Generated by pacms.orera.in on date: 2024-05-17

Promoter Details
Promoter Name :
Mr SIDHARTH SEKHAR MOHAPATRA
Project Name :
"9 GRAND AVENUE"
Project Location :
over Plot no- 133/1259, Khata No.147, Mouza-Ransinghpur, P.S- Khandagiri, Tahasil-Bhubaneswar, Dist. Khordha, Odisha

Form- I

A. Promoter's Details

:  M/s. ODISHA UDYOG INFRAPROJECTS :  Partnership
:  1820201900286/2019 :View
NA :  N-3,448, IRC VILLAGE,NAYAPALLI
:  N-3, 448, IRC Village , Nayapalli, Bhubaneswar, Dist. khordha, Odisha. :  md@odishaudyog.com
:  2555007 :  9437384889
:  AAEFO0893K :View
:  10YEARS :  ODISHA
:  www.odishaudyog.in

B. Details of Board of Directors / Partners / MC Members

:  SIDHARTHA SEKHAR MOHAPATRA :  
:  Partner :  BBPPM9384N
:PAN Card :  sunny98610@yahoo.com
:  MBA :  9437384889
:  12YEARS
:  Yes :  NA
:  BIJAYALAXMI TRIPATHY :  
:  Partner :  ALNPT7980L
:PAN Card :  bijayalaxmi1213061@innovsearch.com
:  MBA :  7853962524
:  9YEARS
:  Yes :  NA

Annexure-1

Details of last projects already implemented (Ongoing or Complete)

Have you implemented any project(s) previously (May be Ongoing or Completed):No

Annexure-2

Details of the project to be registered

:   New :  "9 GRAND AVENUE"
:  Residential :  over Plot no- 133/1259, Khata No.147, Mouza-Ransinghpur, P.S- Khandagiri, Tahasil-Bhubaneswar, Dist. Khordha, Odisha
:  Khordha :  Bhubaneswar
:  751019 :  Development Authority
:  BHUBANESWAR DEVELOPMENT AUTHORITY
:  B+G+9 Multi-storied Residential Apartment Building and G+1 Storey Society-cum-club House :  NA

Land Details of the Project


:  133/1259 :  147
:  Ransinghpur :  3060.30
:  Yes
Yes :  View
:  View
:  Other Person
:  Budhi Rout, S/o Udaynath Rout & Sidha Rout, S/o Dhobei Rout :  The copy of Registered General Power of Attorney No. 41131407238 dtd. 05.12.2014 executed by the legal heir of the Recorded Tenant Budhi Rout, S/o Udaynath Rout & Sidha Rout S/o Dhobei Rout in favour of M/s ODISHA UDYOG INFRAPROJECTS, represented through its Managing Partner, Sri Sidhartha Sekhar Mohapatra With Legal Heir Certificate Attached in page no 26 & page no 27 of the General Power of Attorney copy.
: No
: Yes
:  41131407238 :  05-12-2014
:  Office of the Sub-Registrar, Khandagiri :  Attached

Development Agreement

: Yes
Serial No. Particulars of the Person Land/Plot Details Share of the Person Document Attached
1 (1) BIJAYALAXMI ROUTRAY AND 13 OTHERS 133/1259 46%   Agreement Copy

Building Plan

  View   View
  Download site plan 05-12-2021

Conditions of building plan approval

Sl. No. Description of Conditions Schedule date of compliance Present Status
1 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC/Clearances given by Fire Prevention officer/National Airport Authority/SEIAA, Ministry of Forest & Environment/PHED etc wherever applicable. 31-12-2022 under construction
2 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC/Clearances given by Fire Prevention officer/National Airport Authority/SEIAA, Ministry of Forest & Environment/PHED etc wherever applicable. 31-12-2022 under construction
3 The space which is meant for parking shall not be changed to any other use and shall not be partitioned /closed in any manner. 31-12-2022 under construction
4 20% of the parking space in group housing/apartment building shall be exclusively earmarked for ambulance, fire tender, physically handicapped persons and outside visitors with signage as per norms under Regulation. 31-12-2022 under construction
5 Plantation @ one tree per 80 Sqm of the plot area shall be made by the applicant as per provision under regulation of BDA (Planning & Building Standards) Regulations'2018. 31-12-2022 under construction
6 If the construction / development are not as per the approved plan / deviated beyond permissible norms, the performance security shall be forfeited and action shall be initiated against the applicant /builder / developer as per the provisions of the ODA Act, 1982 Rules and Regulations made there under 31-12-2022 under construction
7 The Owner/ Applicant/Architect/Structural Engineer are fully and jointly responsible for any structural failure of building due to any structural /construction defects , Authority will be no way be held responsible for the same in what so ever manner. 31-12-2022 under construction
8 The concerned Architect / Applicant / Developer are fully responsible for any deviations additions & alternations beyond approved plan/ defective construction etc. shall be liable for action as per the provisions of the Regulation. 31-12-2022 under construction
9 The applicant shall adhere the instruction /specification as per the EIDP duly vetted by CE-cum-EM., BDA. 31-12-2022 under construction
10 All the firefighting installation etc are to be ensured and maintained by the applicant as per NBC-2016. 31-12-2022 under construction
11 No storm water/water shall be discharged to the public road/public premises and other adjoining plots. 31-12-2022 under construction
12 Adhere to the provisions of BDA (Planning & Building Standards) Regulation strictly and conditions thereto. 31-12-2022 under construction
13 The Authority shall in no way be held responsible for any structural failure and damage due to earthquake/cyclone/any other natural disaster. 31-12-2022 under construction
14 The number of dwelling units so approved shall not be changed in any manner. 31-12-2022 under construction
15 The applicant shall comply the Fire Safety Recommendation of FPW as per letter No.3169 dt. 16 .11.18 31-12-2022 under construction
16 The applicant shall submit Fire Safety Clearance from FPW before issue of Occupancy Certificate. 31-12-2022 under construction
17 The applicant shall recycle 40% of the waste water generated in the project (ii) 40% of the roof area shall be utilized for Solar Power generation and adhere to the stipulation of Waste Management plan submitted for disposal of the Solid Waste 31-12-2022 under construction

Layout Plan

: Yes :  View

Location Map with geo-coordinates of bend points

Point No. Latitude Longitude
1 20°14'06.8"N 85°47'03.7"E
2 20°14'06"N 85°47'03.3"E
3 20°14'06"N 85°47'03.3"E
4 20°14'07.3"N 85°47'01.5"E
5 20°14'08.2"N 85°47'02.2"E
6 20°14'08.1"N 85°47'02.2"E
7 20°14'06.9"N 85°47'03.6"E
8 20°14'05.7''N 85°47'02.6''E
9 20°14'06.4''N 85°47'02.2''E
10 20°14'05.9''N 85°47'03.1''E
View

Milestone of Project Construction

Description* Scheduled date of completion Current Status Site Images
Site Development 31-01-2019 Work is going on
Roof Casting NA NA NA
Ground Floor/Stilt Floor 30-06-2019 work is going on
1 Floor 02-10-2019 Not Started NA
Brick Work & Plastering NA NA NA
Ground Floor/Stilt Floor 31-10-2020 Not Started NA
1 Floor 31-01-2021 Not Started NA
Electrical Works 30-08-2022 Not Started NA
Concealed Cabling including Plugs & switches 30-08-2022 Not Started NA
Installation & Charging of Transformer 31-09-2022 Not Started NA
Connection to Flats/Apartments 31-10-2022 Not Started NA
PH works 31-04-2022 Not Started NA
Laying of concealed Pipes 31-04-2022 Not Started NA
PH Fittings 30-07-2022 Not Started NA
Overhead Water Tanks 31-02-2022 Not Started NA
Water Supply Connection to all units 31-10-2022 Not Started NA
STP construction and completion 23-11-2022 Not Started NA
Distempering & Colouring of all units and exteriors 31-10-2022 Not Started NA
Fixation of doors and windows 31-09-2022 Not Started NA
Scheduled Date of handing over possession 31-12-2022 Not Started NA
Development of common areas, parks, gardens etc 15-12-2022 Not Started NA
Site Development 31-01-2019 Work is going on NA
NA NA NA NA
Ground Floor/Stilt Floor 30-06-2019 completed
1 Floor 02-10-2019 completed
NA NA NA NA
Ground Floor/Stilt Floor 31-10-2020 completed
1 Floor 31-01-2021 completed
Electrical Works 30-08-2022 Not Started NA
Concealed Cabling including Plugs & switches 30-08-2022 Not Started NA
Installation & Charging of Transformer 31-09-2022 Not Started NA
Connection to Flats/Apartments 31-10-2022 Not Started NA
PH works 31-04-2022 Not Started NA
Laying of concealed Pipes 31-04-2022 Not Started NA
PH Fittings 30-07-2022 Not Started NA
Overhead Water Tanks 31-02-2022 Not Started NA
Water Supply Connection to all units 31-10-2022 Not Started NA
STP construction and completion 23-11-2022 Not Started NA
Distempering & Colouring of all units and exteriors 31-10-2022 Not Started NA
Fixation of doors and windows 31-09-2022 Not Started NA
Scheduled Date of handing over possession 31-12-2022 Not Started NA
Development of common areas, parks, gardens etc 15-12-2022 Not Started NA
Site Development 31-01-2019 Work is going on NA
NA 12-03-2019 completed NA
Ground Floor/Stilt Floor 30-06-2019 completed NA
1 Floor 02-10-2019 completed NA
NA 28-10-2019 completed NA
Ground Floor/Stilt Floor 31-10-2020 completed NA
1 Floor 31-01-2021 completed NA
Electrical Works 30-08-2022 completed NA
Concealed Cabling including Plugs & switches 30-08-2022 completed NA
Installation & Charging of Transformer 31-09-2022 completed NA
Connection to Flats/Apartments 31-10-2022 completed NA
PH works 31-04-2022 completed NA
Laying of concealed Pipes 31-04-2022 completed NA
PH Fittings 30-07-2022 completed NA
Overhead Water Tanks 31-02-2022 completed NA
Water Supply Connection to all units 31-10-2022 completed NA
STP construction and completion 23-11-2022 completed NA
Distempering & Colouring of all units and exteriors 31-10-2022 completed NA
Fixation of doors and windows 31-09-2022 completed NA
Scheduled Date of handing over possession 31-12-2022 completed NA
Development of common areas, parks, gardens etc 15-12-2022 completed NA
Site Development 31-01-2019 Work is going on NA
NA 12-03-2019 completed NA
Ground Floor/Stilt Floor 30-06-2019 completed NA
1 Floor 02-10-2019 completed NA
NA 28-10-2019 completed NA
Ground Floor/Stilt Floor 31-10-2020 completed NA
1 Floor 31-01-2021 completed NA
Electrical Works 30-08-2022 completed NA
Concealed Cabling including Plugs & switches 30-08-2022 completed NA
Installation & Charging of Transformer 31-09-2022 completed NA
Connection to Flats/Apartments 31-10-2022 completed NA
PH works 31-04-2022 completed NA
Laying of concealed Pipes 31-04-2022 completed NA
PH Fittings 30-07-2022 completed NA
Overhead Water Tanks 31-02-2022 completed NA
Water Supply Connection to all units 31-10-2022 completed NA
STP construction and completion 23-11-2022 completed NA
Distempering & Colouring of all units and exteriors 31-10-2022 completed NA
Fixation of doors and windows 31-09-2022 completed NA
Scheduled Date of handing over possession 31-12-2022 completed NA
Development of common areas, parks, gardens etc 15-12-2022 completed NA

Category and no. of units to be developed

:  Residential
:  
:  80
:  
:  
:  
Residential Flats/ House
S. No. Flat No./ House No.

Area in square metres

Ownership
Carpet Area Balcony Area Exclusive Open Terrace Area
1 G01 69.12 3.1587 NA Land Owner
2 G02 89.00 4.2735 NA Land Owner
3 G05 69.12 3.1587 NA Land Owner
4 G06 89.00 4.2735 NA Land Owner
5 103 89.00 4.2735 NA Land Owner
6 104 69.96 2.9729 NA Land Owner
7 107 93.46 3.3445 NA Land Owner
8 108 69.96 2.9729 NA Land Owner
9 201 69.12 3.1587 NA Land Owner
10 202 89.00 4.2735 NA Land Owner
11 205 69.12 3.1587 NA Land Owner
12 206 93.46 3.3445 NA Land Owner
13 303 89.00 4.2735 NA Land Owner
14 304 69.96 2.9729 NA Land Owner
15 307 93.46 3.3445 NA Land Owner
16 308 69.96 2.9729 NA Land Owner
17 401 69.12 3.1587 NA Land Owner
18 402 89.00 4.2735 NA Land Owner
19 405 69.12 3.1587 NA Land Owner
20 406 93.46 3.3445 NA Land Owner
21 503 89.00 4.2735 NA Land Owner
22 504 69.96 2.9729 NA Land Owner
23 507 93.46 3.3445 NA Land Owner
24 508 69.96 2.9729 NA Land Owner
25 601 69.12 3.1587 NA Land Owner
26 602 89.00 4.2735 NA Land Owner
27 605 69.12 3.1587 NA Land Owner
28 606 93.46 3.3445 NA Land Owner
29 703 89.00 4.2735 NA Land Owner
30 704 69.96 2.9729 NA Land Owner
31 707 93.46 3.3445 NA Land Owner
32 708 69.96 2.9729 NA Land Owner
33 801 69.12 3.1587 NA Land Owner
34 802 89.00 4.2735 NA Land Owner
35 904 69.96 2.9729 NA Land Owner
36 907 93.46 3.3445 NA Land Owner
37 908 69.96 2.9729 NA Land Owner
38 G03 89.00 4.2735 NA Promoter
39 G04 69.96 2.9729 NA Promoter
40 G07 89.00 4.2735 NA Promoter
41 G08 69.96 2.9729 NA Promoter
42 101 69.12 3.1587 NA Promoter
43 102 89.00 4.2735 NA Promoter
44 105 69.12 3.1587 NA Promoter
45 106 93.46 3.3445 NA Promoter
46 203 89.00 4.2735 NA Promoter
47 204 69.96 2.9729 NA Promoter
48 207 93.46 3.3445 NA Promoter
49 208 69.96 2.9729 NA Promoter
50 301 69.12 3.1587 NA Promoter
51 302 89.00 4.2735 NA Promoter
52 305 69.12 3.1587 NA Promoter
53 306 93.46 3.3445 NA Promoter
54 403 89.00 4.2735 NA Promoter
55 404 69.96 2.9729 NA Promoter
56 407 93.46 3.3445 NA Promoter
57 408 69.96 2.9729 NA Promoter
58 501 69.12 3.1587 NA Promoter
59 502 89.00 4.2735 NA Promoter
60 505 69.12 3.1587 NA Promoter
61 506 93.46 3.3445 NA Promoter
62 603 89.00 4.2735 NA Promoter
63 604 69.96 2.9729 NA Promoter
64 607 93.46 3.3445 NA Promoter
65 608 69.96 2.9729 NA Promoter
66 701 69.12 3.1587 NA Promoter
67 702 89.00 4.2735 NA Promoter
68 705 69.12 3.1587 NA Promoter
69 706 93.46 3.3445 NA Promoter
70 803 89.00 4.2735 NA Promoter
71 804 69.96 2.9729 NA Promoter
72 805 69.12 3.1587 NA Promoter
73 806 93.46 3.3445 NA Promoter
74 807 93.46 3.3445 NA Promoter
75 808 69.96 2.9729 NA Promoter
76 901 69.12 3.1587 NA Promoter
77 902 89.00 4.2735 NA Promoter
78 903 89.00 4.2735 NA Promoter
79 905 69.12 3.1587 NA Promoter
80 906 93.46 3.3445 NA Promoter
Types of garages and parking
House No. Type of Garage/ Parking allotted Serial No., if any Dimension (Length x Width) in Metres Floor area in sq. metres Garage/Parking area cost is included or additional
G01 Covered Parking G01 5.652m x 2.400m 13.57sqm Included
G02 Covered Parking G02 5.652m x 2.400m 13.57sqm Included
G03 Covered Parking G03 5.651m x 2.400m 13.56sqm Included
G04 Covered Parking G04 5.651m x 2.400m 13.56sqm Included
G05 Covered Parking G05 4.496m x 2.235m 10.05sqm Included
G06 Covered Parking G06 4.496m x 2.235m 10.05sqm Included
G07 Covered Parking G07 5.486m x 2.781m 15.26sqm Included
G08 Covered Parking G08 5.486m x 2.781m 15.26sqm Included
101 Covered Parking 101 2.337m x 4.496m 10.51sqm Included
102 Covered Parking 102 2.337m x 4.496m 10.51sqm Included
103 Covered Parking 103 3.200m x 4.326m 13.84sqm Included
104 Covered Parking 104 3.150m x 4.572m 14.40sqm Included
105 Covered Parking 105 2.972m x 4.572m 13.59sqm Included
106 Covered Parking 106 5.563m x 2.400m 13.35sqm Included
107 Covered Parking 107 5.563m x 2.400m 13.35sqm Included
108 Covered Parking 108 5.563m x 2.972m 16.53sqm Included
201 Covered Parking 201 3.480m x 4.572m 15.91sqm Included
202 Covered Parking 202 2.692m x 4.572m 12.31sqm Included
203 Covered Parking 203 2.692m x 4.572m 12.31sqm Included
204 Covered Parking 204 3.581m x 4.572m 16.37sqm Included
205 Covered Parking 205 4.166m x 4.572m 19.05sqm Included
206 Covered Parking 206 5.563m x 2.972m 16.53sqm Included
207 Covered Parking 207 5.563m x 2.972m 16.53sqm Included
208 Covered Parking 208 2.972m x 4.572m 13.59sqm Included
301 Covered Parking 301 3.480m x 4.572m 15.91sqm Included
302 Covered Parking 302 2.692m x 4.572m 12.31sqm Included
303 Covered Parking 303 2.692m x 4.572m 12.31sqm Included
304 Covered Parking 304 3.480m x 4.572m 15.91sqm Included
305 Covered Parking 305 2.395m x 4.725m 11.32sqm Included
306 Covered Parking 306 3.353m x 4.725m 15.84sqm Included
307 Covered Parking 307 3.099m x 4.216m 13.07sqm Included
308 Covered Parking 308 2.565m x 5.461m 14.01sqm Included
401 Covered Parking 401 3.353m x 4.547m 15.25sqm Included
402 Covered Parking 402 3.200m x 4.547m 14.55sqm Included
403 Covered Parking 403 4.800m x 2.634m 12.64sqm Included
404 Covered Parking 404 4.800m x 2.634m 12.64sqm Included
405 Covered Parking 405 3.480m x 7.399m 25.75sqm Included
406 Covered Parking 406 4.617m x 2.743m 12.66sqm Included
407 Covered Parking 407 4.072m x 2.743m 11.17sqm Included
408 Covered Parking 408 4.636m x 3.181m 14.75sqm Included
501 Covered Parking 501 2.748m x 4.136m 11.37sqm Included
502 Covered Parking 502 2.743m x 4.412m 12.10sqm Included
503 Covered Parking 503 2.440m x 4.531m 11.06sqm Included
504 Covered Parking 504 2.743m x 4.759m 13.05sqm Included
505 Covered Parking 505 2.743m x 4.741m 13.00sqm Included
506 Covered Parking 506 3.516m x 4.735m 16.65sqm Included
507 Covered Parking 507 2.743m x 5.283m 14.49sqm Included
508 Covered Parking 508 2.743m x 5.283m 14.49sqm Included
601 Covered Parking 601 2.743m x 5.283m 14.49sqm Included
602 Covered Parking 602 2.743m x 5.283m 14.49sqm Included
603 Covered Parking 603 2.743m x 5.283m 14.49sqm Included
604 Covered Parking 604 2.743m x 5.283m 14.49sqm Included
605 Covered Parking 605 2.743m x 5.283m 14.49sqm Included
606 Covered Parking 606 2.997m x 4.780m 14.33sqm Included
607 Covered Parking 607 2.573m x 4.768m 12.27sqm Included
608 Covered Parking 608 2.573m x 4.753m 12.23sqm Included
701 Covered Parking 701 2.573m x 4.741m 12.20sqm Included
702 Covered Parking 702 2.564m x 4.726m 12.12sqm Included
703 Covered Parking 703 2.564m x 4.714m 12.09sqm Included
704 Covered Parking 704 2.564m x 4.702m 12.06sqm Included
705 Covered Parking 705 2.564m x 4.691m 12.03sqm Included
706 Covered Parking 706 5.523m x 2.821m 15.58sqm Included
707 Covered Parking 707 4.877m x 2.743m 13.38sqm Included
708 Covered Parking 708 4.877m x 2.743m 13.38sqm Included
801 Covered Parking 801 4.877m x 2.743m 13.38sqm Included
802 Covered Parking 802 4.877m x 2.743m 13.38sqm Included
803 Covered Parking 803 4.877m x 2.743m 13.38sqm Included
804 Covered Parking 804 4.877m x 2.160m 10.53sqm Included
805 Covered Parking 805 2.463m x 4.670m 11.50sqm Included
806 Covered Parking 806 2.745m x 4.710m 12.93sqm Included
807 Covered Parking 807 2.745m x 4.790m 13.15sqm Included
808 Covered Parking 808 2.743m x 4.844m 13.29sqm Included
901 Covered Parking 901 2.743m x 4.835m 13.26sqm Included
902 Covered Parking 902 2.743m x 4.824m 13.23sqm Included
903 Covered Parking 903 2.607m x 4.839m 12.62sqm Included
904 Covered Parking 904 2.743m x 4.600m 12.62sqm Included
905 Covered Parking 905 2.743m x 4.877m 13.38sqm Included
906 Covered Parking 906 2.743m x 4.877m 13.38sqm Included
907 Covered Parking 907 2.743m x 4.877m 13.38sqm Included
908 Covered Parking 908 2.743m x 4.595m 12.60sqm Included
Yes

Facilities to be provided

Particulars of Facilities Status of the facility Brief description of facility
Drinking Water Facility Ground Water Copy of Consent Letter
Fire Fighting Facility Yes SPRINKLERS IN BASEMENT,LANDING VALVE WITH HOSE REEL , ALARAMING SYSTEM, FIRE EXTINGUISHERS,HEAT DETECTION SYSTEM IN BASEMENT, SIGNAGES
Emergency Evacuation Services Yes Rescue landings and Signages
Use of Renewable Energy Yes solar system
Lift Facility Yes 03 NOS OF LIFTS, SCHINDLER LIFTS, VR SYSTEM, AUTOMATIC SS LIFTS, 2 NOS OF 6 PERSONS, AND 01 NOS FIRE LIFT(2.997 M * 1.62 M)
Market Complex No
Community Hall Yes GROUND FLOOR-105.72 SQ. MT
Gymnasium Yes 92.61 SQ. MT.
Swimming Pool No
Play Ground No
Park/Garden No
Plantation Area Yes 400SQM
Others(Please Specify) No
Internal Road Yes 6.0 MTR DRIVEWAY
External Road No
Elecricity Supply Yes Copy of Consent Letter
Other Amenities No ProjectFacility_857938568_1547015432.pdf

Bank Particulars of the Project

  DCB Bank Limited
  Bhubaneswar
  16723900000019
  DCBL0000167
   View
  2570133
  7853962524

Particulars of Architect/Construction Engineer/Contractor/Chartered Accountant

Name position Address with mobile number and email address Registration number Key real estate projects Is active Effective date
DEBRAJ BEHERA Architect SAHIDNAGAR, Bhubaneswar, Contacy No- 9437443333, Mail ID-alcoveconsultancy@gmail.com CA2004/33719 TATA ARIANA(LOCAL ARCHITECT), HYATT BHUBANESWAR, RAVI SHANKER UNIVERSITY, HOTEL SWAMY RESORTS, ITC WELCOME GROUP. Yes
Amitabh Sahu (Batra And Swain Associates F. No.-322050E) Chartered Accountant 409/410,Forum Mart,89,Kharabela Nagar,bbsr-751001, contact No- M. No.-064676 Adak Heights,Adak Infrastructures Pvt. Ltd. Yes
Umakanta Jena Construction Engineer 109/2106, Shastri Nagar, Unit IV, Bhubaneswar-751001 RTP/DTP (ST. Er.) 027/2017 Neha Palace(MKNK Constructions Pvt. Ltd.) , Hotel Swosti Premium No 09-09-2019
FAKIR MOHON PRADHAN Construction Engineer PLOT NO-536(P), Mahatab Road, Old Town, Bhubaneswar-751002 F0900601090 Hotel Vineeth's Bhubaneswar Yes

Financial Details

:  2223 :   View
  31-12-2022 :  550
:  773 :  900

Documents Attached

Description of Document Option Documents
Fire Safety Certificate Undertaking Attached
Affidavit in Form-A as per clause-l of sub-section-2 of section-4 of the Act Yes Attached
Allotment letter format Yes Attached
Conveyance Deed Format Yes Attached
Affidavit to adopt agreement for sale format as per Rule-8(1) of ORE (R and D) Rules, 2017 Yes Attached
Annual Report 2017-18 Attached
IT Return 2017-18 Attached
Audit Report 2017-18 Attached


Other documents

Sl No Document Name Attached File
1 Allotment Letter:   View
“I undertake that the information submitted by me in this application are correct and true to best my knowledge. I also understand that providing false or wrong information is punishable under the Section-60 of the Real Estate (Regulation & Development) Act, 2016. I also further understand that furnishing wrong or false information will lead to rejection of my application registration of the project with forfeiture of registration fee and other charges deposited by me.”
  Sir, as per your queries, we have submitted all the details and documents.And I would like request you to allow us an ORERA approval which would help us delivering intending purchasers/buyers their dream home in the stipulated time given to us by BDA and ORERA.

Construction Progress

Updated Construction Progress

SL NO. Description Scheduled date of completion Current Status Remarks
1 Site Development 31-01-2019 Work is going on
2 Roof Casting NA NA NA
3 Ground Floor/Stilt Floor 30-06-2019 work is going on
4 1 Floor 02-10-2019 Not Started NA
5 Brick Work & Plastering NA NA NA
6 Ground Floor/Stilt Floor 31-10-2020 Not Started NA
7 1 Floor 31-01-2021 Not Started NA
8 Electrical Works 30-08-2022 Not Started NA
9 Concealed Cabling including Plugs & switches 30-08-2022 Not Started NA
10 Installation & Charging of Transformer 31-09-2022 Not Started NA
11 Connection to Flats/Apartments 31-10-2022 Not Started NA
12 PH works 31-04-2022 Not Started NA
13 Laying of concealed Pipes 31-04-2022 Not Started NA
14 PH Fittings 30-07-2022 Not Started NA
15 Overhead Water Tanks 31-02-2022 Not Started NA
16 Water Supply Connection to all units 31-10-2022 Not Started NA
17 STP construction and completion 23-11-2022 Not Started NA
18 Distempering & Colouring of all units and exteriors 31-10-2022 Not Started NA
19 Fixation of doors and windows 31-09-2022 Not Started NA
20 Scheduled Date of handing over possession 31-12-2022 Not Started NA
21 Development of common areas, parks, gardens etc 15-12-2022 Not Started NA
Updated Changes on 22-11-2020
22 Site Development 31-01-2019 Work is going on NA
23 NA NA NA NA
24 Ground Floor/Stilt Floor 30-06-2019 completed
25 1 Floor 02-10-2019 completed
26 NA NA NA NA
27 Ground Floor/Stilt Floor 31-10-2020 completed
28 1 Floor 31-01-2021 completed
29 Electrical Works 30-08-2022 Not Started NA
30 Concealed Cabling including Plugs & switches 30-08-2022 Not Started NA
31 Installation & Charging of Transformer 31-09-2022 Not Started NA
32 Connection to Flats/Apartments 31-10-2022 Not Started NA
33 PH works 31-04-2022 Not Started NA
34 Laying of concealed Pipes 31-04-2022 Not Started NA
35 PH Fittings 30-07-2022 Not Started NA
36 Overhead Water Tanks 31-02-2022 Not Started NA
37 Water Supply Connection to all units 31-10-2022 Not Started NA
38 STP construction and completion 23-11-2022 Not Started NA
39 Distempering & Colouring of all units and exteriors 31-10-2022 Not Started NA
40 Fixation of doors and windows 31-09-2022 Not Started NA
41 Scheduled Date of handing over possession 31-12-2022 Not Started NA
42 Development of common areas, parks, gardens etc 15-12-2022 Not Started NA
Updated Changes on 15-07-2023
43 Site Development 31-01-2019 Work is going on NA
44 NA 12-03-2019 completed NA
45 Ground Floor/Stilt Floor 30-06-2019 completed NA
46 1 Floor 02-10-2019 completed NA
47 NA 28-10-2019 completed NA
48 Ground Floor/Stilt Floor 31-10-2020 completed NA
49 1 Floor 31-01-2021 completed NA
50 Electrical Works 30-08-2022 completed NA
51 Concealed Cabling including Plugs & switches 30-08-2022 completed NA
52 Installation & Charging of Transformer 31-09-2022 completed NA
53 Connection to Flats/Apartments 31-10-2022 completed NA
54 PH works 31-04-2022 completed NA
55 Laying of concealed Pipes 31-04-2022 completed NA
56 PH Fittings 30-07-2022 completed NA
57 Overhead Water Tanks 31-02-2022 completed NA
58 Water Supply Connection to all units 31-10-2022 completed NA
59 STP construction and completion 23-11-2022 completed NA
60 Distempering & Colouring of all units and exteriors 31-10-2022 completed NA
61 Fixation of doors and windows 31-09-2022 completed NA
62 Scheduled Date of handing over possession 31-12-2022 completed NA
63 Development of common areas, parks, gardens etc 15-12-2022 completed NA
Updated Changes on 15-07-2023
64 Site Development 31-01-2019 Work is going on NA
65 NA 12-03-2019 completed NA
66 Ground Floor/Stilt Floor 30-06-2019 completed NA
67 1 Floor 02-10-2019 completed NA
68 NA 28-10-2019 completed NA
69 Ground Floor/Stilt Floor 31-10-2020 completed NA
70 1 Floor 31-01-2021 completed NA
71 Electrical Works 30-08-2022 completed NA
72 Concealed Cabling including Plugs & switches 30-08-2022 completed NA
73 Installation & Charging of Transformer 31-09-2022 completed NA
74 Connection to Flats/Apartments 31-10-2022 completed NA
75 PH works 31-04-2022 completed NA
76 Laying of concealed Pipes 31-04-2022 completed NA
77 PH Fittings 30-07-2022 completed NA
78 Overhead Water Tanks 31-02-2022 completed NA
79 Water Supply Connection to all units 31-10-2022 completed NA
80 STP construction and completion 23-11-2022 completed NA
81 Distempering & Colouring of all units and exteriors 31-10-2022 completed NA
82 Fixation of doors and windows 31-09-2022 completed NA
83 Scheduled Date of handing over possession 31-12-2022 completed NA
84 Development of common areas, parks, gardens etc 15-12-2022 completed NA

Booking Status

Residential Flats/ House
S. No. Flat No./ House No.

Area in square metres

Ownership Status
Carpet Area Balcony Area Exclusive Open Terrace Area
1 G01 69.12 3.1587 NA Land Owner
2 G02 89.00 4.2735 NA Land Owner
3 G05 69.12 3.1587 NA Land Owner
4 G06 89.00 4.2735 NA Land Owner
5 103 89.00 4.2735 NA Land Owner
6 104 69.96 2.9729 NA Land Owner
7 107 93.46 3.3445 NA Land Owner
8 108 69.96 2.9729 NA Land Owner
9 201 69.12 3.1587 NA Land Owner
10 202 89.00 4.2735 NA Land Owner
11 205 69.12 3.1587 NA Land Owner
12 206 93.46 3.3445 NA Land Owner
13 303 89.00 4.2735 NA Land Owner
14 304 69.96 2.9729 NA Land Owner
15 307 93.46 3.3445 NA Land Owner
16 308 69.96 2.9729 NA Land Owner
17 401 69.12 3.1587 NA Land Owner
18 402 89.00 4.2735 NA Land Owner
19 405 69.12 3.1587 NA Land Owner
20 406 93.46 3.3445 NA Land Owner
21 503 89.00 4.2735 NA Land Owner
22 504 69.96 2.9729 NA Land Owner
23 507 93.46 3.3445 NA Land Owner
24 508 69.96 2.9729 NA Land Owner
25 601 69.12 3.1587 NA Land Owner
26 602 89.00 4.2735 NA Land Owner
27 605 69.12 3.1587 NA Land Owner
28 606 93.46 3.3445 NA Land Owner
29 703 89.00 4.2735 NA Land Owner
30 704 69.96 2.9729 NA Land Owner
31 707 93.46 3.3445 NA Land Owner
32 708 69.96 2.9729 NA Land Owner
33 801 69.12 3.1587 NA Land Owner
34 802 89.00 4.2735 NA Land Owner
35 904 69.96 2.9729 NA Land Owner
36 907 93.46 3.3445 NA Land Owner
37 908 69.96 2.9729 NA Land Owner
38 G03 89.00 4.2735 NA Promoter
39 G04 69.96 2.9729 NA Promoter
40 G07 89.00 4.2735 NA Promoter
41 G08 69.96 2.9729 NA Promoter
42 101 69.12 3.1587 NA Promoter
43 102 89.00 4.2735 NA Promoter
44 105 69.12 3.1587 NA Promoter
45 106 93.46 3.3445 NA Promoter
46 203 89.00 4.2735 NA Promoter
47 204 69.96 2.9729 NA Promoter
48 207 93.46 3.3445 NA Promoter
49 208 69.96 2.9729 NA Promoter
50 301 69.12 3.1587 NA Promoter
51 302 89.00 4.2735 NA Promoter
52 305 69.12 3.1587 NA Promoter
53 306 93.46 3.3445 NA Promoter
54 403 89.00 4.2735 NA Promoter
55 404 69.96 2.9729 NA Promoter
56 407 93.46 3.3445 NA Promoter
57 408 69.96 2.9729 NA Promoter
58 501 69.12 3.1587 NA Promoter
59 502 89.00 4.2735 NA Promoter
60 505 69.12 3.1587 NA Promoter
61 506 93.46 3.3445 NA Promoter
62 603 89.00 4.2735 NA Promoter
63 604 69.96 2.9729 NA Promoter
64 607 93.46 3.3445 NA Promoter
65 608 69.96 2.9729 NA Promoter
66 701 69.12 3.1587 NA Promoter
67 702 89.00 4.2735 NA Promoter
68 705 69.12 3.1587 NA Promoter
69 706 93.46 3.3445 NA Promoter
70 803 89.00 4.2735 NA Promoter
71 804 69.96 2.9729 NA Promoter
72 805 69.12 3.1587 NA Promoter
73 806 93.46 3.3445 NA Promoter
74 807 93.46 3.3445 NA Promoter
75 808 69.96 2.9729 NA Promoter
76 901 69.12 3.1587 NA Promoter
77 902 89.00 4.2735 NA Promoter
78 903 89.00 4.2735 NA Promoter
79 905 69.12 3.1587 NA Promoter
80 906 93.46 3.3445 NA Promoter

Financial Status

SL No. Funds Collected from the Allottees Funds Borrowed from Financial Institutions Funds Employed from Own Sources Expenditure As On Date Status
1 87270951 0 0 71518573 20-11-2020 fourth floor roof casting
2 0 0 0 0 30-06-2023 Construction work completed. Awaiting for Occupancy Certificate from BDA, documents attached for perusal.
3 0 0 0 30-06-2023 Construction work completed. Awaiting for Occupancy Certificate from BDA, documents attached for perusal.

Updated Conditions of building plan approval

Sl. No. Description of Conditions Schedule date of compliance Present Status
1 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC/Clearances given by Fire Prevention officer/National Airport Authority/SEIAA, Ministry of Forest & Environment/PHED etc wherever applicable. 31-12-2022 under construction
2 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC/Clearances given by Fire Prevention officer/National Airport Authority/SEIAA, Ministry of Forest & Environment/PHED etc wherever applicable. 31-12-2022 under construction
3 The space which is meant for parking shall not be changed to any other use and shall not be partitioned /closed in any manner. 31-12-2022 under construction
4 20% of the parking space in group housing/apartment building shall be exclusively earmarked for ambulance, fire tender, physically handicapped persons and outside visitors with signage as per norms under Regulation. 31-12-2022 under construction
5 Plantation @ one tree per 80 Sqm of the plot area shall be made by the applicant as per provision under regulation of BDA (Planning & Building Standards) Regulations'2018. 31-12-2022 under construction
6 If the construction / development are not as per the approved plan / deviated beyond permissible norms, the performance security shall be forfeited and action shall be initiated against the applicant /builder / developer as per the provisions of the ODA Act, 1982 Rules and Regulations made there under 31-12-2022 under construction
7 The Owner/ Applicant/Architect/Structural Engineer are fully and jointly responsible for any structural failure of building due to any structural /construction defects , Authority will be no way be held responsible for the same in what so ever manner. 31-12-2022 under construction
8 The concerned Architect / Applicant / Developer are fully responsible for any deviations additions & alternations beyond approved plan/ defective construction etc. shall be liable for action as per the provisions of the Regulation. 31-12-2022 under construction
9 The applicant shall adhere the instruction /specification as per the EIDP duly vetted by CE-cum-EM., BDA. 31-12-2022 under construction
10 All the firefighting installation etc are to be ensured and maintained by the applicant as per NBC-2016. 31-12-2022 under construction
11 No storm water/water shall be discharged to the public road/public premises and other adjoining plots. 31-12-2022 under construction
12 Adhere to the provisions of BDA (Planning & Building Standards) Regulation strictly and conditions thereto. 31-12-2022 under construction
13 The Authority shall in no way be held responsible for any structural failure and damage due to earthquake/cyclone/any other natural disaster. 31-12-2022 under construction
14 The number of dwelling units so approved shall not be changed in any manner. 31-12-2022 under construction
15 The applicant shall comply the Fire Safety Recommendation of FPW as per letter No.3169 dt. 16 .11.18 31-12-2022 under construction
16 The applicant shall submit Fire Safety Clearance from FPW before issue of Occupancy Certificate. 31-12-2022 under construction
17 The applicant shall recycle 40% of the waste water generated in the project (ii) 40% of the roof area shall be utilized for Solar Power generation and adhere to the stipulation of Waste Management plan submitted for disposal of the Solid Waste 31-12-2022 under construction
Updated Changes on 21-11-2020
18 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC/Clearances given by Fire Prevention officer/National Airport Authority/SEIAA, Ministry of Forest & Environment/PHED etc wherever applicable. 31-12-2022 Done
19 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC/Clearances given by Fire Prevention officer/National Airport Authority/SEIAA, Ministry of Forest & Environment/PHED etc wherever applicable. 31-12-2022 Done
20 The space which is meant for parking shall not be changed to any other use and shall not be partitioned /closed in any manner. 31-12-2022 Done
21 20% of the parking space in group housing/apartment building shall be exclusively earmarked for ambulance, fire tender, physically handicapped persons and outside visitors with signage as per norms under Regulation. 31-12-2022 Done
22 Plantation @ one tree per 80 Sqm of the plot area shall be made by the applicant as per provision under regulation of BDA (Planning & Building Standards) Regulations'2018. 31-12-2022 under construction
23 If the construction / development are not as per the approved plan / deviated beyond permissible norms, the performance security shall be forfeited and action shall be initiated against the applicant /builder / developer as per the provisions of the ODA Act, 1982 Rules and Regulations made there under 31-12-2022 Done
24 The Owner/ Applicant/Architect/Structural Engineer are fully and jointly responsible for any structural failure of building due to any structural /construction defects , Authority will be no way be held responsible for the same in what so ever manner. 31-12-2022 Done
25 The concerned Architect / Applicant / Developer are fully responsible for any deviations additions & alternations beyond approved plan/ defective construction etc. shall be liable for action as per the provisions of the Regulation. 31-12-2022 Done
26 The applicant shall adhere the instruction /specification as per the EIDP duly vetted by CE-cum-EM., BDA. 31-12-2022 Done
27 All the firefighting installation etc are to be ensured and maintained by the applicant as per NBC-2016. 31-12-2022 under construction
28 No storm water/water shall be discharged to the public road/public premises and other adjoining plots. 31-12-2022 Done
29 Adhere to the provisions of BDA (Planning & Building Standards) Regulation strictly and conditions thereto. 31-12-2022 Done
30 The Authority shall in no way be held responsible for any structural failure and damage due to earthquake/cyclone/any other natural disaster. 31-12-2022 Done
31 The number of dwelling units so approved shall not be changed in any manner. 31-12-2022 Done
32 The applicant shall comply the Fire Safety Recommendation of FPW as per letter No.3169 dt. 16 .11.18 31-12-2022 Done
33 The applicant shall submit Fire Safety Clearance from FPW before issue of Occupancy Certificate. 31-12-2022 Done
34 The applicant shall recycle 40% of the waste water generated in the project (ii) 40% of the roof area shall be utilized for Solar Power generation and adhere to the stipulation of Waste Management plan submitted for disposal of the Solid Waste 31-12-2022 Done
Updated Changes on 15-07-2023
35 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC/Clearances given by Fire Prevention officer/National Airport Authority/SEIAA, Ministry of Forest & Environment/PHED etc wherever applicable. 31-12-2022 Done
36 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC/Clearances given by Fire Prevention officer/National Airport Authority/SEIAA, Ministry of Forest & Environment/PHED etc wherever applicable. 31-12-2022 Done
37 The space which is meant for parking shall not be changed to any other use and shall not be partitioned /closed in any manner. 31-12-2022 Done
38 20% of the parking space in group housing/apartment building shall be exclusively earmarked for ambulance, fire tender, physically handicapped persons and outside visitors with signage as per norms under Regulation. 31-12-2022 Done
39 Plantation @ one tree per 80 Sqm of the plot area shall be made by the applicant as per provision under regulation of BDA (Planning & Building Standards) Regulations'2018. 31-12-2022 Done
40 If the construction / development are not as per the approved plan / deviated beyond permissible norms, the performance security shall be forfeited and action shall be initiated against the applicant /builder / developer as per the provisions of the ODA Act, 1982 Rules and Regulations made there under 31-12-2022 Done
41 The Owner/ Applicant/Architect/Structural Engineer are fully and jointly responsible for any structural failure of building due to any structural /construction defects , Authority will be no way be held responsible for the same in what so ever manner. 31-12-2022 Done
42 The concerned Architect / Applicant / Developer are fully responsible for any deviations additions & alternations beyond approved plan/ defective construction etc. shall be liable for action as per the provisions of the Regulation. 31-12-2022 Done
43 The applicant shall adhere the instruction /specification as per the EIDP duly vetted by CE-cum-EM., BDA. 31-12-2022 Done
44 All the firefighting installation etc are to be ensured and maintained by the applicant as per NBC-2016. 31-12-2022 Done
45 No storm water/water shall be discharged to the public road/public premises and other adjoining plots. 31-12-2022 Done
46 Adhere to the provisions of BDA (Planning & Building Standards) Regulation strictly and conditions thereto. 31-12-2022 Done
47 The Authority shall in no way be held responsible for any structural failure and damage due to earthquake/cyclone/any other natural disaster. 31-12-2022 Done
48 The number of dwelling units so approved shall not be changed in any manner. 31-12-2022 Done
49 The applicant shall comply the Fire Safety Recommendation of FPW as per letter No.3169 dt. 16 .11.18 31-12-2022 Done
50 The applicant shall submit Fire Safety Clearance from FPW before issue of Occupancy Certificate. 31-12-2022 Done
51 The applicant shall recycle 40% of the waste water generated in the project (ii) 40% of the roof area shall be utilized for Solar Power generation and adhere to the stipulation of Waste Management plan submitted for disposal of the Solid Waste 31-12-2022 Done
Updated Changes on 15-07-2023
52 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC/Clearances given by Fire Prevention officer/National Airport Authority/SEIAA, Ministry of Forest & Environment/PHED etc wherever applicable. 31-12-2022 Done
53 The owner/applicant/Technical Person shall strictly adhere to the terms and conditions imposed in the NOC/Clearances given by Fire Prevention officer/National Airport Authority/SEIAA, Ministry of Forest & Environment/PHED etc wherever applicable. 31-12-2022 Done
54 The space which is meant for parking shall not be changed to any other use and shall not be partitioned /closed in any manner. 31-12-2022 Done
55 20% of the parking space in group housing/apartment building shall be exclusively earmarked for ambulance, fire tender, physically handicapped persons and outside visitors with signage as per norms under Regulation. 31-12-2022 Done
56 Plantation @ one tree per 80 Sqm of the plot area shall be made by the applicant as per provision under regulation of BDA (Planning & Building Standards) Regulations'2018. 31-12-2022 Done
57 If the construction / development are not as per the approved plan / deviated beyond permissible norms, the performance security shall be forfeited and action shall be initiated against the applicant /builder / developer as per the provisions of the ODA Act, 1982 Rules and Regulations made there under 31-12-2022 Done
58 The Owner/ Applicant/Architect/Structural Engineer are fully and jointly responsible for any structural failure of building due to any structural /construction defects , Authority will be no way be held responsible for the same in what so ever manner. 31-12-2022 Done
59 The concerned Architect / Applicant / Developer are fully responsible for any deviations additions & alternations beyond approved plan/ defective construction etc. shall be liable for action as per the provisions of the Regulation. 31-12-2022 Done
60 The applicant shall adhere the instruction /specification as per the EIDP duly vetted by CE-cum-EM., BDA. 31-12-2022 Done
61 All the firefighting installation etc are to be ensured and maintained by the applicant as per NBC-2016. 31-12-2022 Done
62 No storm water/water shall be discharged to the public road/public premises and other adjoining plots. 31-12-2022 Done
63 Adhere to the provisions of BDA (Planning & Building Standards) Regulation strictly and conditions thereto. 31-12-2022 Done
64 The Authority shall in no way be held responsible for any structural failure and damage due to earthquake/cyclone/any other natural disaster. 31-12-2022 Done
65 The number of dwelling units so approved shall not be changed in any manner. 31-12-2022 Done
66 The applicant shall comply the Fire Safety Recommendation of FPW as per letter No.3169 dt. 16 .11.18 31-12-2022 Done
67 The applicant shall submit Fire Safety Clearance from FPW before issue of Occupancy Certificate. 31-12-2022 Done
68 The applicant shall recycle 40% of the waste water generated in the project (ii) 40% of the roof area shall be utilized for Solar Power generation and adhere to the stipulation of Waste Management plan submitted for disposal of the Solid Waste 31-12-2022 Done

Updated Project Documents

Sl. No. Title of the document Upload Document
1 NOC GROUND WATER
2 NOC GROUND WATER
3 Additional Share Allocation agreement
4 Additional Share Allocation agreement
5 Agreement for Sale -GIRISH CHANDRA NAYAK
6 Agreement for Sale-Ranjit Kumar Mishra
7 Agreement for Sale-Ranjit Kumar Mohanty
8 Agreement for Sale-Shivani Patra
9 Building Photo
10 Building Photo
11 Building Photo
12 Building Photo
13 Building Photo
14 Building Photo
15 9 GRAND Application for OC
16 Bank Challan copy for OC
:  SIDHARTHA SEKHAR MOHAPATRA :  
NA :  BBPPM9384N
:PAN Card :  sunny98610@yahoo.com
:  MBA :  9437384889
:  12YEARS
:  Yes :  NA
:  BIJAYALAXMI TRIPATHY :  
NA :  ALNPT7980L
:PAN Card :  bijayalaxmi1213061@innovsearch.com
:  MBA :  7853962524
:  9YEARS
:  Yes :  NA

Particulars of Architect/Construction Engineer/Contractor/Chartered Accountant

Name position Address with mobile number and email address Registration number Key real estate projects Is active Effective date
DEBRAJ BEHERA Architect SAHIDNAGAR, Bhubaneswar, Contacy No- 9437443333, Mail ID-alcoveconsultancy@gmail.com CA2004/33719 TATA ARIANA(LOCAL ARCHITECT), HYATT BHUBANESWAR, RAVI SHANKER UNIVERSITY, HOTEL SWAMY RESORTS, ITC WELCOME GROUP. Yes
Amitabh Sahu (Batra And Swain Associates F. No.-322050E) Chartered Accountant 409/410,Forum Mart,89,Kharabela Nagar,bbsr-751001, contact No- M. No.-064676 Adak Heights,Adak Infrastructures Pvt. Ltd. Yes
Umakanta Jena Construction Engineer 109/2106, Shastri Nagar, Unit IV, Bhubaneswar-751001 RTP/DTP (ST. Er.) 027/2017 Neha Palace(MKNK Constructions Pvt. Ltd.) , Hotel Swosti Premium No 09-09-2019
FAKIR MOHON PRADHAN Construction Engineer PLOT NO-536(P), Mahatab Road, Old Town, Bhubaneswar-751002 F0900601090 Hotel Vineeth's Bhubaneswar Yes

Updated Units

House No. Type of Garage/ Parking allotted Serial No., if any Dimension (Length x Width) in Metres Floor area in sq. metres Garage/Parking area cost is included or additional
G01 Covered Parking G01 5.652m x 2.400m 13.57sqm Included
G02 Covered Parking G02 5.652m x 2.400m 13.57sqm Included
G03 Covered Parking G03 5.651m x 2.400m 13.56sqm Included
G04 Covered Parking G04 5.651m x 2.400m 13.56sqm Included
G05 Covered Parking G05 4.496m x 2.235m 10.05sqm Included
G06 Covered Parking G06 4.496m x 2.235m 10.05sqm Included
G07 Covered Parking G07 5.486m x 2.781m 15.26sqm Included
G08 Covered Parking G08 5.486m x 2.781m 15.26sqm Included
101 Covered Parking 101 2.337m x 4.496m 10.51sqm Included
102 Covered Parking 102 2.337m x 4.496m 10.51sqm Included
103 Covered Parking 103 3.200m x 4.326m 13.84sqm Included
104 Covered Parking 104 3.150m x 4.572m 14.40sqm Included
105 Covered Parking 105 2.972m x 4.572m 13.59sqm Included
106 Covered Parking 106 5.563m x 2.400m 13.35sqm Included
107 Covered Parking 107 5.563m x 2.400m 13.35sqm Included
108 Covered Parking 108 5.563m x 2.972m 16.53sqm Included
201 Covered Parking 201 3.480m x 4.572m 15.91sqm Included
202 Covered Parking 202 2.692m x 4.572m 12.31sqm Included
203 Covered Parking 203 2.692m x 4.572m 12.31sqm Included
204 Covered Parking 204 3.581m x 4.572m 16.37sqm Included
205 Covered Parking 205 4.166m x 4.572m 19.05sqm Included
206 Covered Parking 206 5.563m x 2.972m 16.53sqm Included
207 Covered Parking 207 5.563m x 2.972m 16.53sqm Included
208 Covered Parking 208 2.972m x 4.572m 13.59sqm Included
301 Covered Parking 301 3.480m x 4.572m 15.91sqm Included
302 Covered Parking 302 2.692m x 4.572m 12.31sqm Included
303 Covered Parking 303 2.692m x 4.572m 12.31sqm Included
304 Covered Parking 304 3.480m x 4.572m 15.91sqm Included
305 Covered Parking 305 2.395m x 4.725m 11.32sqm Included
306 Covered Parking 306 3.353m x 4.725m 15.84sqm Included
307 Covered Parking 307 3.099m x 4.216m 13.07sqm Included
308 Covered Parking 308 2.565m x 5.461m 14.01sqm Included
401 Covered Parking 401 3.353m x 4.547m 15.25sqm Included
402 Covered Parking 402 3.200m x 4.547m 14.55sqm Included
403 Covered Parking 403 4.800m x 2.634m 12.64sqm Included
404 Covered Parking 404 4.800m x 2.634m 12.64sqm Included
405 Covered Parking 405 3.480m x 7.399m 25.75sqm Included
406 Covered Parking 406 4.617m x 2.743m 12.66sqm Included
407 Covered Parking 407 4.072m x 2.743m 11.17sqm Included
408 Covered Parking 408 4.636m x 3.181m 14.75sqm Included
501 Covered Parking 501 2.748m x 4.136m 11.37sqm Included
502 Covered Parking 502 2.743m x 4.412m 12.10sqm Included
503 Covered Parking 503 2.440m x 4.531m 11.06sqm Included
504 Covered Parking 504 2.743m x 4.759m 13.05sqm Included
505 Covered Parking 505 2.743m x 4.741m 13.00sqm Included
506 Covered Parking 506 3.516m x 4.735m 16.65sqm Included
507 Covered Parking 507 2.743m x 5.283m 14.49sqm Included
508 Covered Parking 508 2.743m x 5.283m 14.49sqm Included
601 Covered Parking 601 2.743m x 5.283m 14.49sqm Included
602 Covered Parking 602 2.743m x 5.283m 14.49sqm Included
603 Covered Parking 603 2.743m x 5.283m 14.49sqm Included
604 Covered Parking 604 2.743m x 5.283m 14.49sqm Included
605 Covered Parking 605 2.743m x 5.283m 14.49sqm Included
606 Covered Parking 606 2.997m x 4.780m 14.33sqm Included
607 Covered Parking 607 2.573m x 4.768m 12.27sqm Included
608 Covered Parking 608 2.573m x 4.753m 12.23sqm Included
701 Covered Parking 701 2.573m x 4.741m 12.20sqm Included
702 Covered Parking 702 2.564m x 4.726m 12.12sqm Included
703 Covered Parking 703 2.564m x 4.714m 12.09sqm Included
704 Covered Parking 704 2.564m x 4.702m 12.06sqm Included
705 Covered Parking 705 2.564m x 4.691m 12.03sqm Included
706 Covered Parking 706 5.523m x 2.821m 15.58sqm Included
707 Covered Parking 707 4.877m x 2.743m 13.38sqm Included
708 Covered Parking 708 4.877m x 2.743m 13.38sqm Included
801 Covered Parking 801 4.877m x 2.743m 13.38sqm Included
802 Covered Parking 802 4.877m x 2.743m 13.38sqm Included
803 Covered Parking 803 4.877m x 2.743m 13.38sqm Included
804 Covered Parking 804 4.877m x 2.160m 10.53sqm Included
805 Covered Parking 805 2.463m x 4.670m 11.50sqm Included
806 Covered Parking 806 2.745m x 4.710m 12.93sqm Included
807 Covered Parking 807 2.745m x 4.790m 13.15sqm Included
808 Covered Parking 808 2.743m x 4.844m 13.29sqm Included
901 Covered Parking 901 2.743m x 4.835m 13.26sqm Included
902 Covered Parking 902 2.743m x 4.824m 13.23sqm Included
903 Covered Parking 903 2.607m x 4.839m 12.62sqm Included
904 Covered Parking 904 2.743m x 4.600m 12.62sqm Included
905 Covered Parking 905 2.743m x 4.877m 13.38sqm Included
906 Covered Parking 906 2.743m x 4.877m 13.38sqm Included
907 Covered Parking 907 2.743m x 4.877m 13.38sqm Included
908 Covered Parking 908 2.743m x 4.595m 12.60sqm Included

Generated by pacms.orera.in on date: 2024-05-17