: Silkcity Developers | : Partnership |
: 1120202100272 of 2021 | :View |
NA | : Rajiv Nagar, 1st Lane, Behind Govt ITI, Khodasingi, Berhampur, PIN-760010, Dist-Ganjam |
: Rajiv Nagar, 1st Lane, Behind Govt. ITI, Khodasingi, Berhampur, Dist- Ganjam, Pin- 760010. | : pkp_s@yahoo.co.in |
: 7788919705 | |
: AECFS3476G | :View |
: 8 MONTHS | : No Experience |
NA |
: Pradeep Kumar Panigrahy | : |
: Partner | : AKPPP8580M |
:PAN Card | : pkp_s@yahoo.co.in |
: DME (Mech) | : 7788919705 |
: 25 years ( Ex General Manager of DLF Ltd) | |
: Yes | : NA |
: J. Nageswara Rao | : |
: Partner | : ADOPR3673F |
:PAN Card | : j.nageswar16@gmail.com |
: Graduate | : 9437064556 |
: 10 years of experience | |
: Yes | : NA |
: Prasanna Kumar Patro | : |
: Partner | : BZGPP7835N |
:PAN Card | : prasanna76patro@gmail.com |
: Graduate | : 9040168033 |
: 10 years of experience | |
: Yes | : NA |
: Simanchal Gouda | : |
: Partner | : AFSPG5961M |
:PAN Card | : simanchalagouda66@gmail.com |
: Graduate | : 7008509365 |
: 10 years of experience | |
: Yes | : NA |
: Saudamini Rath | : |
: Partner | : AESPR1304J |
:PAN Card | : soudaminirath65@gmail.com |
: Graduate | : 7978969116 |
: 10 years of experience | |
: Yes | : NA |
: Sankar Narayan Mohanty | : |
: Partner | : AOPPM0440K |
:PAN Card | : sankarmohanty456@gmail.com |
: Graduate | : 9861978823 |
: 10 years of experience | |
: Yes | : NA |
: New | : PANCHAVATI |
: Residential | : ( Residential Project, S+4, No. of Units - 68 ) |
: Ganjam | : Berhampur MC |
: 760006 | : Urban Local Body |
: Berhampur Municipal Corporation | |
: S+4 storied Residential Apartment | : NA |
: 45 | : 283/1226 |
: Sankarpur | : 842 |
: Yes | |
No | : View |
: View | |
: Other Person | |
: Chandra Sekhar Sabat | : The land owner has executed development agreement with the promoter and also the promoter is the GPA holder over the project plot. |
: No | |
: Yes | |
: 10612001264 | : 07-03-2020 |
: Sub-Registrar, Berhampur | : Attached |
: 45/1069 | : 283/1226 |
: Sankarpur | : 162 |
: Yes | |
No | : View |
: View | |
: Other Person | |
: Chandra Sekhar Sabat | : The land owner has executed development agreement with the promoter and also the promoter is the GPA holder over the project plot |
: No | |
: Yes | |
: 10612001264 | : 07-03-2020 |
: Sub-Registrar, Berhampur | : Attached |
: 45/1504 | : 283/1226 |
: Sankarpur | : 680 |
: Yes | |
No | : View |
: View | |
: Other Person | |
: Chandra Sekhar Sabat | : The land owner has executed development agreement with the promoter and also the promoter is the GPA holder over the project plot |
: No | |
: Yes | |
: 10612001264 | : 07-03-2020 |
: Sub-Registrar, Berhampur | : Attached |
: 45/1067 | : 283/2160 |
: Sankarpur | : 789 |
: Yes | |
No | : View |
: View | |
: Other Person | |
: Chandra Sekhar Sabat | : The land owner has executed development agreement with the promoter and also the promoter is the GPA holder over the project plot |
: No | |
: Yes | |
: 10612001264 | : 07-03-2020 |
: Sub-Registrar, Berhampur | : Attached |
: 45/1068 | : 283/1318 |
: Sankarpur | : 259 |
: Yes | |
No | : View |
: View | |
: Other Person | |
: Chandra Sekhar Sabat | : The land owner has executed development agreement with the promoter and also the promoter is the GPA holder over the project plot |
: No | |
: Yes | |
: 10612001264 | : 07-03-2020 |
: Sub-Registrar, Berhampur | : Attached |
: 39/2245 | : 283/1059 |
: Sankarpur | : 198 |
: Yes | |
No | : View |
: View | |
: Other Person | |
: Chandra Sekhar Sabat | : The land owner has executed development agreement with the promoter and also the promoter is the GPA holder over the project plot |
: No | |
: Yes | |
: 10612001264 | : 07-03-2020 |
: Sub-Registrar, Berhampur | : Attached |
: 40/2246 | : 283/1059 |
: Sankarpur | : 202 |
: Yes | |
No | : View |
: View | |
: Other Person | |
: Chandra Sekhar Sabat | : The land owner has executed development agreement with the promoter and also the promoter is the GPA holder over the project plot |
: No | |
: Yes | |
: 10612001264 | : 07-03-2020 |
: Sub-Registrar, Berhampur | : Attached |
: Yes |
Serial No. | Particulars of the Person | Land/Plot Details | Share of the Person | Document Attached |
---|---|---|---|---|
1 | Chandra Sekhar Sabat | Plot no. 45, 45/1069, 45/1504, 45/1067,45/1068, 39/2245 and 40/2246, Khata No. 283 /1226, 283/ 2160, 283/1318 and 283/1059 | 33% | Agreement Copy |
View | View |
Download site plan | 24-02-2024 |
Sl. No. | Description of Conditions | Schedule date of compliance | Present Status |
---|---|---|---|
1 | Parking space measuring 1524 sqm as shown in the approved plan shall be strictly adhered | 24-02-2024 | Not started |
2 | The land over which construction is proposed is access able by an approved means of access of 12.19 mtr. Width | 24-02-2024 | Not started |
3 | 20% of the land shall be utilized for plantation. | 24-02-2024 | Not started |
4 | The permit tee shall keep the BeMC Berhampur informed in writing at least one week before starting construction as per Regulation No. 15 of the B.D.A Planning and Building (Standards) Regulations. | 24-02-2024 | Not started |
5 | The conditions relating to development of roads and drains shall be complied first before start of the project as suggested by BeMC, Berhampur vide Letter No. 1533 dated 29.01'.202L & as per Affidavit dated 07.o2.2021. | 24-02-2024 | Not started |
6 | For safe discharge of effluent, an inverted filter of adequate size is to be constructed and treated effluent BODS at 20 C should be less than 30 mg/l only be disposed to municipal drain to avoid contamination of sub-soil water and for proper drainage and sanitation, the conditions imposed by Municipal Commissioner, Berhampur Municipal Corporation as per Affidavit dated OL.O2.2O2L are to be strictly adhered for drainage of waste water generated by the occupants of the apartment. | 24-02-2024 | Not started |
7 | Fire safety measures and arrangement as per under taking on dated 0L.02.2021, are to be strictly followed. | 24-02-2024 | Not started |
8 | The promoter shall obtain necessary permission from the SOUTHCO regarding safety for electrical installation and connection | 24-02-2024 | Not started |
9 | The applicant shall not occupy or permit to occupy the building or permit to use the building or any part thereof until completion certificate is submitted to this authority as per section-20 of the O.D.A Act and the Regulations. | 24-02-2024 | Not started |
10 | Adequate safety measures shall be adopted for treatment and disposal of septic tank effluent under no circumstances untreated right soil shall be discharged in to the drains inverted filter, if necessary, shall be constructed and the effluent from the septic tank/soak pit shall flow through them to ensure reduction of contaminant level to the standards fixed by OPCB and CPCB before discharge into the drains. | 24-02-2024 | Not started |
11 | The space meant for parking shall not be changed to any other use and shall not be partitioned / closed in any manner. | 24-02-2024 | Not started |
12 | 25 % area of pa rking space shall be earmarked for visitors. | 24-02-2024 | Not started |
13 | He has to construct garbage storage bin not less than L00 sqm. Within his premises for smooth management of solid waste. | 24-02-2024 | Not started |
14 | The developer has to construct roof rain water harvesting structure @ 6 cum for 100 sqm. of terrace area. | 24-02-2024 | Not started |
: Yes | : View |
Point No. | Latitude | Longitude |
---|---|---|
1 | 19°20'11.2"N | 84°46'05.4"E |
2 | 19°20'09.9"N | 84°46'05.4"E |
3 | 19°20'09.7"N | 84°46'05.6"E |
4 | 19°20'09.7"N | 84°46'05.9"E |
5 | 19°20'09.9"N | 84°46'06.7"E |
6 | 19°20'09.6"N | 84°46'06.7"E |
7 | 19°20'08.6"N | 84°46'06.0"E |
8 | 19°20'08.4"N | 84°46'04.2"E'' |
9 | 19°20'08.5"N | 84°46'04.0"E |
10 | 19°20'09.5"N | 84°46'04.3"E |
11 | 19°20'10.1"N'' | 84°46'04.6"E |
12 | 19°20'10.3"N'' | 84°46'04.5"E |
13 | 19°20'10.5"N | 84°46'04.6"E |
14 | 19°20'10.8"N | 84°46'04.7"E |
15 | 19°20'11.2"N | 84°46'04.6"E |
16 | 19°20'11.2"N | 84°46'04.7"E |
Description* | Scheduled date of completion | Current Status | Site Images |
---|---|---|---|
Site Development | 31-08-2021 | In progress | |
Roof Casting | NA | NA | NA |
Ground Floor/Stilt Floor | 31-10-2021 | In progress | |
1 Floor | 31-12-2021 | Not started | NA |
2 Floor | 28-02-2022 | Not started | NA |
3 Floor | 30-04-2022 | Not started | NA |
4 Floor | 30-06-2022 | Not started | NA |
Brick Work & Plastering | NA | NA | NA |
Ground Floor/Stilt Floor | 30-04-2022 | Not started | NA |
1 Floor | 30-06-2022 | Not started | NA |
2 Floor | 15-08-2022 | Not started | NA |
3 Floor | 30-09-2022 | Not started | NA |
4 Floor | 15-11-2022 | Not started | NA |
Electrical Works | 31-01-2023 | Not started | NA |
Concealed Cabling including Plugs & switches | 31-01-2023 | Not started | NA |
Installation & Charging of Transformer | 15-11-2022 | Not started | NA |
Connection to Flats/Apartments | 31-01-2023 | Not started | NA |
PH works | 31-03-2023 | Not started | NA |
Laying of concealed Pipes | 31-03-2023 | Not started | NA |
PH Fittings | 31-03-2023 | Not started | NA |
Overhead Water Tanks | 31-03-2023 | Not started | NA |
Water Supply Connection to all units | 31-03-2023 | Not started | NA |
STP construction and completion | 31-05-2023 | Not started | NA |
Distempering & Colouring of all units and exteriors | 31-07-2023 | Not started | NA |
Fixation of doors and windows | 31-10-2023 | Not started | NA |
Scheduled Date of handing over possession | 31-03-2024 | Not started | NA |
Development of common areas, parks, gardens etc | 24-02-2024 | Not started | NA |
Site Development | 31-08-2021 | Completed | NA |
NA | NA | NA | NA |
Ground Floor/Stilt Floor | 31-10-2021 | Completed | NA |
1 Floor | 31-12-2021 | Completed | NA |
2 Floor | 28-02-2022 | Completed | NA |
3 Floor | 30-04-2022 | Completed | NA |
4 Floor | 30-06-2022 | Completed | NA |
NA | NA | NA | NA |
Ground Floor/Stilt Floor | 30-04-2022 | Under Process | NA |
1 Floor | 30-06-2022 | Under Process | NA |
2 Floor | 15-08-2022 | Under Process | NA |
3 Floor | 30-09-2022 | Under Process | NA |
4 Floor | 15-11-2022 | Under Process | NA |
Electrical Works | 31-01-2023 | Under Process | NA |
Concealed Cabling including Plugs & switches | 31-01-2023 | Not Started | NA |
Installation & Charging of Transformer | 15-11-2022 | Not started | NA |
Connection to Flats/Apartments | 31-01-2023 | Not started | NA |
PH works | 31-03-2023 | Under Process | NA |
Laying of concealed Pipes | 31-03-2023 | Not started | NA |
PH Fittings | 31-03-2023 | Not started | NA |
Overhead Water Tanks | 31-03-2023 | Not started | NA |
Water Supply Connection to all units | 31-03-2023 | Not started | NA |
STP construction and completion | 31-05-2023 | Not started | NA |
Distempering & Colouring of all units and exteriors | 31-07-2023 | Not started | NA |
Fixation of doors and windows | 31-10-2023 | Not started | NA |
Scheduled Date of handing over possession | 31-03-2024 | Not started | NA |
Development of common areas, parks, gardens etc | 24-02-2024 | Not started | NA |
: Residential | |
: 68
|
|
Residential Flats/ House | |||||
---|---|---|---|---|---|
S. No. | Flat No./ House No. | ||||
Area in square metres |
Ownership | ||||
Carpet Area | Balcony Area | Exclusive Open Terrace Area | |||
1 | 101 | 56.35 | 3.5 | Nil | Promoter |
2 | 102 | 68.27 | 2.79 | Nil | Land Owner |
3 | 103 | 56.79 | 3.35 | Nil | Promoter |
4 | 104 | 55.65 | 4.85 | Nil | Promoter |
5 | 105 | 68.86 | 4.85 | Nil | Promoter |
6 | 106 | 67.00 | 4.05 | Nil | Promoter |
7 | 107 | 66.45 | 4.76 | Nil | Land Owner |
8 | 108 | 66.45 | 3.35 | Nil | Promoter |
9 | 109 | 66.45 | 4.75 | Nil | Promoter |
10 | 110 | 78.95 | 4.75 | Nil | Promoter |
11 | 111 | 52.35 | 6.48 | Nil | Land Owner |
12 | 112 | 57.50 | 6.46 | Nil | Promoter |
13 | 113 | 59.25 | 4.25 | Nil | Promoter |
14 | 114 | 73.80 | 3.95 | Nil | Promoter |
15 | 115 | 67.75 | Nil | Nil | Land Owner |
16 | 116 | 71.42 | 5.67 | Nil | Land Owner |
17 | 117 | 74.98 | 5.67 | Nil | Land Owner |
18 | 201 | 56.35 | 3.5 | Nil | Promoter |
19 | 202 | 68.27 | 2.79 | Nil | Promoter |
20 | 203 | 56.79 | 3.35 | Nil | Promoter |
21 | 204 | 55.65 | 4.85 | Nil | Promoter |
22 | 205 | 68.86 | 4.85 | Nil | Land Owner |
23 | 206 | 67.00 | 4.05 | Nil | Promoter |
24 | 207 | 66.45 | 4.76 | Nil | Promoter |
25 | 208 | 66.45 | 3.35 | Nil | Land Owner |
26 | 209 | 66.45 | 4.75 | Nil | Promoter |
27 | 210 | 78.95 | 4.75 | Nil | Promoter |
28 | 211 | 52.35 | 6.48 | Nil | Land Owner |
29 | 212 | 57.50 | 6.46 | Nil | Land Owner |
30 | 213 | 59.25 | 4.25 | Nil | Promoter |
31 | 214 | 73.80 | 3.95 | Nil | Land Owner |
32 | 215 | 67.75 | Nil | Nil | Promoter |
33 | 216 | 71.42 | 5.67 | Nil | Land Owner |
34 | 217 | 74.98 | 5.67 | Nil | Promoter |
35 | 301 | 56.35 | 3.5 | Nil | Promoter |
36 | 302 | 68.27 | 2.79 | Nil | Land Owner |
37 | 303 | 56.79 | 3.35 | Nil | Promoter |
38 | 304 | 55.65 | 4.85 | Nil | Land Owner |
39 | 305 | 68.86 | 4.85 | Nil | Promoter |
40 | 306 | 67.00 | 4.05 | Nil | Promoter |
41 | 307 | 66.45 | 4.76 | Nil | Land Owner |
42 | 308 | 66.45 | 3.35 | Nil | Promoter |
43 | 309 | 66.45 | 4.75 | Nil | Promoter |
44 | 310 | 78.95 | 4.75 | Nil | Promoter |
45 | 311 | 52.35 | 6.48 | Nil | Promoter |
46 | 312 | 57.50 | 6.46 | Nil | Promoter |
47 | 313 | 59.25 | 4.25 | Nil | Land Owner |
48 | 314 | 73.80 | 3.95 | Nil | Promoter |
49 | 315 | 67.75 | Nil | Nil | Land Owner |
50 | 316 | 71.42 | 5.67 | Nil | Promoter |
51 | 317 | 74.98 | 5.67 | Nil | Promoter |
52 | 401 | 56.35 | 3.5 | Nil | Promoter |
53 | 402 | 68.27 | 2.79 | Nil | Promoter |
54 | 403 | 56.79 | 3.35 | Nil | Land Owner |
55 | 404 | 55.65 | 4.85 | Nil | Land Owner |
56 | 405 | 68.86 | 4.85 | Nil | Promoter |
57 | 406 | 67.00 | 4.05 | Nil | Land Owner |
58 | 407 | 66.45 | 4.76 | Nil | Promoter |
59 | 408 | 66.45 | 3.35 | Nil | Promoter |
60 | 409 | 66.45 | 4.75 | Nil | Land Owner |
61 | 410 | 78.95 | 4.75 | Nil | Land Owner |
62 | 411 | 52.35 | 6.48 | Nil | Promoter |
63 | 412 | 57.50 | 6.46 | Nil | Promoter |
64 | 413 | 59.25 | 4.25 | Nil | Promoter |
65 | 414 | 73.80 | 3.95 | Nil | Promoter |
66 | 415 | 67.75 | Nil | Nil | Promoter |
67 | 416 | 71.42 | 5.67 | Nil | Promoter |
68 | 417 | 74.98 | 5.67 | Nil | Land Owner |
Types of garages and parking | ||||||
---|---|---|---|---|---|---|
House No. | Type of Garage/ Parking allotted | Serial No., if any | Dimension (Length x Width) in Metres | Floor area in sq. metres | Garage/Parking area cost is included or additional | |
101 | Covered Parking | 1 | 4.26MX3.10M | 13.20SQM | Included | 102 | Covered Parking | 2 | 4.26MX3.10M | 13.20SQM | Included | 103 | Covered Parking | 3 | 4.26MX3.10M | 13.20SQM | Included | 104 | Covered Parking | 4 | 4.26MX3.10M | 13.20SQM | Included | 105 | Covered Parking | 5 | 4.26MX3.10M | 13.20SQM | Included | 106 | Covered Parking | 6 | 4.26MX3.10M | 13.20SQM | Included | 107 | Covered Parking | 7 | 4.26MX3.10M | 13.20SQM | Included | 108 | Covered Parking | 8 | 4.26MX3.10M | 13.20SQM | Included | 109 | Covered Parking | 9 | 4.26MX3.10M | 13.20SQM | Included | 110 | Covered Parking | 10 | 4.26MX3.10M | 13.20SQM | Included | 111 | Covered Parking | 11 | 4.26MX3.10M | 13.20SQM | Included | 112 | Covered Parking | 12 | 4.26MX3.10M | 13.20SQM | Included | 113 | Covered Parking | 13 | 4.26MX3.10M | 13.20SQM | Included | 114 | Covered Parking | 14 | 4.26MX3.10M | 13.20SQM | Included | 115 | Covered Parking | 15 | 4.26MX3.10M | 13.20SQM | Included | 116 | Covered Parking | 16 | 4.26MX3.10M | 13.20SQM | Included | 117 | Covered Parking | 17 | 4.26MX3.10M | 13.20SQM | Included | 201 | Covered Parking | 18 | 4.26MX3.10M | 13.20SQM | Included | 202 | Covered Parking | 19 | 4.26MX3.10M | 13.20SQM | Included | 203 | Covered Parking | 20 | 4.26MX3.10M | 13.20SQM | Included | 204 | Covered Parking | 21 | 4.26MX3.10M | 13.20SQM | Included | 205 | Covered Parking | 22 | 4.26MX3.10M | 13.20SQM | Included | 206 | Covered Parking | 23 | 4.26MX3.10M | 13.20SQM | Included | 207 | Covered Parking | 24 | 4.26MX3.10M | 13.20SQM | Included | 208 | Covered Parking | 25 | 4.26MX3.10M | 13.20SQM | Included | 209 | Covered Parking | 26 | 4.26MX3.10M | 13.20SQM | Included | 210 | Covered Parking | 27 | 4.26MX3.10M | 13.20SQM | Included | 211 | Covered Parking | 28 | 4.26MX3.10M | 13.20SQM | Included | 212 | Covered Parking | 29 | 4.26MX3.10M | 13.20SQM | Included | 213 | Covered Parking | 30 | 4.26MX3.10M | 13.20SQM | Included | 214 | Covered Parking | 31 | 4.26MX3.10M | 13.20SQM | Included | 215 | Covered Parking | 32 | 4.26MX3.10M | 13.20SQM | Included | 216 | Covered Parking | 33 | 4.26MX3.10M | 13.20SQM | Included | 217 | Covered Parking | 34 | 4.26MX3.10M | 13.20SQM | Included | 301 | Covered Parking | 35 | 4.26MX3.10M | 13.20SQM | Included | 302 | Covered Parking | 36 | 4.26MX3.10M | 13.20SQM | Included | 303 | Covered Parking | 37 | 4.26MX3.10M | 13.20SQM | Included | 304 | Covered Parking | 38 | 4.26MX3.10M | 13.20SQM | Included | 305 | Covered Parking | 39 | 4.26MX3.10M | 13.20SQM | Included | 306 | Covered Parking | 40 | 4.26MX3.10M | 13.20SQM | Included | 307 | Covered Parking | 41 | 4.26MX3.10M | 13.20SQM | Included | 308 | Covered Parking | 42 | 4.26MX3.10M | 13.20SQM | Included | 309 | Covered Parking | 43 | 4.26MX3.10M | 13.20SQM | Included | 310 | Covered Parking | 44 | 4.26MX3.10M | 13.20SQM | Included | 311 | Covered Parking | 45 | 4.26MX3.10M | 13.20SQM | Included | 312 | Covered Parking | 46 | 4.26MX3.10M | 13.20SQM | Included | 313 | Covered Parking | 47 | 4.26MX3.10M | 13.20SQM | Included | 314 | Covered Parking | 48 | 4.26MX3.10M | 13.20SQM | Included | 315 | Covered Parking | 49 | 4.26MX3.10M | 13.20SQM | Included | 316 | Covered Parking | 50 | 4.26MX3.10M | 13.20SQM | Included | 317 | Covered Parking | 51 | 4.26MX3.10M | 13.20SQM | Included | 401 | Covered Parking | 52 | 4.26MX3.10M | 13.20SQM | Included | 402 | Covered Parking | 53 | 4.26MX3.10M | 13.20SQM | Included | 403 | Covered Parking | 54 | 4.26MX3.10M | 13.20SQM | Included | 404 | Covered Parking | 55 | 4.26MX3.10M | 13.20SQM | Included | 405 | Covered Parking | 56 | 4.26MX3.10M | 13.20SQM | Included | 406 | Covered Parking | 57 | 4.26MX3.10M | 13.20SQM | Included | 407 | Covered Parking | 58 | 4.26MX3.10M | 13.20SQM | Included | 408 | Covered Parking | 59 | 4.26MX3.10M | 13.20SQM | Included | 409 | Covered Parking | 60 | 4.26MX3.10M | 13.20SQM | Included | 410 | Covered Parking | 61 | 4.26MX3.10M | 13.20SQM | Included | 411 | Covered Parking | 62 | 4.26MX3.10M | 13.20SQM | Included | 412 | Covered Parking | 63 | 4.26MX3.10M | 13.20SQM | Included | 413 | Covered Parking | 64 | 4.26MX3.10M | 13.20SQM | Included | 414 | Covered Parking | 65 | 4.26MX3.10M | 13.20SQM | Included | 415 | Covered Parking | 66 | 4.26MX3.10M | 13.20SQM | Included | 416 | Covered Parking | 67 | 4.26MX3.10M | 13.20SQM | Included | 417 | Covered Parking | 68 | 4.26MX3.10M | 13.20SQM | Included |
Particulars of Facilities | Status of the facility | Brief description of facility |
---|---|---|
Drinking Water Facility | Ground Water | Copy of Consent Letter |
Fire Fighting Facility | Yes | Staircase, Fire Extinguisher |
Emergency Evacuation Services | Yes | Staircase |
Use of Renewable Energy | No | |
Lift Facility | Yes | 1 No. lift of JET elevator/Johnson/OTIS brand of 5 person capacity with ARD facility |
Market Complex | No | |
Community Hall | Yes | 15 sqm with tile flooring |
Gymnasium | No | |
Swimming Pool | No | |
Play Ground | No | |
Park/Garden | No | |
Plantation Area | Yes | 320.84 sqm |
Others(Please Specify) | No | |
Internal Road | Yes | 3.12 M wide & 173.76 M length internal road with concrete flooring |
External Road | Yes | 12.19 sqm wide blacktop road adjacent to project plot |
Elecricity Supply | Yes | Copy of Consent Letter |
Other Amenities | No |