Generated by pacms.orera.in on date: 2024-05-20
: ACPL Builders Pvt. Ltd. | : Private Company |
: U45201OR2010PTC011756 | :View |
NA | : JAILROAD |
: JAILROAD | : acpl_bls@yahoo.com |
: 7381444488 | : 9439395058 |
: AAICA3543M | :View |
: 9YEARS OF EXPERIENCE IN CONSTRUCTION OF FLATS | : ORISSA |
: www.acplbuilders.com |
: sangeeta mohanty | : |
: Director | : BNWPM7513C |
:PAN Card | : acpl_bls@yahoo.com |
: B-arch | : 7381444888 |
: 8 YEARS OF EXP | |
: Yes | : NA |
: MANOJ KUMAR MOHANTY | : |
: Managing Director | : ACHPM9617Q |
:PAN Card | : monoj_mohanty@yahoo.co.in |
: Bachelor in Engineering | : 9439395058 |
: 38 YEARS EXPERIENCE | |
: Yes | : NA |
: swapna mohanty | : |
: Director | : ADPPM1143A |
:PAN Card | : acpl_bls@yahoo.com |
: GRADUATE IN ARTS | : 7381444488 |
: 9 YEARS OF EXPERIENCE | |
: Yes | : NA |
: New | : ACPL FORTUNE |
: Residential | : BAHSKARGANJ , UNIT NO. 10 , BALASORE 756001 |
: Baleswar | : Baleswar MPL |
: 756001 | : Regional Improvement Trust |
: BRIT & MUNICIPALITY | |
: G+4 | : NA |
: No |
View | View |
Download site plan | 24-04-2022 |
NA |
Point No. | Latitude | Longitude |
---|---|---|
1 | 21°29'46'.04'' | 86°55'10.64'' |
2 | 21°29'45.90'' | 86°55'10.94'' |
3 | 21°29'45.53'' | 86°55'10.65'' |
4 | 21°29'46.67'' | 86°55'10.47'' |
Description* | Scheduled date of completion | Current Status | Site Images |
---|---|---|---|
Site Development | 21-09-2019 | Ongoing | NA |
Roof Casting | NA | NA | NA |
Ground Floor/Stilt Floor | 20-09-2019 | Complete | NA |
1 Floor | 22-10-2019 | Complete | NA |
2 Floor | 25-11-2019 | Complete | NA |
3 Floor | 28-12-2019 | Complete | NA |
4 Floor | 28-01-2020 | Complete | NA |
Brick Work & Plastering | NA | NA | NA |
Ground Floor/Stilt Floor | 10-11-2019 | Complete | NA |
1 Floor | 18-12-2019 | Complete | NA |
2 Floor | 21-01-2020 | Complete | NA |
3 Floor | 24-02-2020 | ongoing | NA |
4 Floor | 18-03-2020 | yet to start | NA |
Electrical Works | 14-04-2020 | yet to start | NA |
Concealed Cabling including Plugs & switches | 14-08-2020 | yet to start | NA |
Installation & Charging of Transformer | 09-02-2021 | yet to start | NA |
Connection to Flats/Apartments | 22-03-2021 | yet to start | NA |
PH works | 15-11-2020 | yet to start | NA |
Laying of concealed Pipes | 11-11-2020 | yet to start | NA |
PH Fittings | 04-11-2020 | yet to start | NA |
Overhead Water Tanks | 01-08-2020 | yet to start | NA |
Water Supply Connection to all units | 12-01-2021 | yet to start | NA |
STP construction and completion | 01-03-2021 | ongoing | NA |
Distempering & Colouring of all units and exteriors | 01-05-2021 | yet to start | NA |
Fixation of doors and windows | 09-09-2020 | yet to start | NA |
Scheduled Date of handing over possession | 24-02-2022 | yet to start | NA |
Development of common areas, parks, gardens etc | 29-12-2021 | yet to start | NA |
: Residential | |
: 12
|
|
Residential Flats/ House | |||||
---|---|---|---|---|---|
S. No. | Flat No./ House No. | ||||
Area in square metres |
Ownership | ||||
Carpet Area | Balcony Area | Exclusive Open Terrace Area | |||
1 | 101 | 67.09 | 4.16 | Divided equally among all the 12 Flat owners | Promoter |
2 | 102 | 65.00 | 2.85 | Divided equally among all the 12 Flat owners | Promoter |
3 | 103 | 88.21 | 6.25 | Divided equally among all the 12 Flat owners | Promoter |
4 | 201 | 67.09 | 4.16 | Divided equally among all the 12 Flat owners | Promoter |
5 | 202 | 65.00 | 2.85 | Divided equally among all the 12 Flat owners | Promoter |
6 | 203 | 88.21 | 6.25 | Divided equally among all the 12 Flat owners | Promoter |
7 | 301 | 67.09 | 4.16 | Divided equally among all the 12 Flat owners | Promoter |
8 | 302 | 65.00 | 2.85 | Divided equally among all the 12 Flat owners | Promoter |
9 | 303 | 88.21 | 6.25 | Divided equally among all the 12 Flat owners | Promoter |
10 | 401 | 67.09 | 4.16 | Divided equally among all the 12 Flat owners | Promoter |
11 | 402 | 65.00 | 2.85 | Divided equally among all the 12 Flat owners | Promoter |
12 | 403 | 88.21 | 6.25 | Divided equally among all the 12 Flat owners | Promoter |
Types of garages and parking | ||||||
---|---|---|---|---|---|---|
House No. | Type of Garage/ Parking allotted | Serial No., if any | Dimension (Length x Width) in Metres | Floor area in sq. metres | Garage/Parking area cost is included or additional | |
101 | Covered Parking | 01 | 4.57 X 2.31 | 10.55 | Included | 102 | Covered Parking | 02 | 4.57 X 2.31 | 10.55 | Included | 103 | Covered Parking | 03 | 4.57 X 2.31 | 10.55 | Included | 201 | Covered Parking | 04 | 4.57 X 2.31 | 10.55 | Included | 202 | Covered Parking | 05 | 4.57 X 2.31 | 10.55 | Included | 203 | Covered Parking | 06 | 4.57 X 2.31 | 10.55 | Included | 301 | Covered Parking | 07 | 4.57 X 2.31 | 10.55 | Included | 302 | Covered Parking | 08 | 4.57 X 2.31 | 10.55 | Included | 303 | Covered Parking | 09 | 4.57 X 2.31 | 10.55 | Included | 401 | Covered Parking | 10 | 4.57 X 2.31 | 10.55 | Included | 402 | Covered Parking | 11 | 4.57 X 2.31 | 10.55 | Included | 403 | Covered Parking | 12 | 4.57 X 2.31 | 10.55 | Included |
Particulars of Facilities | Status of the facility | Brief description of facility |
---|---|---|
Drinking Water Facility | Ground Water | Copy of Consent Letter |
Fire Fighting Facility | Yes | EACH FLOOR HAS 4KGS OF ABC PRESSED POWDER CYLINDER |
Emergency Evacuation Services | No | |
Use of Renewable Energy | No | |
Lift Facility | Yes | 1 NO OF BRANDED LIFT HAVING CAPACITY OF 5 PASSENGERS |
Market Complex | No | |
Community Hall | Yes | 11.25 sqm |
Gymnasium | No | |
Swimming Pool | No | |
Play Ground | No | |
Park/Garden | No | |
Plantation Area | Yes | 101.51 Sqm |
Others(Please Specify) | No | |
Internal Road | Yes | 28.37 x 3 = 85.13 Square Meters |
External Road | No | |
Elecricity Supply | Yes | Copy of Consent Letter |
Other Amenities | No |
Generated by pacms.orera.in on date: 2024-05-20