGWA/ NOC/ INF/ ORIG/2022/17054 DATED 17.11.2022. 30-04-2026 NOT STARTED

Updated Project Documents

Sl. No. Title of the document Upload Document
1 Proforma I
2 Proforma II
3 Proforma III
4 Proforma-III
5 Proforma-I & II
6 Proforma I & II
7 Proforma III
8 Proforma- i & II
9 Proforma-III
:  KALINGA KESHARI RATH :  
NA :  ALWPR1547G
:PAN Card :  kkrath@evos.co.in
:  B.TECH, MBA :  9040051152
:  11 YEARS
:  Yes :  NA
:  SRUJANIKA MISHRA :  
NA :  DYZPM0589Q
:PAN Card :  kkrath@evos.co.in
:  B.A. :  9040051152
:  6 YEARS
:  Yes :  NA
:  DEEPAK DAS :  
NA :  BGDPD0699E
:PAN Card :  deepakds961@gmail.com
:  Graduation and Diploma in H.M :  9040077993
:  5 YEARS
:  Yes :  NA

Particulars of Architect/Construction Engineer/Contractor/Chartered Accountant

Name position Address with mobile number and email address Registration number Key real estate projects Is active Effective date
SAMIR KUMAR PATEL Architect PLOT NO-A-610,RAJENDRA BIHAR APARTMENT FOREST PARK,BHUBANSWAR.MOB-9437033229,email-sk.patel@gmail.com CA/2006/38244 EVOS GALAXY
SUDHANSU SEKHAR PANDA Construction Engineer BHUBANPUR, JAGATPUR, ,CUTTACK-754021, PHONE:8917573014, Email: sudhansup02@gmail.com RTP/DTP(STER)012/2017 EVOS GALAXY
GOURAV CHOUDHRY Chartered Accountant BAPUJI NAGAR,BHUBANSWAR-751019,MOB-9776022240, email-gourav.choudhurt1988@gmail.com FRN-329356E EVOS GALAXY

Updated Units

House No. Type of Garage/ Parking allotted Serial No., if any Dimension (Length x Width) in Metres Floor area in sq. metres Garage/Parking area cost is included or additional
Updated Changes
101 Covered Parking 101 5 M X3 M 15 SQM Included
102 Covered Parking 102 5 M X3 M 15 SQM Included
103 Covered Parking 103 5 M X3 M 15 SQM Included
104 Covered Parking 104 5 M X3 M 15 SQM Included
105 Covered Parking 105 5 M X3 M 15 SQM Included
106 Covered Parking 106 5 M X3 M 15 SQM Included
201 Covered Parking 201 5 M X3 M 15 SQM Included
202 Covered Parking 202 5 M X3 M 15 SQM Included
203 Covered Parking 203 5 M X3 M 15 SQM Included
204 Covered Parking 204 5 M X3 M 15 SQM Included
205 Covered Parking 205 5 M X3 M 15 SQM Included
206 Covered Parking 206 5 M X3 M 15 SQM Included
301 Covered Parking 301 5 M X3 M 15 SQM Included
302 Covered Parking 302 5 M X3 M 15 SQM Included
303 Covered Parking 303 5 M X3 M 15 SQM Included
304 Covered Parking 304 5 M X3 M 15 SQM Included
305 Covered Parking 305 5 M X3 M 15 SQM Included
306 Covered Parking 306 5 M X3 M 15 SQM Included
401 Covered Parking 401 5 M X3 M 15 SQM Included
402 Covered Parking 402 5 M X3 M 15 SQM Included
403 Covered Parking 403 5 M X3 M 15 SQM Included
404 Covered Parking 404 5 M X3 M 15 SQM Included
405 Covered Parking 405 5 M X3 M 15 SQM Included
406 Covered Parking 406 5 M X3 M 15 SQM Included