1 |
The land/building shall be used exclusively commercial-cum-residential building and the uses shall not be changed to any other use without prior approval of this Authority.
|
31-07-2022
|
NOT STARTED
|
2 |
Parking space measuring 867.70 sqm (covered parking -697.42+open parking-170.28) as shown in the approved plan shall be strictly adhered.
|
31-07-2022
|
NOT STARTED
|
3 |
The land over which construction is proposed is accessible by an approved means of access of 18.00 mtr width.
|
31-07-2022
|
NOT STARTED
|
4 |
10% of the land shall be utilized for plantation.
|
31-07-2022
|
NOT STARTED
|
5 |
The conditions relating to development of roads and drains shall be complied first before start of the project as suggested by BMC, bramapur are to be strictly followed.
|
31-07-2022
|
NOT STARTED
|
6 |
For safe discharge of effluent an inverted filter of adequate size is to be constructed and treated effluent BOD5 at 20C should be less than 30 mg/l only be disposed to municipal drain to avoid contamination of sub-soil water and for proper drainage and sanitation the conditions imposed by BMC, Barhampur are to be strictly adhered for drainage of waste water generated by the occupants of the building.
|
31-07-2022
|
NOT STARTED
|
7 |
Fire safety measures and arrangement as per recommendations of the RECOMM1408260012021000283, DATED 12.10.2021 as per Affidavit dated 1.3.2017 are to be strictly followed.
|
31-07-2022
|
NOT STARTED
|
8 |
The conditions imposed and communicated by the Regional Director, CGWA New Delhi are to be followed to catar the domestic requirements of the occupants and sanitation of the proposed building.
|
31-07-2022
|
NOT STARTED
|
9 |
The apartment building B+G+3storied commercial-cum-residential building is to be constructed confirming to the approved plan and sgtructural design prepared by Regd structural engineer as per the provision of NBC taking into account the safety factors like cyclone and earthqualke etc. and it is the combined responsibility of the owner /developer /architect/structure engineer if there is structural failuire due to any structural defects for whatsoever reason endangering the inmates and the public.
|
31-07-2022
|
NOT STARTED
|
10 |
The promoter shall obtain necessary permission from the SOUTHCO regarding safety for electrical installation and connection.
|
31-07-2022
|
NOT STARTED
|
11 |
The applicant shall not occupy or permit to occupy the building or permit to use the building or any part thereof until completion certificate is submitted to this authority as per section-20 of the ODA Act and regulations.
|
31-07-2022
|
NOT STARTED
|
12 |
The authority shall stand indemnified and kept harmless against all proceeding in any court of before any authorities and all expenses /losses claims which this authority may incur or become liable to pay as a result or in consequence thereof.
|
31-07-2022
|
NOT STARTED
|
13 |
The developer shall make own arrangement for supply of drinking water shall not insist upon PHED for providing water from the city water supply system.
|
31-07-2022
|
NOT STARTED
|
14 |
The residential building shall not be occupied without obtaining occupancy certificate of BDA as required under building regulations.
|
31-07-2022
|
NOT STARTED
|
15 |
The set back as indicated in the building plan shall be strictly adhered.
|
31-07-2022
|
NOT STARTED
|
16 |
The space meant for parking shall not be changed to any other use and shall not be partitioned closed in any manner.
|
31-07-2022
|
NOT STARTED
|
17 |
20% of the parking space shall exclusively earmarked visitors.
|
31-07-2022
|
NOT STARTED
|
18 |
He has to construct garbage bin not less than 100sqm within his premises for smooth management of solid waste.
|
31-07-2022
|
NOT STARTED
|
19 |
The developer has construct roof rain water harvesting structure @6cum for 100sqm of terrace area.
|
31-07-2022
|
NOT STARTED
|
20 |
Adequate safety measures shall be adopted for treatment and disposal of septic tank effluent under no circumstances untreated night soil shall be discharged into the drains. Inverted filters if necessary shall be constructed and the effluent from the septic tank/soak pit shall flow through them ensure reduction of containment level to the standarddes fixed by OPCB and CPCB before discharge into the drains.
|
31-07-2022
|
NOT STARTED
|
21 |
No further floor in future is allowed beyond B+G+3 considering the ground coverage and set back provided in construction of B+G+3 commercial-cum-residential building.
|
31-07-2022
|
NOT STARTED
|
Updated Changes on 15-07-2023 |
22 |
The land/building shall be used exclusively commercial-cum-residential building and the uses shall not be changed to any other use without prior approval of this Authority.
|
31-07-2022
|
WILL COMPLY AS PER CONDITION
|
23 |
Parking space measuring 867.70 sqm (covered parking -697.42+open parking-170.28) as shown in the approved plan shall be strictly adhered.
|
31-07-2022
|
COMPLETED
|
24 |
The land over which construction is proposed is accessible by an approved means of access of 18.00 mtr width.
|
31-07-2022
|
COMPLETED
|
25 |
10% of the land shall be utilized for plantation.
|
31-07-2022
|
NOT STARTED
|
26 |
The conditions relating to development of roads and drains shall be complied first before start of the project as suggested by BMC, bramapur are to be strictly followed.
|
31-07-2022
|
IN PROGRESS
|
27 |
For safe discharge of effluent an inverted filter of adequate size is to be constructed and treated effluent BOD5 at 20C should be less than 30 mg/l only be disposed to municipal drain to avoid contamination of sub-soil water and for proper drainage and sanitation the conditions imposed by BMC, Barhampur are to be strictly adhered for drainage of waste water generated by the occupants of the building.
|
31-07-2022
|
NOT STARTED
|
28 |
Fire safety measures and arrangement as per recommendations of the RECOMM1408260012021000283, DATED 12.10.2021 as per Affidavit dated 1.3.2017 are to be strictly followed.
|
31-07-2022
|
IN PROGRESS
|
29 |
The conditions imposed and communicated by the Regional Director, CGWA New Delhi are to be followed to catar the domestic requirements of the occupants and sanitation of the proposed building.
|
31-07-2022
|
NOT STARTED
|
30 |
The apartment building B+G+3storied commercial-cum-residential building is to be constructed confirming to the approved plan and sgtructural design prepared by Regd structural engineer as per the provision of NBC taking into account the safety factors like cyclone and earthqualke etc. and it is the combined responsibility of the owner /developer /architect/structure engineer if there is structural failuire due to any structural defects for whatsoever reason endangering the inmates and the public.
|
31-07-2022
|
NOT STARTED
|
31 |
The promoter shall obtain necessary permission from the SOUTHCO regarding safety for electrical installation and connection.
|
31-07-2022
|
IN PROGRESS
|
32 |
The applicant shall not occupy or permit to occupy the building or permit to use the building or any part thereof until completion certificate is submitted to this authority as per section-20 of the ODA Act and regulations.
|
31-07-2022
|
NOT STARTED
|
33 |
The authority shall stand indemnified and kept harmless against all proceeding in any court of before any authorities and all expenses /losses claims which this authority may incur or become liable to pay as a result or in consequence thereof.
|
31-07-2022
|
NOT STARTED
|
34 |
The developer shall make own arrangement for supply of drinking water shall not insist upon PHED for providing water from the city water supply system.
|
31-07-2022
|
NOT STARTED
|
35 |
The residential building shall not be occupied without obtaining occupancy certificate of BDA as required under building regulations.
|
31-07-2022
|
NOT STARTED
|
36 |
The set back as indicated in the building plan shall be strictly adhered.
|
31-07-2022
|
NOT STARTED
|
37 |
The space meant for parking shall not be changed to any other use and shall not be partitioned closed in any manner.
|
31-07-2022
|
COMPLY AS PER CONDITION
|
38 |
20% of the parking space shall exclusively earmarked visitors.
|
31-07-2022
|
IN PROGRESS
|
39 |
He has to construct garbage bin not less than 100sqm within his premises for smooth management of solid waste.
|
31-07-2022
|
NOT STARTED
|
40 |
The developer has construct roof rain water harvesting structure @6cum for 100sqm of terrace area.
|
31-07-2022
|
NOT STARTED
|
41 |
Adequate safety measures shall be adopted for treatment and disposal of septic tank effluent under no circumstances untreated night soil shall be discharged into the drains. Inverted filters if necessary shall be constructed and the effluent from the septic tank/soak pit shall flow through them ensure reduction of containment level to the standarddes fixed by OPCB and CPCB before discharge into the drains.
|
31-07-2022
|
NOT STARTED
|
42 |
No further floor in future is allowed beyond B+G+3 considering the ground coverage and set back provided in construction of B+G+3 commercial-cum-residential building.
|
31-07-2022
|
NOT STARTED
|
Updated Changes on 14-07-2024 |
43 |
The land/building shall be used exclusively commercial-cum-residential building and the uses shall not be changed to any other use without prior approval of this Authority.
|
31-07-2022
|
WILL COMPLY AS PER CONDITION
|
44 |
Parking space measuring 867.70 sqm (covered parking -697.42+open parking-170.28) as shown in the approved plan shall be strictly adhered.
|
31-07-2022
|
COMPLETED
|
45 |
The land over which construction is proposed is accessible by an approved means of access of 18.00 mtr width.
|
31-07-2022
|
COMPLETED
|
46 |
10% of the land shall be utilized for plantation.
|
31-07-2022
|
NOT STARTED
|
47 |
The conditions relating to development of roads and drains shall be complied first before start of the project as suggested by BMC, bramapur are to be strictly followed.
|
31-07-2022
|
IN PROGRESS
|
48 |
For safe discharge of effluent an inverted filter of adequate size is to be constructed and treated effluent BOD5 at 20C should be less than 30 mg/l only be disposed to municipal drain to avoid contamination of sub-soil water and for proper drainage and sanitation the conditions imposed by BMC, Barhampur are to be strictly adhered for drainage of waste water generated by the occupants of the building.
|
31-07-2022
|
WILL COMPLY AS PER CONDITION
|
49 |
Fire safety measures and arrangement as per recommendations of the RECOMM1408260012021000283, DATED 12.10.2021 as per Affidavit dated 1.3.2017 are to be strictly followed.
|
31-07-2022
|
IN PROGRESS
|
50 |
The conditions imposed and communicated by the Regional Director, CGWA New Delhi are to be followed to catar the domestic requirements of the occupants and sanitation of the proposed building.
|
31-07-2022
|
WILL COMPLY AS PER CONDITION
|
51 |
The apartment building B+G+3storied commercial-cum-residential building is to be constructed confirming to the approved plan and sgtructural design prepared by Regd structural engineer as per the provision of NBC taking into account the safety factors like cyclone and earthqualke etc. and it is the combined responsibility of the owner /developer /architect/structure engineer if there is structural failuire due to any structural defects for whatsoever reason endangering the inmates and the public.
|
31-07-2022
|
COMPLETED
|
52 |
The promoter shall obtain necessary permission from the SOUTHCO regarding safety for electrical installation and connection.
|
31-07-2022
|
COMPLETED
|
53 |
The applicant shall not occupy or permit to occupy the building or permit to use the building or any part thereof until completion certificate is submitted to this authority as per section-20 of the ODA Act and regulations.
|
31-07-2022
|
WILL COMPLY AS PER CONDITION
|
54 |
The authority shall stand indemnified and kept harmless against all proceeding in any court of before any authorities and all expenses /losses claims which this authority may incur or become liable to pay as a result or in consequence thereof.
|
31-07-2022
|
WILL COMPLY AS PER CONDITION
|
55 |
The developer shall make own arrangement for supply of drinking water shall not insist upon PHED for providing water from the city water supply system.
|
31-07-2022
|
UNDER PROGRESS
|
56 |
The residential building shall not be occupied without obtaining occupancy certificate of BDA as required under building regulations.
|
31-07-2022
|
WILL COMPLY AS PER CONDITION
|
57 |
The set back as indicated in the building plan shall be strictly adhered.
|
31-07-2022
|
COMPLETED
|
58 |
The space meant for parking shall not be changed to any other use and shall not be partitioned closed in any manner.
|
31-07-2022
|
COMPLY AS PER CONDITION
|
59 |
20% of the parking space shall exclusively earmarked visitors.
|
31-07-2022
|
IN PROGRESS
|
60 |
He has to construct garbage bin not less than 100sqm within his premises for smooth management of solid waste.
|
31-07-2022
|
IN PROGRESS
|
61 |
The developer has construct roof rain water harvesting structure @6cum for 100sqm of terrace area.
|
31-07-2022
|
COMPLETED
|
62 |
Adequate safety measures shall be adopted for treatment and disposal of septic tank effluent under no circumstances untreated night soil shall be discharged into the drains. Inverted filters if necessary shall be constructed and the effluent from the septic tank/soak pit shall flow through them ensure reduction of containment level to the standarddes fixed by OPCB and CPCB before discharge into the drains.
|
31-07-2022
|
COMPLY AS PER CONDITION
|
63 |
No further floor in future is allowed beyond B+G+3 considering the ground coverage and set back provided in construction of B+G+3 commercial-cum-residential building.
|
31-07-2022
|
AGREE
|