1 |
Site Development
|
31-01-2020
|
NOT STARTED
|
|
2 |
Roof Casting
|
NA
|
NA
|
NA |
3 |
Ground Floor/Stilt Floor
|
31-03-2020
|
NOT STARTED
|
NA |
4 |
1 Floor
|
30-04-2020
|
NOT STARTED
|
NA |
5 |
2 Floor
|
16-06-2020
|
NOT STARTED
|
NA |
6 |
Brick Work & Plastering
|
NA
|
NA
|
NA |
7 |
Ground Floor/Stilt Floor
|
31-12-2020
|
NOT STARTED
|
NA |
8 |
1 Floor
|
10-02-2021
|
NOT STARTED
|
NA |
9 |
Electrical Works
|
30-06-2022
|
NOT STARTED
|
NA |
10 |
Concealed Cabling including Plugs & switches
|
30-06-2022
|
NOT STARTED
|
NA |
11 |
Installation & Charging of Transformer
|
30-06-2022
|
NOT STARTED
|
NA |
12 |
Connection to Flats/Apartments
|
30-06-2022
|
NOT STARTED
|
NA |
13 |
PH works
|
30-06-2022
|
NOT STARTED
|
NA |
14 |
Laying of concealed Pipes
|
30-06-2022
|
NOT STARTED
|
NA |
15 |
PH Fittings
|
30-09-2022
|
NOT STARTED
|
NA |
16 |
Overhead Water Tanks
|
30-09-2022
|
NOT STARTED
|
NA |
17 |
Water Supply Connection to all units
|
31-10-2022
|
NOT STARTED
|
NA |
18 |
STP construction and completion
|
31-10-2022
|
NOT STARTED
|
NA |
19 |
Distempering & Colouring of all units and exteriors
|
31-10-2022
|
NOT STARTED
|
NA |
20 |
Fixation of doors and windows
|
31-10-2022
|
NOT STARTED
|
NA |
21 |
Scheduled Date of handing over possession
|
09-11-2022
|
NOT STARTED
|
NA |
22 |
Development of common areas, parks, gardens etc
|
08-11-2022
|
NOT STARTED
|
NA |
23 |
3 Floor
|
30-08-2020
|
NOT STARTED
|
NA |
24 |
4 Floor
|
15-10-2020
|
NOT STARTED
|
NA |
25 |
2 Floor
|
30-04-2021
|
NOT STARTED
|
NA |
26 |
3 Floor
|
30-06-2021
|
NOT STARTED
|
NA |
27 |
4 Floor
|
30-08-2021
|
NOT STARTED
|
NA |
Updated Changes on 19-01-2021 |
28 |
Site Development
|
28-12-2019
|
Completed
|
NA |
29 |
NA
|
NA
|
NA
|
NA |
30 |
Ground Floor/Stilt Floor
|
15-01-2021
|
Completed
|
NA |
31 |
1 Floor
|
30-04-2020
|
NOT STARTED
|
NA |
32 |
2 Floor
|
16-06-2020
|
NOT STARTED
|
NA |
33 |
NA
|
NA
|
NA
|
NA |
34 |
Ground Floor/Stilt Floor
|
31-12-2020
|
NOT STARTED
|
NA |
35 |
1 Floor
|
10-02-2021
|
NOT STARTED
|
NA |
36 |
Electrical Works
|
30-06-2022
|
NOT STARTED
|
NA |
37 |
Concealed Cabling including Plugs & switches
|
30-06-2022
|
NOT STARTED
|
NA |
38 |
Installation & Charging of Transformer
|
30-06-2022
|
NOT STARTED
|
NA |
39 |
Connection to Flats/Apartments
|
30-06-2022
|
NOT STARTED
|
NA |
40 |
PH works
|
30-06-2022
|
NOT STARTED
|
NA |
41 |
Laying of concealed Pipes
|
30-06-2022
|
NOT STARTED
|
NA |
42 |
PH Fittings
|
30-09-2022
|
NOT STARTED
|
NA |
43 |
Overhead Water Tanks
|
30-09-2022
|
NOT STARTED
|
NA |
44 |
Water Supply Connection to all units
|
31-10-2022
|
NOT STARTED
|
NA |
45 |
STP construction and completion
|
31-10-2022
|
NOT STARTED
|
NA |
46 |
Distempering & Colouring of all units and exteriors
|
31-10-2022
|
NOT STARTED
|
NA |
47 |
Fixation of doors and windows
|
31-10-2022
|
NOT STARTED
|
NA |
48 |
Scheduled Date of handing over possession
|
09-11-2022
|
NOT STARTED
|
NA |
49 |
Development of common areas, parks, gardens etc
|
08-11-2022
|
NOT STARTED
|
NA |
50 |
3 Floor
|
30-08-2020
|
NOT STARTED
|
NA |
51 |
4 Floor
|
15-10-2020
|
NOT STARTED
|
NA |
52 |
2 Floor
|
30-04-2021
|
NOT STARTED
|
NA |
53 |
3 Floor
|
30-06-2021
|
NOT STARTED
|
NA |
54 |
4 Floor
|
30-08-2021
|
NOT STARTED
|
NA |
Updated Changes on 24-09-2021 |
55 |
Site Development
|
28-12-2019
|
Completed
|
NA |
56 |
NA
|
28-12-2019
|
Completed
|
NA |
57 |
Ground Floor/Stilt Floor
|
15-01-2021
|
Completed
|
NA |
58 |
1 Floor
|
30-04-2020
|
Completed
|
NA |
59 |
2 Floor
|
16-06-2020
|
Completed
|
NA |
60 |
NA
|
16-06-20
|
Completed
|
NA |
61 |
Ground Floor/Stilt Floor
|
31-12-2020
|
Completed
|
NA |
62 |
1 Floor
|
10-02-2021
|
Completed
|
NA |
63 |
Electrical Works
|
30-06-2022
|
NOT STARTED
|
NA |
64 |
Concealed Cabling including Plugs & switches
|
30-06-2022
|
NOT STARTED
|
NA |
65 |
Installation & Charging of Transformer
|
30-06-2022
|
NOT STARTED
|
NA |
66 |
Connection to Flats/Apartments
|
30-06-2022
|
NOT STARTED
|
NA |
67 |
PH works
|
30-06-2022
|
NOT STARTED
|
NA |
68 |
Laying of concealed Pipes
|
30-06-2022
|
NOT STARTED
|
NA |
69 |
PH Fittings
|
30-09-2022
|
NOT STARTED
|
NA |
70 |
Overhead Water Tanks
|
30-09-2022
|
NOT STARTED
|
NA |
71 |
Water Supply Connection to all units
|
31-10-2022
|
NOT STARTED
|
NA |
72 |
STP construction and completion
|
31-10-2022
|
NOT STARTED
|
NA |
73 |
Distempering & Colouring of all units and exteriors
|
31-10-2022
|
NOT STARTED
|
NA |
74 |
Fixation of doors and windows
|
31-10-2022
|
NOT STARTED
|
NA |
75 |
Scheduled Date of handing over possession
|
09-11-2022
|
NOT STARTED
|
NA |
76 |
Development of common areas, parks, gardens etc
|
08-11-2022
|
NOT STARTED
|
NA |
77 |
3 Floor
|
30-08-2020
|
Completed
|
NA |
78 |
4 Floor
|
15-10-2020
|
Completed
|
NA |
79 |
2 Floor
|
30-04-2021
|
Completed
|
NA |
80 |
3 Floor
|
30-06-2021
|
Completed
|
NA |
81 |
4 Floor
|
30-08-2021
|
Completed
|
NA |
Updated Changes on 24-01-2022 |
82 |
Site Development
|
28-12-2019
|
Completed
|
NA |
83 |
NA
|
28-12-2019
|
Completed
|
NA |
84 |
Ground Floor/Stilt Floor
|
15-01-2021
|
Completed
|
|
85 |
1 Floor
|
30-04-2020
|
Completed
|
|
86 |
2 Floor
|
16-06-2020
|
Completed
|
|
87 |
NA
|
16-06-20
|
Completed
|
NA |
88 |
Ground Floor/Stilt Floor
|
31-12-2020
|
Completed
|
NA |
89 |
1 Floor
|
10-02-2021
|
Completed
|
NA |
90 |
Electrical Works
|
30-06-2022
|
NOT STARTED
|
NA |
91 |
Concealed Cabling including Plugs & switches
|
30-06-2022
|
NOT STARTED
|
NA |
92 |
Installation & Charging of Transformer
|
30-06-2022
|
NOT STARTED
|
NA |
93 |
Connection to Flats/Apartments
|
30-06-2022
|
NOT STARTED
|
NA |
94 |
PH works
|
30-06-2022
|
NOT STARTED
|
NA |
95 |
Laying of concealed Pipes
|
30-06-2022
|
NOT STARTED
|
NA |
96 |
PH Fittings
|
30-09-2022
|
NOT STARTED
|
NA |
97 |
Overhead Water Tanks
|
30-09-2022
|
NOT STARTED
|
NA |
98 |
Water Supply Connection to all units
|
31-10-2022
|
NOT STARTED
|
NA |
99 |
STP construction and completion
|
31-10-2022
|
NOT STARTED
|
NA |
100 |
Distempering & Colouring of all units and exteriors
|
31-10-2022
|
NOT STARTED
|
NA |
101 |
Fixation of doors and windows
|
31-10-2022
|
NOT STARTED
|
NA |
102 |
Scheduled Date of handing over possession
|
09-11-2022
|
NOT STARTED
|
NA |
103 |
Development of common areas, parks, gardens etc
|
08-11-2022
|
NOT STARTED
|
NA |
104 |
3 Floor
|
30-08-2020
|
Completed
|
NA |
105 |
4 Floor
|
15-10-2020
|
Completed
|
NA |
106 |
2 Floor
|
30-04-2021
|
Completed
|
NA |
107 |
3 Floor
|
30-06-2021
|
Completed
|
NA |
108 |
4 Floor
|
30-08-2021
|
Completed
|
NA |
Updated Changes on 14-04-2023 |
109 |
Site Development
|
28-12-2019
|
Completed
|
NA |
110 |
NA
|
28-12-2019
|
Completed
|
NA |
111 |
Ground Floor/Stilt Floor
|
15-01-2021
|
Completed
|
NA |
112 |
1 Floor
|
30-04-2020
|
Completed
|
NA |
113 |
2 Floor
|
16-06-2020
|
Completed
|
NA |
114 |
NA
|
16-06-20
|
Completed
|
NA |
115 |
Ground Floor/Stilt Floor
|
31-12-2020
|
Completed
|
NA |
116 |
1 Floor
|
10-02-2021
|
Completed
|
NA |
117 |
Electrical Works
|
30-06-2022
|
Completed
|
NA |
118 |
Concealed Cabling including Plugs & switches
|
30-06-2022
|
Completed
|
NA |
119 |
Installation & Charging of Transformer
|
30-06-2022
|
Completed
|
NA |
120 |
Connection to Flats/Apartments
|
30-06-2022
|
Completed
|
NA |
121 |
PH works
|
30-06-2022
|
Completed
|
NA |
122 |
Laying of concealed Pipes
|
30-06-2022
|
Completed
|
NA |
123 |
PH Fittings
|
30-09-2022
|
Completed
|
NA |
124 |
Overhead Water Tanks
|
30-09-2022
|
Completed
|
NA |
125 |
Water Supply Connection to all units
|
31-10-2022
|
Completed
|
NA |
126 |
STP construction and completion
|
31-10-2022
|
Completed
|
NA |
127 |
Distempering & Colouring of all units and exteriors
|
31-10-2022
|
Completed
|
|
128 |
Fixation of doors and windows
|
31-10-2022
|
Completed
|
NA |
129 |
Scheduled Date of handing over possession
|
09-11-2022
|
Completed
|
|
130 |
Development of common areas, parks, gardens etc
|
08-11-2022
|
Completed
|
NA |
131 |
3 Floor
|
30-08-2020
|
Completed
|
NA |
132 |
4 Floor
|
15-10-2020
|
Completed
|
NA |
133 |
2 Floor
|
30-04-2021
|
Completed
|
NA |
134 |
3 Floor
|
30-06-2021
|
Completed
|
NA |
135 |
4 Floor
|
30-08-2021
|
Completed
|
NA |